André Augustinus Infrastructure  Turbines  Radmon  Thermocouple readout  Netgear redundancy  Other cavern items  Cooling CRs  Other CR and surface.

Slides:



Advertisements
Similar presentations
Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
Advertisements

André Augustinus 5 March 2007 Infrastructure status.
André Augustinus 15 March 2003 DCS Workshop Safety Interlocks.
CPV DCS STATUS REPORT Mikhail Bogolyubsky (IHEP, Protvino) Serguei Sadovsky (IHEP, Protvino) CERN, DCS meeting, 30 January, 2007.
André Augustinus 16 June 2003 DCS Workshop Safety.
LECC V. Bobillier1 Overview of LHCb Electronics installation aspects V. Bobillier; L. Roy; J. Christiansen CERN - LHCb.
David Emschermann DCS Workshop – PI Heidelberg – 22/01/2007 How to power up the TRD David Emschermann Physikalisches Institut Universität Heidelberg updated.
Status at P2 C. Lippmann Jan. 22, 2007 TRD DCS workshop at PI, Heidelberg.
SR1 ongoing workH.Pernegger21/2/02 Ongoing work in SR1 and preparations for detector macro assembly Heinz Pernegger.
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
JPV, TB of Nov.15 th, ‘Rack Status‘ Jean-Pierre Vanuxem, PH-AIS.
Saverio Minutoli INFN Genova 1 1 T1 Electronic status Electronics Cards involved: Anode Front End Card Cathode Front End Card Read-Out Control card VFAT.
André Augustinus 16 September 2002 Safety issues.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
1 LV Power Supplies L.Jirden* u Detector solutions u Contracts u Tests u Outstanding issues *Presented by André Augustinus.
DCS T0 DCS Answers to DCS Commissioning and Installation related questions ALICE week T.Karavicheva and the T0 team T0 DCS Answers to.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
1 Responsibilities & Planning DCS WS L.Jirdén.
André Augustinus 17 June 2002 Technology Overview What is out there to fulfil our requirements? (with thanks to Tarek)
Evaporative Heater Design, qualification and planning M.Olcese PRR SCT off-detector cooling PRR SCT off-detector cooling March March 2005.
André Augustinus 26 October 2004 ALICE Technical Board DCS for ‘services’ costs On behalf of Lennart Jirdén.
LS1 : EL Upgrades & Consolidation Chamonix– February 8 th 2012 F. Duval on behalf of EN/EL The goal of LS1 is to implement everything needed for a safe.
Claudio Bortolin. 1 st June: PT100 electrical connection failure (Temp Chiller water In&Out) 1) it required an access to the cavern to be fixed 2) access.
André Augustinus 6 October 2005 Cabling, Interlocks, Racks Some remarks.
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
André Augustinus 10 March 2003 DCS Workshop Detector Controls Layout Introduction.
Progress Completed Order/Fabricate SS Piping for HBD Purge gas from all detectors DAQ tests Prep. for Shutdown work (open doors, move carriages, etc. Pave.
CERN, O.Pinazza: ALICE TOF DCS1 ALICE TOF DCS Answers to DCS Commissioning and Installation related questions ALICE week at CERN O. Pinazza and.
E.Guschin (INR,Moscow) 17 July 2007 CALO commissioning group meeting CERN Status of PS/SPD LED system.
PS VFE & PS/SPD FE Electronics Status and Plans 21 November 2007 LPC Clermont.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
DSS  Informal review Tuesday 24 th October 10:00 Room , organized by Laurent Roy.  Subsystems will not be allowed to run overnight or at weekends.
IDE DCS development overview Ewa Stanecka, ID Week, CERN
André Augustinus 9 October 2006 Interlocks update.
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
LS1 planning meeting /4/13 ALICE TBStatus of LS1 activities - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare.
R. Boyd 1 February  Dr. M. Saleem  D. Jana  M. R. Meera Labbai  R. Boyd.
24/03/2010ALICE TOF General Meeting March TOF hardware and data taking 2010 Andrea Alici Museo Storico della Fisica e Centro Studi e Ricerche “Enrico.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
March 12 th 2013 Muon LS1 operation meeting1 Muon LS1 Status Outline Recap of last week P1 weekly schedule Muon related activities Open issues and discussions.
14 February 2007 G. Bohner, R. Bonnefoy, M. Crouau, P. Jacquet, C. Lacan, J. Lecoq, S. Monteil, P. Perret, G. Reinmuth, K. Suchorski LPC Clermont PS Very-Front-End.
LS1 planning meeting /7/13LS1 planning meeting - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS.
TOF status and LS1 plansTOF status and LS1 plans 27/06/2012.
1 Update on Power Supplies TB L.Jirden u LV u Concerns u Orders & deliveries u Maintenance u HV u Overview u purchasing.
André Augustinus 17 June 2002 Detector URD summaries or, what we understand from your URD.
ACS news RF cabling campaign: DONE Final tests cavity tuning motor (ctrl): in progress recabling software upgrade Water cooling: ADT static pressure test:
The (prototype) C&V Framework component used for the SPD Cooling Control A.Tauro, G.De Cataldo.
André Augustinus 13 June 2005 User Requirements, interlocks, cabling, racks, etc. Some remarks.
Interventions on electrical distribution and racks’ infrastructure still to be done during LS1 and their impact W.Iwanski.
TC meeting P2 planning wks 3&4 A.Tauro
CALO News Pascal Perret LPC Clermont 22 January 2012.
1. Road to the EDR 2 Requirements Safety system Transfer line concept Plant concept design Requirements Evaporator concept and performance Transfer line.
LHCb CO 2 cooling meeting Burkhard Schmidt – May 20,
DCal-ALICE integration and installation plan and status A. Tauro.
V Thermo-siphon Workshop Test protocol Jan Godlewski PH/DT-PO On behalf of thermo-siphon working group
1 04 April 2007 L. Roy Detector Safety System for infrastructure - General fire detection (barracks, cavern) - Sniffer system (smoke detection above the.
ELENA installation progress F. Butin / ELENA collaboration.
Detector Safety System overview DSS is a PLC based system designed to protect ATLAS detector from damages. Front end (hardware) 2 redundant PLC ~700 input.
MVD COOLING STATUS COOLING PLANT: -UPDATE of THE HYDRAULIC SYSTEM -INTEGRATION OF THE MVD COOLING CIRCUIT PATHS INSIDE THE PANDA AREA -DEFINITION OF THE.
ProtoDUNE - SP SLOW CONTROLS MEETING 11/11/2016 CERN – EP/DT
TS2 preparatory meeting
Injectors BLM system: PS Ring installation at EYETS
PMD PMD Plans Detector Issues and solution Plans for LS1 29 June 2012.
352MHz Klystron Control for the 3MeV Linac test stand
XFEL Vacuum System Commissioning
ACS news Circulator TCU: control tests in progress All cavity racks
TPC Detector Control System
CSC Electronics Installation and Commissioning Oct ‘06
Linac4 Connection Broken Line 07/08/19
Presentation transcript:

André Augustinus Infrastructure  Turbines  Radmon  Thermocouple readout  Netgear redundancy  Other cavern items  Cooling CRs  Other CR and surface items  Water cooled Wiener PS ALICE Technical Coordination06 March 2015

André Augustinus Turbines  86 racks done, 8 to be done (A-area racks)  6 spares to be distributed in rack areas  Done by next week  More spares at surface (need to buy motor/fan): ~5 units  For LS2: more convenient way to bring material to I and O racks (platform), and to C rack area (opening muon floor) ALICE Technical Coordination06 March 2015

André Augustinus Radmon  Radmon I Junction box installed yesterday (05/03, Gilles) Install ELMB box, ELMB cable and patch cables Power supply (CR3) Commissioning Operational early April  Radmon II Operational (thanks Ombretta) Ready for sector test ALICE Technical Coordination06 March 2015

André Augustinus Thermocouple readout  Beampipe and AD, rack C29  PLC solution  All material available  Installation/cabling to be done next weeks  Commissioning can be done remotely ALICE Technical Coordination06 March 2015

André Augustinus Netgear redundancy  Secondary uplinks to be cabled up (8 short Ethernet cables)  MUX power supplies being prepared by Spie  Status: TOF: HW installed, some recabling to be done SDD: HW installed, operational in non-redundant way EMC/FMD: switches installed, mux to be installed, recabling to be done V0/AD: to be installed ALICE Technical Coordination06 March 2015

André Augustinus Other cavern items  High priority (=before closure) Cable up hardware interlock for PHOS and CPV (new LV PS) Recommission water leak detection  Medium priority Install additional webcams Integration rack monitoring C33,C34  Low priority Junction boxes for ‘multipurpose’ cables Labels on rack power circuit breakers ALICE Technical Coordination06 March 2015

André Augustinus Cooling CRs  Install drainage in CR4  Check CR2 racks  Heat exchangers CR4 Most of them changed, When possible moved to bottom Several difficult to access  Close CR4 racks as much as possible (doors, panels) ALICE Technical Coordination06 March 2015

André Augustinus Other CR and surface items  Recommission CR waterleak detection  Recommission/extend CR3 rack temperature monitoring  Finalize & commission CR2 rack temperature monitoring  Connect hardware signals from new UPSes ALICE Technical Coordination06 March 2015

André Augustinus Other CR and surface items  Refurbish small room in CR3 (furniture, closure)  Clean out the storage room in front of CR3, Atelier/on buffer zone/in front of office Inventory of connectors etc.  Clean up “Revol”, update cable inventory Inventory of other items (rack/cooling/power/…)  Preparation SXL2 cleanroom and around (network, power, environment monitoring) ALICE Technical Coordination06 March 2015

André Augustinus Water cooled Wiener PS  3 incidents (2 recent, 1 ‘early days’); rupture of elbow tube pieces, leading to major water leaks  ~220 units in ALICE are concerned  Micro cracks identified on ~all samples (all experiments)  Low risk, but major impact e.g. rupture in a TRD rack could wipe out 10 supplies in one go Collateral damage probably limited (only I and O, no detectors or electronics below)  Coordination effort by PH-ESE ALICE Technical Coordination06 March 2015

André Augustinus Water cooled Wiener PS  Several scenarios: ‘roulement’ using spares (a la turbines) during TS: will not really work for us, too many different types (>20) with only limited spares. Will take very long. Bulk repair during long TS (xmas) Wait LS2 ALICE Technical Coordination06 March 2015

André Augustinus Water cooled Wiener PS  Repair options: Replace all water circuit with inox tubing Straight sections only show longitudinal cracks and have thicker walls, no real risk of rupture. Elbow sections show perpendicular cracks, thinner walls. risk of rupture. Suggestion to exchange only elbow, connector and safety valve. Cheaper, less risky intervention (will not have to touch LV part).  Organization, logistics At wiener, when carefully planned ~2-3 weeks round trip (>1000 euros for full refurbishment) At CERN, ~300 euros material. CERN (FSU) technicians trained by Wiener. Will need local test setup (hydraulic and electric) ALICE Technical Coordination06 March 2015

André Augustinus ALICE Technical Coordination06 March 2015