OTC Pres Project Del P5 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Jeff Gower, State Construction.

Slides:



Advertisements
Similar presentations
Metro Muncipal Agreement Program
Advertisements

Stewardship Oversight Committee Project Delivery Design & Construction Performance Measures May 2012.
LPA Projects LPA projects Alum Creek Bike Trail $3,200,000 Parsons/Livingston $14,500,000 Riversouth Phase $9,900,000 Lane Avenue $1,700,000 Arcadia.
Bob Smith, P.E. Region 1 Benjamin Acimovic, P.E., Region 1
Presented by: Fouad Al-Malazi ID No.: Managing Construction Contracts By Robert D. Gilbreath Chapter 1 CONSTRUCTION CONTRACTS: Roles and Relationships.
Global Congress Global Leadership Vision for Project Management.
City of Eugene Certification Project Case Study. Why Did Eugene Get Certified? Can’t do fund exchange ODOT's Local Agency Program More project control.
How to Submit a Winning Bid for State Goods & Services Corinna Cooper, CPPB Contracts Consultant May 22, 2014.
Joe White (608) Wayne Chase (608) WisDOT Materials Management Section 1.
OTIA III State Bridge Delivery Program CEI Tool Ron Reisdorf, PE Senior Construction Engineer Oregon Department of Transportation April 9, 2008.
“TI” Ohhhh….. (TIO) (No TIO is not a person!) What is it all about?
NEW YORK STATE DEPARTMENT OF TRANSPORTATION South Cascade Drive/Miller Road (Formerly Route 219)/ Cattaraugus Creek Design-Build Project (PIN ,
12-May-151 Khan Younis Waste Water Treatment Plant Management Arrangements Khan Younis Waste Water Treatment Plant Management Arrangements.
Department of Transportation Support Services Branch ODOT Procurement Office Intergovernmental Agreements 455 Airport Rd. SE, Bldg K Salem, OR
Community Facility Loans/Grants Architect Flow Chart Owner has need for project. RD Area Office is contacted. RD visits project site and discusses project.
THE PROJECT TEAM TYPICAL REQUIREMENTS AND RESPONSIBILITIES OF THE PROJECT TEAM TRADITIONAL TEAM ORGANIZATION AND VARIATIONS THE OWNER’S TEAM THE DESIGN.
PROCEDURES FOR SELECTING THE CONTRACTOR
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Route 110 over Route 27 Design-Build Project (PIN , D900027) Town of Babylon, Suffolk County Request.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Interstate 81 Bridges over Route 80 Design-Build Project (PIN , D900023) Town of Tully, Onondaga County.
Project Delivery Overview June 2015 Final PD Training FMD WUSM 6/15/15 1.
CVE 1000 Construction Engineering The Project Delivery System Prof. Ralph V. Locurcio, PE.
AASHTO Subcommittee on Construction
MyFloridaMarketPlace Roundtable August 20, 2003 MyFloridaMarketPlace.
This Presentation is a Copyrighted Property of Waller S. Poage, AIA, CSI, MAI, CVS – All Rights are Reserved Session CDT 01 – Fundamentals Lesson CDT 1.3.
Construction Management: At Risk. PROJECT MANAGEMENT STRUCTURE: Contractual Relationships Owner Architect/Engineer General Contractor Sub Construction.
Improving Understanding, Function and Procedural DBE Compliance ODOT OCR DBE Triage Training Office of Civil Rights DBE Program ODOT Training March 1,
Commissioning of Fire Protection and Life Safety Systems Presented by: Charles Kilfoil Bechtel National Waste Treatment Plant Richland WA.
CEM 520 Construction Contracting Dr S. Almohawis Course Content.
Kenneth D. Fenton P.S. Clark County Engineer’s Office.
HIGHWAY/UTILITY PROGRAM OVERVIEW ROADWAY CONFERENCE APRIL 20, 2009.
CVE 4070 Construction Engineering Test-2 & Review Prof. Ralph V. Locurcio, PE.
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Superstructure and Bridge Replacements in Region 9 Design-Build Project (PIN , D900020) Broome, Delaware,
NEW YORK STATE DEPARTMENT OF TRANSPORTATION Superstructure and Bridge Replacements in Regions 2 & 9 Design-Build Project (PIN , D900022) Herkimer,
New York State Department of Transportation Accelerated Bridge Program Phase 1B Design-Build Projects Request for Proposals Informational Meeting April.
Genesee County Road Commission Fred Peivandi, P.E. County Highway Engineer MTPA July 15, 2011 TIP Project Administration.
Local Government Section Welcome Marty Andersen ODOT Local Government Section 355 Capitol Street NE, Rm. 326 Salem, Oregon Ph:
Contractor / Engineer Conference 2010 Dispute Resolution Process Dispute Resolution Process.
Procurement Authority Representative Roles and Responsibilities Amanda Price, Program Development Coordinator, Planning and Programming, Transportation.
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
CONSTRUCTION ADMINISTRATION Measurement and Payment Dr. Alaattin Kanoğlu Spring, 2013 Professional Practice Management I.B.U. Architecture Undergraduate.
Agency Construction Management :CM NOT AT-RISK
Conformance & Documentation Services Copyright © 2009 Sleighter Engineering, Inc.
Change Orders. CO Proposals Initiated by owner or GC –Owner requests estimate for work proposed –GC CO results from changed site condition or response.
Construction Eng 221 Project Management and Administration.
American Recovery and Reinvestment Act of 2009 Energy Efficiency and Conservation Block Grant Program Small City and County Grant Kick-Off Meeting California.
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
OTC Pres: Bid & Award Phase 4 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Eryca McCartin, Office.
UNIVERSITY OF DAR ES SALAAM t Selection and Employment of Consultants Negotiations with Consultants; Monitoring Performance of Consultants; Resolving Disputes.
Project Delivery Performance Improvement Report to the Oregon Transportation Commission Hal Gard, Technical Services, Geo-Environmental Dee Jones, Technical.
1 1 Effective Administration of Commercial Contracts Breakout Session # Session D06 Name: Holly Walker, CPCM Corporate Learning Solutions and Contract.
PRE-PLANNING FOR CONSTRUCTION PROJECTS. OVERVIEW ASSESSING OWNER CAPABILITIES ANALYSIS OF RESOURCES REGULATORY REQUIREMENTS SITE DEVELOPMENT REVIEWING.
Introduction to Procurement for Public Housing Authorities Getting Started: Basic Administrative Requirements Unit 1.
Dallas Area Rapid Transit Pre-Bid Conference Solicitation No. B Bus stop Amenity Cleaning April 13, 2016.
CHANGE ORDER/CLAIMS MANAGEMENT MODULE 9. Change Order Management.
Role & Responsibility for Quality Assurance What is your opinion on this topic heading? Role and Responsibility of: Role and Responsibility of….(Er.) for.
QUALITY ASSURANCE MODULE 3. Definitions Quality Assurance - A process/effort that ensures that processes are followed, that the processes of doing right.
Metra Construction Contractor Prevailing Wage Workshop
CONTRACT ADMINISTRATION
Resident Engineer Training
Construction Oversight
Pre-Construction Services
State Aid Construction
Oral statements or discussion during the Pre-Bid Meeting will not be binding, nor will they change or affect the IFB or the terms or conditions within.
Emulsion Task Force Meeting
Quality Assurance for Emulsified Asphalt Surface Treatments
Controlling Project Cost and Schedule
Centralization of Texas State Contract Compliance Functions
Department Of Energy Review Linac Coherent Light Source Project
State Aid Construction
Construction Management Services April 16, 2018
Presentation transcript:

OTC Pres Project Del P5 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Jeff Gower, State Construction & Materials Engineer December 10, 2008 Construction Construction Management – Phase 5

OTC Pres Project Del P5 12/08 Page 2 Project Delivery Process

OTC Pres Project Del P5 12/08 Page 3 Construction Duration: 6 months – 4 years Contract management Quality Assurance Environmental Compliance Work Force Monitoring Dispute/Claims resolution process Payment Final documentation Stakeholder Involvement

OTC Pres Project Del P5 12/08 Page 4 Construction Begins Contractor supplies materials and performs work according to contract and plans for construction Agency makes sure the contractor completes work as contracted

OTC Pres Project Del P5 12/08 Page 5 Contract Management Project Manager What they do – Project Manager assigned to administer each contract – Assure compliance with contract requirements – Manage contract within construction authorization – Negotiate changes as necessary – Communicate with stakeholders

OTC Pres Project Del P5 12/08 Page 6 Contract Management Inspectors / Testers What they do –Inspectors assigned to monitor and document progress –Monitor quality, quantity, workmanship –Central Materials Lab – AASHTO Materials Reference Library - Certified –Materials staff monitor quality of materials

OTC Pres Project Del P5 12/08 Page 7 Quality Assurance/Quality Control (QA/QC) All test equipment and lab facilities certified by ODOT Central Lab All testing technicians certified by ODOT Construction QA Unit Contractor provides Quality Control testing at specified frequencies. ODOT Region Construction QA staff verify contractor results on random basis.

OTC Pres Project Del P5 12/08 Page 8 Discrepancies must be investigated and resolved Dispute resolution testing by Central Lab Fabrication Inspection at plant Central Lab provides specialized materials testing Construction Section provides specialized support Quality Assurance/Quality Control (QA/QC)

OTC Pres Project Del P5 12/08 Page 9 Contract Management Other roles in Construction Office staff to coordinate documentation and process payment Construction Section provides support and statewide consistency.

OTC Pres Project Del P5 12/08 Page 10 Environmental Compliance Require contractor submittal of plans prior to starting work. Inspectors monitor compliance to plans and permits daily. Region Environmental Coordinators review progress and provide assistance regularly. Regulatory Agencies visit projects occasionally.

OTC Pres Project Del P5 12/08 Page 11 Work Force Monitoring Review Contractor submitted payrolls for compliance to prevailing wage monthly. Track progress of Contractor in meeting: - Workforce diversity goals - DBE Participation goals - Apprenticeship goals

OTC Pres Project Del P5 12/08 Page 12 Contract Management Delegated Change Order Authority - Project Manager $100,000 & 14 Days - Area Manager $250,000 & 30 Days - Region Manager $250,000 & 30 Days - Contract Administration Engineer/Chief Engineer Anything above

OTC Pres Project Del P5 12/08 Page 13 Contract Management Delegated overrun in Authorization Authorities - Project Manager None - Area Manager $250,000 - Region Manager $500,000 - Oregon Transportation Commission Unlimited

OTC Pres Project Del P5 12/08 Page 14 Change Order Process (Approximately 1500 per year) PM Identifies need for Contract Change Order (CCO) PM develops details of CCO with Engineer of Record and Contractor PM negotiates cost of CCO PM gets necessary approvals for CCO PM executes CCO

OTC Pres Project Del P5 12/08 Page 15 Payment Monthly Estimate by 8 th of each month Progress Payment to Prime by 23 rd of each month All payments require Quality/Quantity documentation Price Adjustments made for: - Non-specification materials - Changed work - Incentive/Disincentives - Material price escalation (Steel, fuel, asphalt) Retainage of 2.5% held until final acceptance

OTC Pres Project Del P5 12/08 Page 16 Dispute/Claims Resolution Process PM performs initial evaluation/resolution of any dispute Use Third Party Neutral (Non-Binding) Claim Process: - PM Review - Region Level Review - Agency Level Review - Arbitration (Less than $25,000) - Claim Review Board - Litigation

OTC Pres Project Del P5 12/08 Page 17 Final Documentation & Acceptance On site work completed Acceptance of Project Completed Project Contact with Motor Carrier on any restrictions

OTC Pres Project Del P5 12/08 Page 18 Construction Program Risks Material Price Escalation Changing Field Conditions Material Availability Variability in Materials & Workmanship Outsourcing Construction Engineering

OTC Pres Project Del P5 12/08 Page 19 Stakeholder Involvement Daily communication with Contractor by PM staff. Frequent communications with effected local agencies and local businesses. Frequent communications with effected residences. Regular contact with impacted regulatory agencies. Regular contact with impacted utilities and rail road. Monthly meetings with Industry to work global issues.

OTC Pres Project Del P5 12/08 Page 20 Costs PhaseModernizationBridgePreservationSafety/Ops Planning9.1%5.2%0.4%3.0% Design9.1%5.4%6.7%13.0% RoW / Utility Relocation3.4%1.3%1.6%4.5% Bid & Award0.1% 0.2%0.8% Construction Engineering6.7% 6.1%9.1% Construction71.6%81.3%85.0%69.6% Total (%)100.0%

OTC Pres Project Del P5 12/08 Page 21 Key Performance Measures # 20 Jobs from Construction Spending ( , – 12,500) #22 Construction Timeliness ( % 2007 – 69%) #23 Construction on Budget (2006 – 73% 2007 – 48%) #24 Certified Businesses (2004 – 11.3% 2007 – 12.9%)

OTC Pres Project Del P5 12/08 Page 22 Other Construction Program Measures Volume of Contractor Payments (2002 – $251 mil $520 mil) Unsettled Claims ( $27 mil $15 mil) % Authorization Expended (2002 – 103.5% 2007 – 99.8%) % Construction Engineering (2002 – 7.8% 2007 – 8.1%)

OTC Pres Project Del P5 12/08 Page 23 Continuous Improvements Technician Certification Program Inspector Certification Program PM Training for ODOT & Consultants Web Based Contract Payment System Contractor Evaluations Change Order Database Statewide Leadership Team

OTC Pres Project Del P5 12/08 Page 24 Discussion