NCSX Project Overview and Management Hutch Neilson, NCSX Project Manager Princeton Plasma Physics Laboratory Oak Ridge National Laboratory Office of Science.

Slides:



Advertisements
Similar presentations
1 BROOKHAVEN SCIENCE ASSOCIATES Environment, Safety and Health Steve Hoey, ESH Manager NSLS-II Project Advisory Committee Meeting March 29, 2012.
Advertisements

1 BROOKHAVEN SCIENCE ASSOCIATES Procurement Dave Paveglio, Contract Administrator NSLS-II PAC Meeting May 25, 2007.
1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab - Berkeley.
Mark Reichanadter LCLS FAC April 20-21, 2006 Meeting of the LCLS Facilities Advisory Committee LCLS Project Management M.
ARIES-General Page 1 Summary of Findings of Lehman Committee to Assess ITER Costing L. Waganer The Boeing Company 8-10 January 2003 ARIES Meeting at UCSD.
NGAO Team Meeting Management Peter Wizinowich May 26, 2009.
Introduction to ARA’s Proposal Resources Don Cole
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
TRU Waste Processing Center Culture and Successful Implementation of an ISO Certified Environmental Management System Presented at the DOE ISM Conference.
 A project is “a unique endeavor to produce a set of deliverables within clearly specified time, cost and quality constraints”
NCSX May 12, 2005 ACC Review- Station 5 J.H. Chrzanowski - 1 ACC Review Of Modular Coil Manufacturing Facility Station No. 5 [VPI] the NCSX Manufacturing.
From Research Prototype to Production
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck Deputy Director (Project Management)
Princeton University Plasma Physics Laboratory EVMS Certification Review NSTX Project Overview Ron Strykowsky October 4-6, 2011.
NCSX NCSX Project Update Hutch Neilson, Project Manager for the NCSX Team Princeton Plasma Physics Laboratory Oak Ridge National Laboratory Briefing for.
TBM Costing Lessons from Recent ITER Activities Scott Willms Los Alamos National Laboratory Presented at INL August 10, 2005.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
ISM 5316 Week 3 Learning Objectives You should be able to: u Define and list issues and steps in Project Integration u List and describe the components.
October 4-5, Status of ARRA funded AIPs Electron Lens Scope, Cost, and Schedule Wolfram Fischer October 4, 2010 Electron Lens.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
HLRF DRAFT Global Design Effort 1 Defining EDR* Work Packages [Engineering Design Report] Ray Larsen SLAC ILC Division for HLRF Team DRAFT April.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Update Steve Dierker Associate Laboratory Director for Light Sources NSLS-II Project Director Conventional Facilities.
SC Project Review of NCSX, April 8-10, 2008 Ron Strykowsky - page 1 Office of Science NCSX Project Review of NCSX April 8-10, 2008 Cost and Schedule Ron.
NCSX NCSX Design Review Guide May 27, 2005 Wayne Reiersen NCSX.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
M. Reichanadter LCLS Project November 2008 FAC Meeting Slac National Accelerator Laboratory Report to the LCLS.
12/2/04Module 2D1 The NCSX Engineering Web – An Overview Part IV Engineering Management & Systems Engineering and Other.
NCSX VACUUM VESSEL PL Goranson Thermal Insulation Final Design Review July 31, 2006 WBS12 NCSX.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
Anthony Indelicato DOE-Princeton Site Office May 2012 Construction Progress Review for the NSTX Upgrade Project Construction Progress Review for the NSTX.
PU-PPPL Earned Value Management System Overview Thomas Egebo October 4-6, 2011 Princeton University Plasma Physics Laboratory EVMS Certification Review.
Fermilab Presentation Greg Bock, Pepin Carolan, Mike Lindgren, Elaine McCluskey 2014 SC PM Workshop July 2014.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
1 LHC-DFBX Fabrication Oversight Plan Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab.
NCSX Systems Engineering Management Plan Peer Review Bob Simmons May 15, 2003.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
NCSX Field Period Assembly (FPA) Operations, Cost and Schedule, Staffing, and Metrology Utilization Mike Viola Field Period Assembly Manager NCSX FPA Peer.
11/2/2005Mike Viola1 November Lehman Review November 2, 2005 NCSX VVSA NCSX Vacuum Vessel Fabrication Major Tool and Machine – S F 3 120° segments.
NCSX Field Period Assembly (FPA) Operations, Cost and schedule, staffing, and metrology utilization Mike Viola Field Period Assembly Manager NCSX FPA Peer.
Mark Reichanadter LCLS October 9-11, 2007 LCLS BCR Overview and EIR LOIs Project Progress / Status Revised Project Baseline.
1 Field Period Assembly Office of Science Project Review Princeton Plasma Physics Laboratory Princeton, NJ November 2, 2005 T. Brown Princeton Plasma Physics.
NCSX NCSX Project Meeting Wayne Reiersen 15 December 2004.
Texas Nodal Program ERCOT Readiness Update TPTF June 23, 2008.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62) Manager.
SC Project Review of NCSX, April 8-10, 2008 NCSX Machine Assembly E. D. Perry.
PPPL is Committed to the Success of NCSX Rob Goldston, Director Princeton Plasma Physics Laboratory August 15, 2007.
Strykowsky 1Project Review November 2, 2005 NCSX Project Review November 2, 2005 Cost and Schedule Ron Strykowsky.
Tom Egebo PPPL Review of the NSTX TF Coil Repair Effort September 3 - 4, 2003 Cost & Schedule to Completion Supported by Columbia U Comp-X General Atomics.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier NSLS-II Conventional Facilities Schedule Review December 13, 2006.
Field Period Assembly Wayne Reiersen SC Project Review PPPL May 2006.
Anthony Indelicato DOE-Princeton Site Office February 2014 Construction Progress Review for the NSTX Upgrade Project Construction Progress Review for the.
NCSX 21 March 2003 Reiersen - 1 PDR Preparations Wayne Reiersen NCSX Engineering Meeting 21 March 2003.
9/28/20051 Mike Viola 1, T. Brown 1, P. Heitzenroeder 1, F. Malinowski 1, W. Reiersen 1, L. Sutton 1, P. Goranson 2, B. Nelson 2, M. Cole 2, M. Manuel.
Anthony Indelicato DOE-Princeton Site Office October 2013 Construction Progress Review for the NSTX Upgrade Project Construction Progress Review for the.
Preparations for working on Station 1 November 22, 2005.
NCSX Strykowsky 1Cost and Schedule Rebaseline April 25, 2005 NCSX Project Re-baseline Review April 25, 2005 Cost and Schedule Ron Strykowsky.
Strykowsky 1Office of Science Review August 15, 2007 Office of Science Project Review NCSX August 15-17, 2007 Cost and Schedule Ron Strykowsky.
NCSX VVSA / MCWF FDR A Systems Engineering Perspective Wayne Reiersen Bob Simmons NCSX VVSA / MCWF FDR May 19-20, 2004 PPPL.
1 WBS 1 Preparation for FDRs NCSX WBS 1 Engineering Meeting March 17, 2003 What establishes the plan? What are near term deliverables? How will we status.
PPPL Stellarator Program Overview Hutch Neilson NCSX Project Manager NCSX Program Advisory Committee Meeting #6 Princeton, NJ December 9, 2002.
Supplier Management Can’t live with them, Can’t live without them!
NCSX Strykowsky 1Independent Project Review (IPR) June 8-9, 2004 NCSX Project Review June 8-9, 2004 Cost, Schedule, and Project Controls Ron Strykowsky.
Anthony Indelicato DOE-Princeton Site Office December 2012 Construction Progress Review for the NSTX Upgrade Project Construction Progress Review for the.
SC Project Review of NCSX, April 8-10, 2008 C. A. Gentile NCSX Startup (WBS 85) C.A.Gentile NCSX CD-4 Startup.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
External Independent Review (EIR)
Preliminary Project Execution Plan
Conventional Facilities
SNS-PPU upgrades the existing accelerator structure
Presentation transcript:

NCSX Project Overview and Management Hutch Neilson, NCSX Project Manager Princeton Plasma Physics Laboratory Oak Ridge National Laboratory Office of Science Project Review Princeton Plasma Physics Laboratory Princeton, NJ May 9, 2006

2 The NCSX Project is About 55% Complete NCSX Stellarator Major Radius 1.4 m Magnetic Field 2.0 T Pulse length ~1 s CD-4 Scope Fabricate & install stellarator. Adapt to existing technical infrastructure. Test system and make first plasma. Schedule and cost April, July, 2009 (76 months) TEC $92.4M Current status: component production and delivery are in full swing. 5 modular coil winding forms delivered. 2nd modular coil nearly completed. Vacuum vessel sectors nearing completion. TF contract awarded. Work performed through 3/06 (36 months): $46M (55% of BCWS). $8.0M in last 6 months

3 We Have Moved into “Production Mode” At Nov., 2005 SC Review: Fabricating “first-of-a-kind” components. 1st MCWF was just delivered. 1st modular coil fabrication was just starting. Were beginning to install ports on first VV segment. Now: Multiple components in process or delivered Modular coils (18) –All 18 MCWF castings have been poured. (was 9 in November) –14 have completed foundry operations (was 4) –5 are in machining operations (was 2). –5 have been delivered to PPPL (was 1) –4 MCs are in production at PPPL (was 1) –1 has been completed (was zero). Vacuum vessel: all 3 segments are in advanced stages of manufacture. Manufacturing processes have been established, though refinements and learning-curve improvements continue. (projected status as of Lehman review.)

4 Component Production –Progress, risk management. Budget update Management Summary. Outline Moved into production mode and retired some major risks. Project is in good financial health. Team staffed and functioning per DOE expectations & project needs.

5 MCWF Deliveries Are Now On Track: 5 Delivered Energy Industries of Ohio, Inc. Initial expectations for #2 and #3 deliveries were not met. Machining process development continued thru first 3 MCWFs - longer than expected. A contract modification was negotiated in February, as #3 was finishing up: –A new delivery schedule, supported by a vendor production plan which the project reviewed and judged to be sound. –A new delivery sequence (of A, B, C types) more favorable to project needs. –A price increase, earned by on-schedule delivery. Vendor is performing well on the new plan. MCWF in Machining High quality is being maintained. New MCWF schedule supports project baseline, maintaining 5 months float.

6 Re-sequencing Mitigated the Impact of MCWF Schedule Stretchout Curre nt Plan New Plan Complete F.P. Sets #1-Nov., #2-Feb., 2007 #3-Aug., 2007 Old Project Schedule New Contract Schedule New Project Schedule Note: 1 Field Period (F.P.) Set = 2 A’s, 2 B’s, and 2 C’s. Project planning assumes a more conservative schedule than contract schedule. (Deliveries every 4.8 weeks vs. every 4 weeks.) F.P. #2 completion delayed by only 1.5 months. –Compensated by slightly compressing Stage 5 field period assembly operations. –F.P. #3 delay (5.5 months) was accommodated by free float.

7 First Modular Coil Was Completed on Schedule Met Level II milestone on schedule (March). –Need to produce at a rate of 1 every 4.8 weeks. Not quite there yet. –Typical start-up issues, e.g. new personnel, unplanned tasks. No major issues. –We are regularly working two-shifts. –Schedule recovery measures as needed: Saturdays, additional staff, optional 3rd winding station. Process developed on twisted racetrack R&D coil is working well in production. –Experienced TRC techs. formed the nucleus of the expanded production crew. –Achieving required tolerance (±0.020 in.) on current center position. Twisted Racetrack Coil L. Dudek J. Chrzanowski. Completed Coil

8 MC Production Costs Are Running Above Estimates, But Coming Down Costs are being tracked in detail and reviewed weekly by management. –Used to target areas for improvement. Estimates have increased, driven by: –Unplanned tasks (e.g., re-work of procured parts, tooling issues.) –Some planned tasks are taking longer than expected. Favorable trends are due to: –Process improvements. –Crew gaining experience. –Multiple coils in production (volume efficiencies.) Cost trends for process steps that have been completed on all 4 coils new estimate

9 All 3 VVSAs are in advanced production #1Vacuum tested, fabrication complete. Ports crated for shipment. Segment is in final inspection #2Port installation complete. Preparing for vacuum test. #3Port installation in progress. Delivery schedule supports project baseline. Process issues have been resolved. New completion schedule is supported by a sound vendor production plan. –Forecast: #1: May. #2: July. #3: August. VVSA fabrication is 9 months off the project critical path. High quality is being maintained. Vacuum Vessel Manufacture is Nearing Completion Major Tool and Machine, Inc. M. Viola VVSA #1 VVSA #2

10 TF Contract Has Been Awarded XYZ Company November Review: cost risks >$1M reported. Wedge casting quotes Estimates for in-house winding and assembly. Now: cost risks retired with fixed-price contract Conducted intensive field investigation of potential suppliers, including visits to ASIPP (China) and ETI by PPPL delegation. Findings: –Schedule and quality requirements can be met. –Wedge support costs can be reduced. –Suppliers can produced complete assemblies. Awarded contract following competitive source selection process. Delivery schedule (#1: Dec. ’06. #18: Sep. ’07) is 7 months off the critical path. TF Coil Subassembly coil wedge supports

11 Work plans and ETC’s have been updated to support forward planning. Contingency request is minimized –Cover variances on completed work, estimate growth for near-term work (at least next 6 months) and for fixed-price contracts. –For longer-term estimate growth: identify as risk. Keep budget in contingency while continuing working to reduce costs. Review again in 6 months. –Reduce work in ancillary systems to maintain sufficient contingency to manage remaining risks and meet CD-4 requirements. $824k request leaves $7,804 contingency (21.4% of remaining work). –We have successfully managed project risks with contingency percentage at about this level since CD-2, while. Project is in Good Financial Health

12 Budget Needs for Stellarator Core Estimate Growth Risks FY-07 modular coil winding ops: $507k. –Continue to push costs down via learning curve and improvements. Re-assess in 6 months. Additional MCWF payments, if vendor earns full incentive: $410k. –Earned if vendor meet the contract schedule, but could be offset by completing project by ~2 months, saving carrying costs.

13 Work Reductions to Offset Cost Growth These are tough measures, but vital to project’s overall financial health. We can meet CD-4 performance requirements with the reduced scope. Sam Barish: Address the impact on research program, esp. 09. Wants to see this slide.

14 At 21.4%, Contingency Remains in its Historical Range Cost risks identified at CD-2 have been successfully managed at this level. Costs of largest procured components (MCWF, VVSA, TF) are now known. Modular coil winding cost trends are favorable, uncertainties have narrowed. All R&D is complete. Title II Design is >75% completed. The main outstanding risks– field period and machine assembly – are significant but no worse than than those we have successfully managed. Nov. Review May Review

15 Contingency is Supported By Updated Risk Assessment Cost reduction opportunities continue to be explored –Simpler cryostat? $350k. –Fabricate PF coils at ASIPP (China)? ~$375K –Accelerate completion up to 2 months via 2-shift assembly operations? (Reduces carrying costs.) ~$400k Schedule contingency maintained at 5 months since CD-2.

16 Initiated vendor re-planning action to arrest MCWF schedule slippage. –Delivery rates have improved. Risk substantially reduced. Initiated TF acquisition re-planning to reduce >$1M cost risks. –Changed from “make” to “buy,” based on focused vendor research. –Fixed-price contract (almost) awarded. Risk substantially reduced. We are improving performance in coil winding operations. –Coil-by-coil costs tracked to target areas for improvement. Operations are tightly managed to optimize cost and schedule. –Cost trends are favorable. Uncertainties narrowed. More improvement expected. Meeting NCSX production needs is a management priority for all groups. –Manufacturing operations, drawings, response to vendor issues, procurement. –Strongly supported by PPPL and ORNL management. Significant risks have been reduced or retired. Cost and Schedule Risks Are Aggressively Managed: Highlights from Last 6 Months

17 We Are Staffed and Functioning per Project Needs Continuity of Engineering Leadership Key NCSX engineers (e.g., Brad Nelson, possibly Phil Heitzenroeder) expect to have growing ITER responsibilities. Transition plan: as ITER needs ramp up, transfer NCSX duties to other NCSX- supported engineers: –Stellarator Design Leadership: Brad  Mike Cole, Wayne Reiersen, Brad. –MCWF Contract Management: Phil  Larry Dudek, Phil. Working with ITER project office to ensure that both projects’ needs are met. The IPT is fully involved in risk management Excellent communication via multiple forums –Watch List (monthly), IPT meetings (monthly), special briefings (by request). Critical activities status (MC, MCWF, VVSA) updated and briefed weekly. Cost performance reports and corrective measures reviewed monthly. Management reserve plans reviewed monthly. Critical issues status reviewed at IPT meetings. FPD approves contingency transfers.

18 Safety is Integrated into NCSX Work at All Levels All staff (including ORNL) take Hazard Awareness Training to improve understanding of NCSX hazards. Safety is addressed in design process and influences choices. –Stage 1 Field Period Assembly. Manufacturing Project Hazard Analysis was updated to include Field Period Assembly operations. –Approved by PPPL Safety Review Committee. –Lab Activity Certification Committee (ACC) reviews facilities and operations. NCSX worker accident (cut hand- non-DART case) was followed up with work group discussions and Lab procedure changes. Safety, cost, and schedule goals are synergistic. –Work is done according to documented plans and procedures. –Project organized for strong safety management, with safety, cost, and schedule responsibilities aligned. Line management is responsible for safety. –Supported by ES&H professionals.

19 The Mix of Activities Will Change in the Next 6 Months Activities Wrapping Up VVSA fabrication VV details and MC winding pack design Activities Continuing MCWF: Complete foundry ops. Deliver 4 more to PPPL. Modular Coil fabrication: Complete 4 more. Activities Starting TF Coil fabrication. Field Period Assembly: Stage 1 (Vacuum Vessel prep) MC interfaces and coil services design.

20 We Will Complete the Project by July, MCWFs delivered in FY Coil winding in FY F.P. Assy in FY Final assembly & testing FY First Plasma July, –5 mos. schedule contingency. R. Strykowsky Hutch Neilson: Update Hutch Neilson: Update

21 Summary of Charge Issues The Project is Making Excellent Progress in Component Production 1.MCWF and VVSA procurements support the project baseline. 2.Risk assessment and management mechanisms are working. Some major issues were successfully addressed since last SC review. 3.Cost of in-house activities is tightly managed. Strong support from PPPL Engineering Dept. (fab. activities) and ORNL Fusion Energy Division (design activities). 4.Cost and schedule estimates have been updated based on design maturity and experience. Tough actions taken to maintain contingency. Contingencies are supported by risk analyses. 5.The Project is staffed and functioning at all levels in accordance with the PEP and DOE requirements (O413.3).

22 Initiated vendor re-planning action to arrest MCWF schedule slippage. –Strong support from Director’s Office, Business Operations, Princeton University. –Credible contract schedule established. –Delivery rates have improved. Risk substantially reduced. Initiated TF acquisition re-planning to reduce >$1M cost risks. –Changed from “make” to “buy,” based on focused vendor research. –Strong Procurement Div. support led to source selection in record time. –Fixed-price contract (almost) awarded. Risk substantially reduced. We are improving performance in coil winding operations. –Dedicated weekly meetings of Project Management and Engineering Dept. Head. –Coil-by-coil costs tracked to target areas for improvement. –Shift work, overtime, staffing, training, crew organization are tightly managed to optimize cost and schedule. –Cost trends are favorable. Uncertainties narrowed. More improvement expected. We meeting NCSX production needs by making it a management priority. –Weekly meetings (Engineering Mgr., WBS Mgrs.) on Field Period Assembly readiness: drawings, parts procurements, procedures, fixtures, safety reviews. –Design team priorities support production: Rapid response to manufacturing issues from vendors or Lab team. Drawing priorities driven by production schedule needs. –Procurement Division provides priority service, including expedited action when neecessary. Significant risks have been reduced or retired. Cost and Schedule Risks Are Aggressively Managed: Highlights from Last 6 Months

23 Contingency vs Costs Drawdown trends look more consistent When plotted vs dollars instead of time.