LHC status Monday 22 nd June 2015 Coordination: Wolfgang Hofle, Mike Lamont.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Mo morning set up 228 bunch injection (36 bunch trains), ramp, squeeze, collisions h luminosity (depending on experiments) ATLAS length scale calibration.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
LHC progress week 19 Monday 11 th May 2015 Coordination: Jan Uythoven, Massimo Giavannozzi, Mike Lamont.
LHC progress Saturday 2 nd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
LHC progress Thursday 30 th April 2015 Coordination: Mike Lamont, Wolfgang Hofle.
LHC 14 & 15 April :22: Ramp to 6.5 TeV lost due to MUFO, resulting in quench 10:30: Access during cryo recovery 16:00: Pre-cycle 17:05: RB.A78 short.
R.Giachino / M.Albert Be/op 5 April 2015 LHC Machine check out 1v1.
Monday 4 th to Friday 8 th Technical stop  Coordination: Katy Foraz  Machine back to Operations Friday evening on schedule Major cryogenics intervention.
LHC 30 th and 31 st July :10 Finish scrubbing fill 25 ns trains by operator dump. –No XPOC data … 08:40 Inject for another scrubbing fill 09:09.
Sat 18/6 – Sun 19/6 07:48 Beam dump due to spurious interlock from BIS 08:30 access BIC repair. RF intervention in parallel. 13:00 Intervention on BIC.
LHC “progress” Wednesday 29 th April 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Monday 29 October 08:48 V/dM scan CMS end of fill #3236. Check of “fast scan”. 10:06 V/dM scan finished, start of RF studies, reducing RF voltage. 11:10.
Thursday 12 th May - recovery from TS 18:30: cryo back in whole ring, also for RF cavities. Preparing to power. Problem with quench loop S23. Access to.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
LHC Status Sat Morning 18-June Bernhard Holzer, Gianluigi Arduini et al Tentative Planning: Luminosity 1092 x 1092 Access: installing low pass filter at.
LHC 23 June :07: Started injection cleaning with B1. 08:13: Fault on MKI B2. –MKI Beam 2 in P8 had a breakdown at 07:49 during the SoftStart process.
LHC 8:30 meetingEBH 1  Cryogenics recovery in point 8  Meanwhile a couple of accesses:  MKI investigation on noise in IP2  Insulation Vacuum.
Friday to Saturday 02:00: Machine closed. 09:00: Cryogenics all OK. Preparing pre-cycle. 10:00: Pre-cycle started. 11:30: Pre-cycle finished. 14:00: Beam.
LHC 1 st August :34 Dump on TDI.B2 jaw position while filling –Checks and change TDI.B2 reference position by 0.1 mm outwards 09:40 Lost cryo in.
Friday March 4 th LHC morning report the short story: from a global point of view we had basically only one access !!!
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
Monday h34: beam (1020b) lost after 10 Hz RF trim. Fill h56: XPOC to be reset by expert. 08h18: Masked QPS_STATE SIS interlocks for RB.A12.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
LHC machine status ~ Daily Summary ~ Daily beam commissioning meeting Week 42 - October 14 th, 2015 CERN, Geneva, CH M. Lamont and S. Redaelli for the.
● Morning: Physics fill with 25 bunches: – 07:00: Injection; – 07:25: Start ramp; – 09:00: End of squeeze and stable beams; – Emittances:  x1 = 3.0 
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
MP3 List of main Issues during March 2010 MP3 - Team.
Last night Lhc closed 15:00 Beam on Ti 8 /Ti2 Prepulse check synchronisation ok with LHCb /RF 17:00 Open Point 4 PC’s and RF 19:00 LBDS energy tracking.
LHC progress Sunday 3rd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
LHC progress Tuesday 28 th April 2015 Coordination: Mike Lamont, Wolfgang Hofle.
08:30 Machines in stand-by 12:30 Access in LHC for QPS and PC:  QPS quench heater power supply RB.A12  EPC for RSF2.A67B2 and RQ9.R8B1.  RCBH27.L1B2.
LHC Fri 6 & Sat 7 Nov :00 End instabilities MD, dump to refresh air at dump TDE cavern 08:00 Access for vacuum team at the TDE starting 10:30 Access.
LHC Machine Status Report Mike Lamont for the LHC team Acknowledgements: Mirko Pojer, Matteo Solfaroli, Katy Foraz et al.
Tuesday 26 th April – morning shift 08:00 Great news, cryo is back! Unluckily it was followed by many other problems, one after the other one. So, spent.
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
R.Giachino / M.Albert Be/op 30 th March 2015 LHC Machine check out 1v1.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
LHC 8 & 9 May :10: Injection kicker B1 faulty on oil level –Check in UA and RA. Leaks fixed, to be further checked in TS1 10:30: Pre-cycle started.
Thursday 20 th April 01:53 RCBV17.R7B2 tripped as happened few days ago: SIS intercepted. 05:54 Stable beams, 1380b, still RF problems B1, abort gap cleaning.
Another typical LHC day. 06:15 Fill 2000 dumped 08:44 Stable beams – fill 2001  1.675e14  1.21e11  ~2 microns normalized emittance 11:34 Beams dump.
04h36: Cryo problem in arc 81. Access. 09h14: Injection.  TI8 injection collimator setup.  Testing new sequence.  New version of vacuum application.
Saturday 14:10 Cryogenics back [26 hours 40 minutes] Pre-cycle 15:30 Beam 2 in  Interlock on TCLIB.6R2.B1. Alessandro Masi found a broken sensor, it would.
Thursday 27 th October 00:57 fill 2257 dumped during squeeze (RQTF.A67B1) 03:52 stable beams fill #2258 4:33 Dumped, problem of LBDS dilution kicker power.
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
RF Commissioning D. Jacquet and M. Gruwé. November 8 th 2007D. Jacquet and M. Gruwé2 RF systems in a few words (I) A transverse dampers system ACCELERATING.
Tuesday 3 rd October STABLE BEAMS until 12:25 when we switched to ADJUST for a EOF test for Tobias  dump B2 first and then B1.  Dump at EOF test because.
AWAKE p+ beam line HWC C. Bracco, J. Schmidt Acknowledgment: MCS, EPC, MPE, SPS-OP, BI, ABP (survey),STI, EA, ACE, RP.
Saturday Coordinators weekend: Mike Lamont, Eva Barbara Holzer
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
Friday 15th June 01:11 Injection.
Summary Friday h38: Ramp down and pre-cycle.
Tuesday Fill lost #1855 at 7:28 due to the trip of RQX.R1. This was traced to a software bug in the FGC… The Class 51 (LHC_PC) FGC software has been upgraded.
LHC Status Wed Morning 13-April R. Assmann, B. Holzer et al
A/N 26 16:00 Access finished problem with the BLM test. one crate is failing the beam permit test. Fixed. Access required in sector 78 for QPS to fix a.
Monday 11/07: Recovery Plenty of accesses.
Last 24 hours RQ5.L1 RQ4.L1 RF trip Line4B LHC status.
LHC Morning Meeting - G. Arduini
Wednesday 30th November 10:00 Access PZ33 for RP, Cryo, EPC, ELQA
Friday 14th December - morning
Wire almost entirely through beam before BLM triggers dump
Yesterday’s morning’s controls issues
Not the most productive 24 hours on record
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
Aims for the week Recover from technical stop and precycle at 10A/s
LHC Morning Meeting - G. Arduini
Wednesday h10: Programmed dump. 07h54: Injection. 200b.
Presentation transcript:

LHC status Monday 22 nd June 2015 Coordination: Wolfgang Hofle, Mike Lamont

TS1 LHC back to OP tonight at 17h00  Patrol completed this afternoon, still some outstanding items. All activities completed except: P4: activities related to BWS at 5R4 and RF commissioning  RF conditioning completed by Saturday 20 th Evening DOROS installation completed by Friday Unlock-out: P2  unlocked except DFBX3L2 (Friday morning); P4  unlocked Friday morning P5  unlocked Friday morning P6  unlocked Friday morning P8  done TS1 detailed schedule: lpc/TS2015/Global%20Schedules/Forms/AllItems.aspx lpc/TS2015/Global%20Schedules/Forms/AllItems.aspx Access constraints: lpc/TS2015/Access%20Constraints/Forms/AllItems.aspx lpc/TS2015/Access%20Constraints/Forms/AllItems.aspx 2 MAJOR TECHNICAL STOP Big thanks to Marzia Bernardini and the OSS team 22/6/2015

Weekend overview Full cryogenics no yet back – Waiting on Sector 78 arc (CS) and inner triplet In the shadowL – RF conditioning and tests – to OP 23:00 Saturday – LBDB generator change and tests – Powering tests and follow-up of issues – Transfer line tests with beam – BLM Injection Interlock Inhibit deployment – Orthogonal CMS cryogenic problem – Extensive debugging 22/6/2015 3

4

Cryogenics The initial problem is a partial breakdown of the insulation vacuum of the main 4.5 K refrigerator whose stabilization has required to install additional pumping systems. As the insulation vacuum is deteriorated, the available power is degraded too. The above problem has generated an initial delay of about 36 hours to restart the sector cooling down. The cooling down of the sectors S78/S81 at ~2 K should be ended for Sunday noon. But!!! We have to stabilize the sector S78 and complete IT cooling down, DBF & LSS levelling. 22/6/ Gerard Ferlin

RF conditioning RF handover to OP Saturday evening – Some problems starting ADT: water cooling for tetrode amplifiers - access 23:20 access on Friday in PZ45 for RF-insulation vacuum interlock problem… – RF cavities fully conditioned conditioning started 6 a.m. Saturday first two cavities for LLRF by 15:00 12 cavities & LLRF ready by 18:00 16 cavities & LLRF ready by 23:00 – LLRF controllers re-started feedbacks set-up – Some issues linked to new front-end processors – Estimate for future technical stops 24 h from start of conditioning to handover of RF (if cavities emptied) Philippe, Helga, Pierre, Andy for the RF team 22/6/2015 6

ADT – Switched ON, sent to injection  ok – D.V. “it was working when I Ieft it … “ Point 4 cooling problem – issue with valve on demineralised water – piquet intervention during night, ok after intervention on Sunday a.m. (CV) – affected all RF and half of ADT (right of IP4) – RF and ADT being switched ON now Power amplifier changed on Sunday 22/6/ Looking good

LBDS Friday evening – Nicolas Magnin and Nicolas Voumard in point 6 investigating an issue with LBDS, one generator was in error. Etienne - Saturday morning – We have a major problem with one of the LBDS generator (broken diode in the free-wheel circuit). Diode stack broke at 7 TeV during an energy scan for re-validation of the system at the end of the TS. – Generator will have to be exchanged Saturday with the lengthy re-commissioning of the LBDS afterwards. Generator change done Conditioning with energy scan completed (and then repeated) on Sunday - delay values different? (see over) 4 h run at > 7 TeV 22/6/ Big thanks to Nicolas Magnin, Nicolas Voumard and team

LBDS – new generator energy scan 22/6/2015 9

BLMs Deployed firmware for “Injection Interlock Inhibit” in two crates – Tests shown correct behaviour. Apart from the cases in the previous messages, tested also that it does not trigger for when each condition needed is wrong. – In short for the two crates at injection if an InhibitTime is set to a time value > 0, the beam energy is below 460 GeV and the HIX.W20-CT (Warning injection 20 ms) event is sent then all interlocks going to the BLM-MSK output will be inhibit for the time equal to that set. – We leave the new version deployed at SR2.I and SR8.I crates, but with the InhibitTime = 0, i.e. it is inactive. Christos Zamantzas and Stephen Jackson 22/6/

Beam to TEDs Beam down both transfer lines up to TEDs TI2 We checked the TI 8 steering with 6 bunches. Situation before 4 amps change and after, with fine corrections in the region upstream the downstream TED where the first two collimators are located. Looks OK now, some fine tuning to be done in the region of the collimators downstream the TED when we inject into LHC. Wolfgang Bartmann Chiara Bracco 22/6/

Powering tests RQ10.L1B2 – FAST Abort at Nominal Current and call the piquet to check if the FWD fault doesn't appear anymore (to be done with an FPA from PIC) RQ8.L4B1 – FAST Abort at Nominal Current and call the piquet to check if the FWD fault doesn't appear anymore (to be done with an FPA from PIC) RQ5.R4B1 – FAST Abort at Nominal Current and call the piquet to check if the FWD fault doesn't appear anymore (to be done with an FPA from PIC) RQ7.L1B2 - Go to flat top and call us for checking I_MEAS versus I_OUT S78 - Launch precycle and use table for controlling converters asap RCBV20.L8B1 - PCC and PNO.d1 RSD1.A34B1 - PIC2, PLI3.b1 (no need to perform local measurements) RB.A56 - PIC2 and check that the switch opens correctly, PCC and check current lead signals, A8R5 and B8R5 signals and see that they are alive (infos to be reported to MP3 who analyses) RQTF.A34B1 – PCC.5 and PIC2_Circuit_quench_via_QPS RB.A81 - PIC2 CIRCUIT QUENCH VIA QPS RQD.A81 - PIC2 CIRCUIT QUENCH VIA QPS RQF.A81 - PIC2 CIRCUIT QUENCH VIA QPS RTQX2.L2 – PCC.T4, PIC2 and PNO.d12 For MP3, please call Per Hagen today and Michele Modena tomorrow. For PIC, please call Ivan Romera. For EPC, the is again available 24/7. 22/6/ Mirko Pojer Fully complete (except S78) Number of issues resolved on the way

Once beam is back… 22/6/

Followed by scrubbing 22/6/