K. Mercier, Shanghai meeting, 19th-22 May 2014 CNES, 5 th June 2014 Karine MERCIER EUSO Balloon Key Point Flight Acceptance Organisation
K. Mercier, Shanghai meeting, 19th-22 May KEY POINT GOAL Key Point main objective: “To ensure that the EUSO-Balloon instrument is ready for flight with respect to the EUSO-Balloon mission requirement and that the necessary tests to demonstrate its qualification and the validation of its performances have been done”
K. Mercier, Shanghai meeting, 19th-22 May Details Objectives In addition detailed objectives are defined below: Analyse the state of the Instrument reference Configuration Verify the instruments budgets Verify the state of qualification of the Instrument through the results of the tests done Verify instrument performances with respect to the mission objectives To present the state of the compliance with the CNES Balloon User’s Manual including the results of the coupled tests and the safety documentation To verify the availability of the instrument User’s Manual To verify the completeness of the campaign documents (including the organisation, the tests procedures, the schedule) Verify the status of the Non Conformities and of the anomalies Verify the closure of the actions of the previous reviews Verify the flight capacity of the camera IR through its interfaces, through its state of qualification and its flight campaign preparation To declare the EUSO-Balloon instrument ready for flight
K. Mercier, Shanghai meeting, 19th-22 May Key Point Organization Main dates Board Members DateTimePlaceStep 26/05/ Deadline for documentation delivery 04/06/ h-15h 15h-16h 16h-18h CNES - Key Point General presentation - Board internal discussion - Questions / Answers Board - Project 05/06/2014--Board Synthesis 05/06/2014- Visio conference Key Point Steering Committee Board PresidentYves ANDRECNES PerformancesPierre MANDROUIRAP Balloon expertAndre VARGASCNES Quality ExpertG BRONDINOCNES