LIGO-G000335-00-D Commissioning at Hanford Stan Whitcomb Program Advisory Committee 12 December 2000 LIGO Livingston Observatory.

Slides:



Advertisements
Similar presentations
September 21, 2005Virgo Status – ESF Workshop1 Status of Virgo B. Mours.
Advertisements

Cascina, January 25th, Coupling of the IMC length noise into the recombined ITF output Raffaele Flaminio EGO and CNRS/IN2P3 Summary - Recombined.
G R LIGO Laboratory1 Advanced LIGO Research and Development David Shoemaker LHO LSC 11 November 2003.
LIGO-G D Detector Installation and Commissioning Stan Whitcomb NSF Annual Review 30 April 2001 Caltech.
1 Virgo commissioning status M.Barsuglia LAL Orsay.
1 Science Opportunities for Australia Advanced LIGO Barry Barish Director, LIGO Canberra, Australia 16-Sept-03 LIGO-G M.
LIGO-G W Status of LIGO Installation and Commissioning Frederick J. Raab, LIGO Hanford Observatory.
LIGO-G0200XX-00-M LIGO Laboratory1 Pre-Isolation Dennis Coyne LIGO Laboratory NSF LIGO Annual Review, at MIT 23 October 2002.
LIGO-G9900XX-00-M LIGO Status and Plans Barry Barish 5 June 2000 Gravitational Waves: A Challenge to Theoretical Astrophysics Trieste, 5-9 June 2000.
Status of the LIGO Project
LIGO-G D partial ADVANCED LIGO1 Development Plan R&D including Design through Final Design Review »for all long lead or high risk subsystems »LIGO.
Laser Interferometer Gravitational-wave Observatory1 Characterization of LIGO Input Optics University of Florida Thomas Delker Guido Mueller Malik Rakhmanov.
LIGO-G9900XX-00-M LIGO Status and Plans Barry Barish March 13, 2000.
LIGO-G M April 5, 2006 Interferometer Sensing and Control (ISC) Cost and Schedule Breakout Presentation NSF Review of Advanced LIGO Project Richard.
Advanced LIGO Commissioning Overview Stanford LVC Meeting, August 27, 2014 Peter Fritschel.
LIGO-G D Commissioning PAC11, 2001 Daniel Sigg, LIGO Hanford Observatory.
LIGO-G W Status of LIGO Installation and Commissioning Frederick J. Raab, LIGO Hanford Observatory.
Max-Planck-Institut für Gravitationsphysik (Albert-Einstein-Institut) Institut für Atom- und Molekülphysik Detector Characterization of GEO 600 during.
LIGO-G D Installation and Commissioning Status Stan Whitcomb Program Advisory Committee 14 June 2001 Caltech.
Joshua Smith December 2003 Detector Characterization of Dual-Recycled GEO600 Joshua Smith for the GEO600 team.
The GEO 600 Detector Andreas Freise for the GEO 600 Team Max-Planck-Institute for Gravitational Physics University of Hannover May 20, 2002.
LIGO-G M Management of the LIGO Project Gary Sanders California Institute of Technology Presented to the Committee on Programs and Plans of the.
LIGO- G D Status of LIGO Stan Whitcomb ACIGA Workshop 21 April 2004.
G Amaldi Meeting 2015, Gwangju, South Korea1 Status of LIGO June 22, 2015 Daniel Sigg LIGO Hanford Observatory (on behalf of the LIGO Scientific.
LIGO-G D The LIGO-I Gravitational-wave Detectors Stan Whitcomb CaJAGWR Seminar February 16, 2001.
LIGO- G D The LIGO Instruments Stan Whitcomb NSB Meeting LIGO Livingston Observatory 4 February 2004.
LIGO-G D “First Lock” for the LIGO Detectors 20 October 2000 LIGO Hanford Observatory Stan Whitcomb.
1 Virgo commissioning: Next steps December 12 st 2005 Hannover, ILIAS-GWA WG1 Matteo Barsuglia, LAL/CNRS.
LIGO-G D Commissioning, Part II PAC 12, June 2002 Peter Fritschel, LIGO MIT.
LIGO-G D What can we Expect for the “Upper Limit” Run Stan Whitcomb LSC Meeting 13 August 2001 LIGO Hanford Observatory A Personal Reading of.
LIGO-G M LIGO Status Report Barry Barish LSC Meeting - Hanford 14 Aug 01.
LIGO-G D LSC Meeting Nov An Early Glimpse at the S3 Run Stan Whitcomb (LIGO–Caltech) LIGO Scientific Collaboration Meeting LIGO Hanford.
Lisa Barsotti - University and INFN Pisa – on behalf of the Virgo Collaboration CASCINA - January 24 th, 2005 ILIAS  Locking of Full Virgo Status of VIRGO.
Status of VIRGO Lisa Barsotti - University and INFN Pisa – on behalf of the VIRGO collaboration ANNECY - December 15 th, 2004  Status of the Commissioning.
Initial and Advanced LIGO Detectors
LIGO-G D 1 Status of Detector Commissioning LSC Meeting, March 2001 Nergis Mavalvala California Institute of Technology.
The status of VIRGO Edwige Tournefier (LAPP-Annecy ) for the VIRGO Collaboration HEP2005, 21st- 27th July 2005 The VIRGO experiment and detection of.
1 Virgo Commissioning Status WG1 meeting Potsdam, 21 st July 2006.
LIGO-G W LIGO Detector Commissioning Reported on behalf of LIGO colleagues by Fred Raab, LIGO Hanford Observatory.
LIGO- G D E7: An Instrument-builder’s Perspective Stan Whitcomb LIGO Caltech LSC Meeting Upper Limits Plenary Session 22 May 2002 LIGO Livingston.
Paolo La Penna ILIAS N5-WP1 meeting Commissioning Progress Hannover, July 2004 VIRGO commissioning progress report.
LIGO- G M Paths to Improving Detector Performance Rainer Weiss, David Shoemaker NSF Review Caltech, 30 April 2001.
International Gravitational Wave Network 11/9/2008 Building an Stefan Ballmer, for the LIGO / VIRGO Scientific Collaboration LIGO G
LIGO-G M LIGO Status Gary Sanders GWIC Meeting Perth July 2001.
Initial and Advanced LIGO Status Gregory Harry LIGO/MIT March 24, 2006 March 24, th Eastern Gravity Meeting G R.
LIGO-G D Detector Installation and Commissioning Stan Whitcomb NSF Operations Review 26 February 2001 LIGO Hanford Observatory.
LIGO-G D “Bi-linear” Noise Mechanisms in Interferometers Stan Whitcomb LIGO/Caltech GWDAW 15 December 2000.
The Status of Advanced LIGO: Light at the end of the Tunnels Jeffrey S. Kissel, for the LIGO Scientific Collaboration April APS Meeting, Savannah, GA April.
Caltech, February 12th1 Virgo central interferometer: commissioning and engineering runs Matteo Barsuglia Laboratoire de l’Accelerateur Lineaire, Orsay.
LIGO G M Intro to LIGO Seismic Isolation Pre-bid meeting Gary Sanders LIGO/Caltech Stanford, April 29, 2003.
LIGO-G Z Report on E3/E4 Lock Losses K. Riles - University of Michigan 1 Report on E3/E4 Lock Losses David Chin, Dick Gustafson Keith.
ALIGO 0.45 Gpc 2014 iLIGO 35 Mpc 2007 Future Range to Neutron Star Coalescence Better Seismic Isolation Increased Laser Power and Signal Recycling Reduced.
LIGO- G M LIGO Status Stan Whitcomb Oversight Committee 20 October 2004.
LIGO-G D Commissioning P Fritschel LIGO NSF review, 23 October 2002 M.I.T.
1 The status of VIRGO E. Tournefier LAPP(Annecy)-IN2P3-CNRS Journées SF2A, Strasbourg 27 juin – 1er juillet 2005 The VIRGO experiment The commissioning.
Page 1 Coles – Operating the Observatories PAC 9 Dec. 13, 2000 G L Operating the Observatories Mark Coles.
Virgo Status Detector Status Computing Data Analysis status and Plans
Status report of Polarization RSE
Installation and Commissioning Status Stan Whitcomb
Nergis Mavalvala MIT IAU214, August 2002
Virgo Update B. Mours LIGO-G Z August 15, 2006 LSC meeting.
Commissioning the LIGO detectors
LIGO Detector Commissioning
Status of LIGO Installation and Commissioning
LIGO Detector Commissioning
Virgo Update – LSC meeting
The Laser Interferometer Gravitational-Wave Observatory
Improving LIGO’s stability and sensitivity: commissioning examples
Arm Length Stabilization at LHO
Status at the Prague meeting
Presentation transcript:

LIGO-G D Commissioning at Hanford Stan Whitcomb Program Advisory Committee 12 December 2000 LIGO Livingston Observatory

LIGO-G D LIGO PAC Meeting 2 Installation Summary All in-vacuum installation complete for LHO 2km ASC and LSC electronics installed for 2 km interferometer, and under test Delayed installation of 4km LHO interferometer pending solution to scattered light problem »Seismic isolation complete »PSL installation underway »In-vacuum optics scheduled for early 2001 DAQ/Control Network infrastructure complete »Generally reliable, but still a few minor problem areas »Still verifying correct signal hook-ups

LIGO-G D LIGO PAC Meeting 3 First Lock for a LIGO Interferometer Laser end test mass Light bounces back and forth along arms about 100 times input test mass Light is “recycled” about 50 times signal Requires test masses to be held in position to meter (atomic diameter) “Locking the interferometer”

LIGO-G D LIGO PAC Meeting 4 Steps to Locking the Interferometer signal Laser X Arm Y Arm Composite Video

LIGO-G D LIGO PAC Meeting 5 Watching the Interferometer Lock signal X Arm Y Arm Laser

LIGO-G D LIGO PAC Meeting 6 Full Interferometer Locking Still a bit tenuous……. 2 Minutes Locked Unlocked

LIGO-G D LIGO PAC Meeting 7 Recombined Michelson with F-P Arms signal X Arm Y Arm Laser Misaligning the Recycling Mirror simplifies the control system More robust lock facilitates some types of noise investigation

LIGO-G D LIGO PAC Meeting 8 Recombined Interferometer Spectrum Factor of 10 5 – 10 6 improvement required

LIGO-G D LIGO PAC Meeting 9 Beginning to Work on Noise Identified electronics noise (ADC) as dominant noise at high frequencies (due to low input laser power) Laser frequency noise dominates in mid frequency band (stabilization from arm common mode not yet implemented) Low frequencies seismic noise? Many resonant features to investigate and eliminate

LIGO-G D LIGO PAC Meeting 10 Cont. to Work on Subsystem Performance Example: Prestabilized Laser Laser stability an important contributor to LIGO sensitivity Steady improvement in laser noise performance »electronics »acoustics »vibrations »elimination of excitation sources Required

LIGO-G D LIGO PAC Meeting 11 Progress Toward Robust Operation Different measure of interferometer performance (in contrast with sensitivity) »Interferometer lock duration goal is 40 hours, Prestabilized laser »Two years continuous operation with ~20% loss in power »Locks to reference cavity and premodecleaner for months Mode Cleaner »Locks for weeks at a time, reacquires lock in few seconds Data Acquisition and Control »Data Acquisition and IOCs (Input Output Controllers) routinely operate for weeks-to-months without problems »Tools in place for tracking machine state: AutoBURT, Conlog

LIGO-G D LIGO PAC Meeting 12 Extending the Lock on a Single Arm Change to X Arm »2/12/00 18 minutes lock »3/4/00 90 minutes lock »3/26/00 10 hours lock Start with Y Arm »12/1/99 Flashes of light »12/9/ seconds lock »1/14/00 2 seconds lock »1/19/00 60 seconds lock »1/21/00 5 minutes lock Laser Result of : -automatic alignment system -tuning electronics -reduction of noise sources 2 km Arm

LIGO-G D LIGO PAC Meeting 13 Recombined Michelson Robustness Locked Unlocked Y Arm X Arm Randomly chosen hour from recent engineering run

LIGO-G D LIGO PAC Meeting 14 Engineering Runs Engineering Runs are a key part of our commissioning plan »Test interferometer stability, reliability »Well defined dataset for off-site analysis »Develop procedures for later operations »Means to include the broader LSC in detector commissioning First Engineering Run (E1) in April 2000 »Single arm operation with wavefront sensing alignment »24 hour duration »Lots of interest and good intentions, but rather limited follow- through on planned analysis

LIGO-G D LIGO PAC Meeting 15 Second Engineering Run (E2) November 2000 »One week of around the clock operation »Approximately 35 scientists participated on site Recombined Michelson with Fabry-Perot arms »Misaligned recycling mirror to make for more robust locking »Typical locked stretches 30 – 90 minutes (longest ~ 3 hours) »>90% duty cycle Organized around 14 detector investigations »Earthtides, frequency noise, calibration, noise stationarity, seismic noise, noise bursts, line tracking, … »More analysis during the run than for entire E1 Major test of DAQ system »Successfully transferred 2 terabytes of data to CACR archive

LIGO-G D LIGO PAC Meeting 16 Earthtide Investigation Observed in earlier E1 Run, but predictions had unexplained time shift ~200 micons P-to-P Main cause of loss of lock for long arms in E2 run Input to design of tidal actuator needed for eventual long lock durations Common mode (both arms stretch together) and differential mode (arms stretch by different amounts)

LIGO-G D LIGO PAC Meeting 17 Summary “Locking the Interferometer” marks a major transition for LIGO »Commissioning a full interferometer, not individual subsystems “First Lock” in the Hanford Observatory control room Steady Progress Locking duration Noise performance Operational experience Still a long way to go!