Nodal Readiness and Transformation Metrics Discussion June 22, 2009 NIT Meeting 06/18/2009 Brandon McElfresh Readiness and Transformation, Metrics Lead.

Slides:



Advertisements
Similar presentations
1 Market Trials Outage Scheduling Qualifications Weekly Update March 4, 2010.
Advertisements

July 21, 2008 TPTF Texas Nodal Market Implementation: Market Readiness Metrics Update Karen Lamoree.
November 1, 2007 TAC Meeting Texas Nodal Program Update Jerry Sullivan, Executive Director.
June 12, 2008 ROS SEM Go-Live procedure Linda Clarke.
August 2, 2007 TAC Meeting Texas Nodal Program Update Tim Pare.
1 Texas Nodal Texas Nodal Program Implementation TPTF June 6, 2006 Agenda.
1 GENMAP Registration Workshop Jan 14, 2010.
Lead from the front Texas Nodal 1 TPTF Update for TAC November 29, 2007 Trip Doggett.
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation Program Implementation Scenarios September 6, 2006.
TPTF Meeting Texas Nodal Program Update Market Readiness Metrics Update Chris Wilkinson PMO.
Market Implementation Board Presentation October 1 Texas Nodal Market Implementation ERCOT Board of Directors Meeting Program status.
1 Single Entry Model (SEM) Go-Live Update ROS Update July 16, 2009.
1 Nodal Market Readiness Cut-Over Activities Kick-Off Meeting May 25, 2010.
Texas Nodal Program ERCOT Readiness Update TPTF March 31, 2008.
1Texas Nodal Texas Nodal Market Trials and Data Verification ROS Meeting By Steve Grendel, ERCOT Thursday, 01/11/2007.
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation TPTF Nodal Status Update November 6, 2006.
Market Implementation Board Presentation July – v1.1F 1 Texas Nodal Market Implementation ERCOT Board of Directors Meeting Program.
Lead from the front Texas Nodal 1 TPTF Update for TAC March 6, 2008 Trip Doggett.
Lead from the front Texas Nodal 1 Texas Nodal Load Frequency Control (LFC) EDS 3 Release 6 - Handbook EDS 3 Release 6 MP Planning.
Texas Nodal Timeline Options, TPTF Jul 11, Timeline Options Trip Doggett TPTF
ROS Meeting – 12/06/071Texas Nodal Program - TPTF Update Texas Nodal Transition Plan Task Force ROS Meeting Stacy Bridges, ERCOT Thursday, 12/06/2007.
TPTF Meeting Texas Nodal Program Update Market Readiness Metrics Update Chris Wilkinson PMO.
March 11, 2008 Texas Nodal Market Redesign Program Commercial Operations Subcommittee.
1Texas Nodal Market Trials Update. 2Texas Nodal LFC Testing Review Review of materials presented at TAC Changes in Market Trials schedule and activities.
Lead from the front Texas Nodal 1 TPTF Update for TAC October 5, 2007 Trip Doggett.
ROS Meeting – 05/15/081Texas Nodal Program - TPTF Update Texas Nodal Transition Plan Task Force ROS Meeting Stacy Bridges, ERCOT Thursday, 05/15/08.
January 15, 2008 Monthly Board of Directors Meeting Texas Nodal Market Implementation Program Update Jerry Sullivan.
Lead from the front Texas Nodal 1 Integrated ERCOT Readiness and Transition (IRT) TPTF - November 6 th, 2006.
Lead from the front Texas Nodal 1 Texas Nodal Registration Kick-off Meeting Matt Mereness June 6 th, 2007.
September 25, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan.
January 21, 2008 TPTF 168 Hour Test Initial Approach Discussion.
Lead from the front Texas Nodal 1 TPTF Update for TAC February 1, 2007 Trip Doggett.
Texas Nodal Market Implementation Metric Sub Group Readiness Advisor January 30, 2006.
Lead from the front Texas Nodal 1 TPTF Update for TAC March 30, 2007 Trip Doggett.
May 22, 2008 TPTF Texas Nodal Market Implementation Program Update Raj Chudgar.
Outage Scheduler Transition Plan Kenneth Ragsdale NATF.
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation ERCOT Board Of Directors – August 15, 2006 TPTF Meeting August.
1 Readiness Scorecard – May ‘10 NATF Brandon McElfresh Nodal Readiness and Transition May 4, 2010.
Nodal Program Update Mike Cleary Sr. VP and Chief Technology Officer.
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation Program Implementation Scenarios September 6, 2006.
October 8, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan Program Director, Market Redesign.
1 June 2010 NATF Meeting NATF Readiness Update Brandon McElfresh June 1, 2010.
Market Redesign Update ERCOT Board of Directors Meeting April 18, 2006 Ron Hinsley Chief Information Officer
August 27, 2007 Executive Committee Meeting Texas Nodal Program Update Jerry Sullivan.
Texas Nodal Program ERCOT Readiness Update TPTF May 5, 2008.
Lead from the front Texas Nodal 1 Integrated ERCOT Readiness and Transition (IRT) TPTF – December 4 th, 2006 ERCOT Qualification.
Lead from the front Texas Nodal 1 TPTF Update for TAC February 7, 2008 Trip Doggett.
Lead from the front Texas Nodal 1 Nodal Transitional Qualification Approach to Qualifications for the Nodal Market August 16, 2007.
April 1, 2008 TPTF Texas Nodal Market Implementation Program Update Jerry Sullivan.
1 Texas Nodal Texas Nodal Program Implementation TAC July 6, 2006 Agenda.
Retail Workshop ERCOT Nodal Update October 06, 2010.
Lead from the front Texas Nodal 1 TPTF Update for TAC August 2, 2007 Trip Doggett.
April Board of Directors Meeting Texas Nodal Program Update Jerry Sullivan Executive Director, Texas Nodal Program.
June 9 th, 2008 TPTF Texas Nodal Program: Market Readiness Metrics Update Mike Beck.
01/21/2009 Telemetry Process & Progress ERCOT State Estimator & LFC Team Operations Advanced Network Applications Support.
October 2, 2008 TAC Texas Nodal Market Implementation: Program Update Ron Hinsley.
July 7, 2008 TPTF Texas Nodal Market Implementation: - Market Readiness Metrics Update Jerry Sullivan.
Texas Nodal Market Implementation Transition Planning Task Force Metric Framework Review Readiness Advisor January 24, 2006.
June 5, 2008 TAC Texas Nodal Market Implementation Program Update Jerry Sullivan.
Lead from the front Texas Nodal 1 EDS Market Call Weekly Update Feb 06, 2009.
1 Market Trials Outage Scheduling Qualifications Weekly Update March 26, 2010.
1 Single Entry Model (SEM) Go-Live TAC Update May 7, 2009.
Lead from the front Texas Nodal 1 Texas Nodal EDS4 - Approach 11/28/2007.
1 Readiness Scorecard – Market Readiness Series Brandon McElfresh Nodal Readiness and Transition January 28, 2010.
August 11, 2008 TPTF EDS Sequence and Durations Discussion Daryl Cote.
1 1 Texas Nodal Program UpdateMarch 21, 2008 Nodal SAS70 Audit – Readiness Approach & Timeline March ‘08June ‘08 Sept ‘08 Dec ‘08 Jan ‘09 Define Readiness.
Market Trials Open Market Participant Call
TPTF Update for TAC October 5, 2007 Trip Doggett
Market Participant Readiness Tracking
Presentation transcript:

Nodal Readiness and Transformation Metrics Discussion June 22, 2009 NIT Meeting 06/18/2009 Brandon McElfresh Readiness and Transformation, Metrics Lead

Nodal Metrics – Overall State Currently there are 84 Metrics with 155 underlying measurements  61 ERCOT Metrics/23 MP Metrics;  77% of the metrics have untested processes for collecting data;  Metric Start/End dates not in Integrated Project Schedule;  3 Full-time resources were needed not including resource time from Client Services and Market Trials teams Other ISOs  Cal ISO–33 metrics in 21 areas, MISO–126 metrics in 10 areas;  ERT plans to consult these other ISOs. Opportunity to  Eliminate redundancy (30 Metrics already identified);  Minimize overhead necessary for reporting;  Simplify reporting for NIT, TAC, and the Board. Proposal  SEM Go-Live to use separate dashboards;  RAT to present improved Metric proposal at the Sept ‘09 NIT meeting;  Metrics reporting to start in Oct/Nov ‘09 to prepare for intense activity during Market Trails. Nodal Readiness Scorecard 2 Nodal Metrics Inventory

Metrics – Initial Observations ObservationOpportunity C1-C10 – Metrics for Contingency Plans for each application. CO3, CO5, CO6, CO7, CO8 – Metrics for RTM, DAM, and CRR Statements and Invoices. E10, E11, E3 – Metrics for EDW Access and Accuracy. E6, E9 – Metrics to develop operating guides and procedures. E7, IMM1 – Metrics for Independent Market Monitor functionality. MO7, EMO13 – Metrics for Facilities Readiness. EM01, MP10, MP11, MP18 – Metrics for registration of Market Participants. MP2, MP3, MP8, MP15A – Metrics for ED3 participation and submission of SCED offers. R0, R1, R2 – Metrics to declare ERCOT and Market Participants ready for Go-Live. MP5, EMO5 – Metrics ICCP Telemetry test and verification of ACE performance are complete. MP17, MP22 – Metrics for MP Qualification Consolidate into one Contingency Plan metric (- 9 Metrics). Move all of the statement and invoice verification into the CO1 “Settle Market for 7 Days” test (- 5 Metrics). Consolidate to one EDW metrics (- 2 Metrics). Consolidate into one Readiness Documentation Metric (- 1 Metric). Consolidate to one IMM Metric (-1 Metric). Consolidate to one Facilities Metric (-1 Metric). Consolidate into one Registration Data Metric (- 3 Metrics). Consolidate to one metric for EDS3 Participation and successful submission of SCED offers (-3 Metrics) Consolidate to one metric to Nodal Readiness for Go- Live (-2 Metric) Mark MP5 and EMO5 as complete on the Metrics dashboard (-2 Metrics. Consolidate into one Qualification Metric (-1 Metric) 3 By just eliminating redundancy we can retire 30 Metrics

Metrics – Next Steps 4 Included below is a list of activities needed to reintroduce the Nodal Metrics Program Inventory metrics and verify the existing owners; Redesign and consolidate metrics based on feedback from owners. Determine whether the metrics still represent relevant milestones in the program; Consult resources with metrics experience; Work with Market Trials project team to map Metric Start/End dates to Market Trials Milestones; Work with the Master Schedulers to associate modified metrics with milestones on the Integrated Program Schedule; Ensure that changes to the metrics reporting process are communicated to and approved by the Nodal Program, Wholesale Client Services, and any other key stakeholders; Present the modified metrics and reporting process to NIT for feedback at September meeting; and Begin reporting the metrics in October/November 2009 in preparation to ensure preparedness for February 2009 Market Trials.