PROPOSED US 34 IMPROVEMENT (4-LANE EXPRESSWAY)
CARMAN RD. TO TR 111 (1350 E) – (8.1 MILES) Construction Plan Preparation – Funded (Strand Assoc.) Plan Preparation has been put on hold due to levee decertification The Phase I study and Environmental Impact Statement (EIS) will be re-opened for this section during 2012 Currently working with FHWA to the define scope of work Cost estimates will be revised as the study progresses
TR 111 TO TR 190 E OF BIGGSVILLE WITH INTERCHANGE (4.7 MILES) Construction Plan Preparation – Funded (Poepping, Stone, Bach & Assoc.) Utility Adjustments – Funded Land Acquisition – Funded Construction Engineering – Funded Construction – Funded Plan Preparation and Land Acquisition are underway Anticipate Late Fall 2012 Letting Funded through the Illinois Jobs Now! Program
TR 190 EAST OF BIGGSVILLE TO S. OF KIRKWOOD (4.5 MILES) Construction Plan Preparation – Funded (Geotech Engineering & Testing) Plan Preparation nearing completion
S. OF KIRKWOOD TO US 67 AT MONMOUTH (6.7 MILES) Construction Plan Preparation – Funded (CMT) Plan Preparation nearing completion