ATLAS Pixel Detector September 2002 N. Hartman LBNL 1 Pixel Support Tube: Cost and Production Schedule September 2002.

Slides:



Advertisements
Similar presentations
SCT BARREL PAR - RAL May 2003 Status of Barrel Mechanical Structures - Cylinder manufacture - Bracket and small components manufacture - Dry assembly.
Advertisements

HFT PXL Mechanical WBS 1.2 March 2010 Howard Wieman LBNL 1.
Fixturing operations for PXL 1 models: MSC.SLDASM MSC_fixtured.SLDASM rail_test_system.SLDASM 2/24/2010.
ATLAS Pixel Detector September 2002 N. Hartman LBNL 1 Pixel Support Tube: Design, Prototyping, and Production PST Progress Update September 2002.
ATLAS Pixel Detector February 2003 N. Hartman LBNL 1 Pixel Support Tube PRR: Assembly, Production, Schedule February 2003.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 14, 2009.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
ATLAS Pixel Detector October 2001 Pixel Week N. Hartman LBNL 1 PST Design Update PST CDR october 2001.
HFT PXL Mechanical July 2010 Howard Wieman LBNL 1.
M. Gilchriese Mechanics Labor and Disk Sectors US Pixel Meeting November 2001.
ATLAS Pixel Detector September 2002 A. Das LBNL 1 Pixel Support Tube Rails: Design and Prototyping September, Review.
RF Cavity / Coupling Coil Module
ATLAS Pixel Detector July 2003 ETC ‘04 E. Anderssen LBNL BPSS and Service Panels Santa Cruz, CA E Anderssen LBNL.
M. Gilchriese Status Report Sectors, Rings, Frame December 2002.
Engineering Division 1 PHENIX Vertex Tracker Production Status and Schedule Eric Anderssen, LBNL.
+ STAR HFT Upgrade – Installation and Integration Rahul Sharma Brookhaven National Laboratory.
ATLAS Pixel Detector Pixel Support Tube Interfaces LBNL Internal PST Review E. Anderssen, LBNL.
FEBRUARY 2003 Pixel Support Tube A. Smith LBNL 1 ATLAS Pixel Support Tube PRR: Parts Pixel Support Tube Production Readiness Review Parts Overview Alexis.
J A Hill – EID RAL 1-2 September EE End Cap Mechanical Design ECAL EE End Cap Engineering CMS-UK Collaboration Meeting Brunel University September.
Ron Madaras, LBL U.S. Pixel Meeting, SCIPP, July 9-10, 2003 Patch Panel 1 (PP1) Brief Review Cost and Effort Estimate.
ATLAS Pixel Detector JULY 2001 Pixel Support Tube N. Hartman LBNL 1 Pixel Support Tube Concept and Design N. Hartman, E. Anderssen, G. Gilchriese, S. Dardin.
DOE/NSF Review of the U.S. ATLAS Construction Project June 3-4, 2002 WBS 1.1 Silicon Subsystem Abe Seiden UC Santa Cruz.
Silicon Inner Layer Sensor PRR, 8 August G. Ginther Update on the D0 Run IIb Silicon Upgrade for the Inner Layer Sensor PRR 8 August 03 George Ginther.
L. Greiner 1IPHC meeting – May 7, 2012 STAR HFT Plans for the next year A short report on HFT/PXL plans for post May 2012 TPC – Time Projection Chamber.
ATLAS Pixel Detector June 2002 PST FDR N. Hartman LBNL 1 Pixel Support Tube: Design and Prototyping PST Final Design Review June 2002.
Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.
ATLAS Pixel Detector Project N. Hartman LBNL 1 Alexis Smith Intern Progress Report Neal Hartman, March 25, 2003.
1 US Pixel Mechanics Role Global support structureIntermediate support structureLocal support structure Stave SectorDisk Barrel x (9-11) x5 x (22,40,56)
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese U.S. ATLAS Review Revised Version November 29, 2000.
News on mechanics Photon veto F. Raffaelli INFN – Sezione di Pisa CERN, January r 02 th, Status of tender Anti Status of the supporting.
M. Gilchriese Overview of Production Plan for Pixel Global Support and Disk Support Rings M. G. D. Gilchriese Lawrence Berkeley National Laboratory February.
M. Gilchriese Sectors, Rings, Frame Assembly and Installation July 18.
ATLAS Pixel Detector February 2002 Cooling Services Connections N. Hartman LBNL Cooling Connections Status Report: LBNL Effort February, 2002 N. Hartman,
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese Revised Version December 18, 2000.
GLAST LAT Project DOE/NASA Review, March 31, GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager
1 Pixel Detector General –July Evidence of galvanic corrosion in EU barrel cooling tubes. Recovery plan implemented, this problem now solved but…..
M. Gilchriese U.S. Pixel Mechanics Overview M. G. D. Gilchriese Lawrence Berkeley National Laboratory April 2000.
M. Gilchriese Disk Sector Production Pixel Local Supports Production Readiness Review.
DOE/NSF Review of U.S. ATLAS /March 2001 WBS Pixel Overview and WBS Pixel Mechanics M. G. D. Gilchriese Lawrence Berkeley Laboratory.
ATLAS 1 Beam Pipe Support Structure (BPSS) Interface and Assembly Final Design Review, April 2003 E. Anderssen, N. Hartman LBNL.
ATLAS 1 Beam Pipe Support Structure (BPSS) Services Interface and Assembly Final Design Review, April 2003 E. Anderssen, N. Hartman, A Smith, LBNL S. Coelli,
M. Gilchriese Pixel Update October 3, M. Gilchriese 2 Outline Barrel status and repair strategy Revised ATLAS installation schedule Finishing pixel.
2011 Calendar Important Dates/Events/Homework. SunSatFriThursWedTuesMon January
SunSatFriThursWedTuesMon January
US Project Plan for MICE Mark Palmer Peter Garbincius, Alan Bross, Rich Krull Fermilab November 24, 2014.
1 PST Heaters 4 panels per segment along pixel support tube. Each segment is 236mm long at the moment. Copper-on-kapton. Nominal 20 ohms per full panel.
Status of Anti project. F. Raffaelli,A. Checchetti,C. Capoccia. INFN CERN, July 14 th, Status of the Anti construction test and schedule. -Status.
ATLAS Pixel Detector Pixel Support Tube and Related November 9, 2001 Pixel Day E. Anderssen, LBNL.
ATLAS Pixel Detector July 2003 SC Pixel Meeting N. Hartman LBNL 1 Pixel Support Tube WBS Santa Cruz Cost Workshop July 9, 2003.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
Walter Sondheim 6/9/20081 DOE – Review of VTX upgrade detector for PHENIX Mechanics: Walter Sondheim - LANL.
M. Gilchriese Work Plan W. Miller iTi M. Cepeda, S. Dardin, M. Gilchriese, C. Haber, R. Post LBNL February 6, 2007.
ATLAS Pixel Detector July 2003 Insertion Device Costs A. Smith, LBNL 1 Insertion Device Costs Overview US Pixel Meeting July 9, 2003.
ATLAS Pixel Detector Pixel Support Tube Interfaces Pixel Support Tube PRR CERN, Geneve E. Anderssen, LBNL.
Preparations to Install the HBD for Run 6 Craig Woody BNL PHENIX Weekly Meeting January 26, 2006.
Proposal for ESS DTL Roadmap. Divide Into Four Phases 1.Conceptual Design Phase (In progress) 2.Technical Design Phase 3.Prototyping Phase 4.Construction.
Steinar Stapnes, LHCC June The ATLAS inner detector TRT endcap A+B TRT endcap C TRT barrel SCT barrel SCT endcap Pixels uWhole ID sits inside bore.
TF Fabrication Progress is being made on TF bundle fabrication activities but the schedule remains tight. All 24 outer conductors have been machined but.
USCMS Pixel PMG, Nov 29, Mechanics Status Disks, ½ Service Cylinders Installation USCMS FPIX FNAL PMG Joe Howell Bruno Gobbi Nov. 29, 2006.
M. Gilchriese - February 2001 Disk Sector Status E. Anderssen, M. Gilchriese, F. Goozen, N. Hartman, T. Johnson, F. McCormack, J. Taylor, T. Weber, J.
21 Mar 2007ALICE - Paul Dauncey1 ALICE CR07: Installation and Commissioning Paul Dauncey Material from: L. Leistam: “ALICE Status” W. Riegler: “Commissioning.
ATLAS 1 Beam Pipe Support SCT TRT Side CSide A Services and Beampipe Support Frame Services and Beampipe Support Frame Pixel Detector Composite support.
Resource Loaded Schedule and Budget Profile
Deadline for Requisitions Payment Processing Date
Beam Pipe and Service Support Structure Production Progress
Support Structure Fabrication
McDonald’s calendar 2007.
McDonald’s calendar 2007.
Cryogenic upgrade of B163, B165 & B253 Status Meeting 19th December 2018
Presentation transcript:

ATLAS Pixel Detector September 2002 N. Hartman LBNL 1 Pixel Support Tube: Cost and Production Schedule September 2002

ATLAS Pixel Detector September 2002 N. Hartman LBNL 2 PST Deliverables 3 Composite tubes 6 Bonded composite flanges Full Length insertion rails Mount pads at forward and barrel (8 total) PST Supports (8 flexures) Pixel detector supports (kinematic, 4 total) Heaters and EMI shielding (continuous over length) PST must be delivered as three bonded assemblies Barrel mount pads are bonded while in dry fit with SCT Forwards must be mounted to guarantee alignment All must be delivered by June ’04 Installation work costed in separate installation plan SCT installation is Sept. ’04

ATLAS Pixel Detector September 2002 N. Hartman LBNL 3 Full Schedule Note schedule is in calendar years, not fiscal Production estimate is rough (will know better by end of Q1 FY03) Based on delivery date of 6/1/04 to CERN SCT installation date 9/1/04 (3 months slack time)

ATLAS Pixel Detector September 2002 N. Hartman LBNL 4 Prototype Schedule Current Progress Note schedule is in calendar years, not fiscal

ATLAS Pixel Detector September 2002 N. Hartman LBNL 5 Prototype Items Shells –Completed Rails –Partially Complete – foot long rails have been made –Lead time of long rail tool is critical –Rail riders must be addressed Flanges –To be outsourced, not yet complete Hoop Stiffeners –May not be prototyped (fabricate during production phase only) –Schedule is already tight without them Mount Pads/Flexures –Mount pads require flat plate material from flange fabrication –If vendor cannot supply in time, must make mount pad material in house PST Assembly (bonding) –Designing bond tooling is critical item (lead time for machining) –Actual assembly can slip a little and overlap with long rail fabrication

ATLAS Pixel Detector September 2002 N. Hartman LBNL 6 Production Summary Prototyping –Continues through Q1 of FY03, but 3 month “slack” exists in Q2 of FY03, while full size mandrel is being machined –Q1 of ’03 is staffed with Research Assistant (FTE) and MT (1/2 FTE) –All production tooling produced in near-final form in prototype phase, except for mandrel –Prototype flange production contract covers tooling that will be used to fabricate production flanges as well (but under additional contract) Production –Begins in Q3 of FY03, Continues to Q4 of FY04 –Production time is staffed with MT (1/2 FTE) –PST Barrel constructed first, in case needed for dry fit with SCT earlier than expected, though many parts will already be made for all sections –Complete PST Delivered June of 2004

ATLAS Pixel Detector September 2002 N. Hartman LBNL 7 Important Milestones Production Readiness Review –December 9, 2002 – CERN Full Size Mandrel and Material Ordered –January 7, 2002 Production Material Delivered –February, 2002 Mandrel Delivered –March, 2002 Production Begins –April 1, 2002 Barrel PST Completed –September 14, 2002 Forward PST’s Completed –June 1, 2002 Fit-up with SCT (mount pads bonded in place?) –June, 2002 SCT/PST Installed –September, 2002

ATLAS Pixel Detector September 2002 N. Hartman LBNL 8 Potential Risks Prototyping –Problem with rail riders –Delay of bond or rail tooling –Delay of flange fabrication (contract) Production –Delays or problems in mandrel machining –Prototype delay eating into production time –Delay in working out mount pad bonding scheme with SCT –Delay in SCT schedule pushing back completion of PST (if dry fit is required for bonding to complete PST)

ATLAS Pixel Detector September 2002 N. Hartman LBNL 9 Cost Summary Costs in FY02 $K ETC02 to ETC03 very similar overall costs Schedule delay of about 6 months Production moved from FY03 to FY03/FY04 Prototyping extended into FY03