The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,

Slides:



Advertisements
Similar presentations
MICE RF and Coupling Coil Module Outstanding Issues Steve Virostek Lawrence Berkeley National Laboratory MICE Collaboration Meeting October 26, 2004.
Advertisements

The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
All experimenters meeting – July 7, 2014 LHC Crab Cavity Overview Tom Nicol – Fermilab All Experimenter’s Meeting July 7, It’s a group effort –
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Cryomodule Concept for the ODU RF Dipole Crab Cavity Tom Nicol* - Fermilab December 10, 2013 * With lots of help from HyeKyoung, Tom J, Shrikant, Ofelia,
FNAL-SCRF 会議報告 1. Cryomodule, Plug-compatible Interface ( 大 内) 2. High Pressure Code, 5K Shield (Tom Peterson)
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Meeting summary (so far, Monday morning) and comments Tom Peterson, Camille Ginsburg (FNAL), Alex Ratti (LBNL) Crab Cavity Meeting, CERN, 1-6 Aug 2013.
Ofelia Capatina on behalf of the CERN specification team
SPL cryo-module conceptual design review Cavity, helium vessel and tuner assembly N. Valverde, G. Arnau, S. Atieh, I. Aviles, O. Capatina, M. Esposito,
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
23 Jan 2007 LASA Cryogenics Global Group 1 ILC Cryomodule piping L. Tavian for the cryogenics global group.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Internal Cryomodule Instrumentation ERL Main Linac Cryomodule 10/10/2015 Peter Quigley, MLC Design Review.
WP3 Required interfaces for cryostat design / integration Patxi DUTHIL SPL 3 rd Collaboration Meeting, CERN, Geneva November 12 th 2009.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
Type IV Cryomodule Proposal (T4CM) Don Mitchell, 16 JAN 2006.
Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
1 HIGH ENERGY ACCELERATOR RESEARCH ORGANIZATION KEKB Review Committee/ NAKAI Hirotaka KEK Crab Cavity - Cryogenics - KEKB Crab Cavity Group - presented.
Date 2007/Oct./25 FNAL-GDE-Meeting Global Design Effort 1 Cryomodule Report N. Ohuchi KEK 1.Cryomodule & Cryogenics KOM 2.GDE-meeting discussion I.Interface.
Workshop Objectives & Highlights from Daresbury Meeting Erk Jensen, CERN.
Summary ( Cryomodule, Plug-compatible Interface) Norihito Ohuchi.
Date 2007/Oct./23 FNAL-GDE-Meeting Global Design Effort 1 Cryomodule Interface Definition (FNAL-GDE-Meeting) N. Ohuchi.
RF-Dipole Cavity: Processing and RF Measurements Procedure
Shrikant_Pattalwar TTC 2015 Dec 1, 2015 SLAC 1 Horizontal Tests in a Vertical Cryostat Shrikant Pattalwar STFC Daresbury Laboratory UK.
HL-LHC Crab Cavity Review Debriefing Comments from LARP June 30, 2014.
Alignment and assembling of the cryomodule Yun He, James Sears, Matthias Liepe.
Cryostat & LHC Tunnel Slava Yakovlev on behalf of the FNAL team: Nikolay Solyak, Tom Peterson, Ivan Gonin, and Timergali Khabibouline The 6 th LHC-CC webex.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
The integration of 420 m detectors into the LHC
LHC Cryostat evaluation Nikolay Solyak Thanks Rama Calaga, Tom Peterson, Slava Yakovlev, Ivan Gonin C11 workshop. FNAL, Oct 27-28, 2008.
HiLumi-LHC/LARP Crab Cavity System External Review – May Work partly supported by the EU FP7 HiLumi LHC grant agreement No and by the.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
SPL cryomodule specification meeting, CERN 19th October 2010 SPL cryomodule specification: Goals of the meeting SPL cryomodule specification: Goals of.
The SPL Short Cryo-module: Status Report V.Parma, CERN, TE-MSC On bahalf of the Cryomodule development team SPL seminar December 2012, 6-7 December 2012,
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
Page 1 CRYOMODULE 650 (TESLA Style) Stand Alone Tom Peterson and Yuriy Orlov Collaboration Meeting 25 Jan 2011.
Ralf Eichhorn CLASSE, Cornell University. I will not talk about: Cavities (Nick and Sam did this) HOM absorbers (did that yesterday) Power couplers (see.
Shrikant_Pattalwar ICEC 26, March 7-11, 2016, Delhi 1 Horizontal Tests in a Vertical Cryostat Shrikant Pattalwar STFC Daresbury Laboratory UK.
Integration and Cold Testing of the CW ERL Cryomodule at Daresbury Shrikant Pattalwar ASTeC, STFC, Daresbury Laboratory (UK) On behalf of ERL Cryomodule.
Wish list from ESS Christine Darve H-ECCTD Kick-off meeting 16 March
Spoke section of the ESS linac: - the Spoke cryomodules - the cryogenic distribution system P. DUTHIL (CNRS-IN2P3 IPN Orsay / Division Accélérateurs) on.
LARP Crab Cavities Cryomodule Integration Meeting Final Notes A.Ratti LBNL.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
1 IPN Orsay / Division Accélérateurs The Spoke cryomodule Vacuum aspects P. DUTHIL on behalf of the IPNO team ESS Lund February 19 th 2013.
ILC : Type IV Cryomodule Design Meeting Main cryogenic issues, L. Tavian, AT-ACR C ryostat issues, V.Parma, AT-CRI CERN, January 2006.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
Crab Cavity Technical Coordination meeting:
CERN – Zanon discussions
Plans towards CC in the LHC a US – centric perspective
at STFC Daresbury laboratory
TTC Topical Workshop - CW SRF, Cornell 12th – 14th June 2013
SPS cryogenic proximity equipment and SM18 validation
LARP Vertical Test Facility
HL-LHC-UK: UK contribution to HL-LHC Crab Cavities and evolution
Hollow e- lens, Cryogenic aspects
WP10.3 LHC Crab Cavities Overview EUCARD SRF Annual Review
CERN Cryomodule Requirements for Crab Cavities
Superconducting RF Crab Cavities
UK RFD Pre-Series cryomodule
HIE-LINAC status report
ESS elliptical cryomodule
Cryomodule Assembly Plan
Cryomodules Challenges for PERLE
CEPC-650MHz Cavity Cryomodule
Magnetic shielding and thermal shielding
SNS PPU Cryomodule Instrumentation
Presentation transcript:

The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme, Grant Agreement Cryomodule for Crab Cavity Tests with SPS Cryomodule for Crab Cavity Tests with SPS Shrikant Pattalwar Accelerator Science and Technology Centre STFC Daresbury Laboratory, UK 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013, Daresbury

Acknowledgements 2 STFCASTeC, Technology, University of Lancaster CERN Various Departments LARP ODU+SLAC, BNL, FNAL This presentation is on behalf of the members of the Global WP4 team Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

Contents Factors Influencing Design Requirements Achievements so far … Concept designs for Helium Vessel and Cryomodule Work in Progress Future Plans Conclusion 3Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

Requirements Operating Temperature Magnetic shielding Helium Vessel Couplers and Interfaces Tuner mechanism Dynamic Heat Load …. Operating Temperature Magnetic shielding Helium Vessel Couplers and Interfaces Tuner mechanism Dynamic Heat Load …. 1. Cavity Two beam pipes Heat load due to beams Helium Vessel Geometry Internal Layout …. Two beam pipes Heat load due to beams Helium Vessel Geometry Internal Layout …. 2. LHC External Geometry Third beam pipe ( SPS Bypass) Coupler Orientations Integration with Infrastructure Operation External Geometry Third beam pipe ( SPS Bypass) Coupler Orientations Integration with Infrastructure Operation 3. SPS Layout Requirements for the cryomodule are influenced by various Factors 4 Talk # 92 by Rama Calaga and # 95 Alex Ratti Talk # 100 by Alick Mcpherson # 106 by Ofelia Capatina Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

Requirements continued 5 Cooling Capacity at various temperatures Cooling Processes Ports and Interfaces Operating modes Cooling Capacity at various temperatures Cooling Processes Ports and Interfaces Operating modes 4. Cryogenic Services Mechanical Design Safety and Pressure Relief Volumes, pipe sizes Methods of QC/QA Mechanical Design Safety and Pressure Relief Volumes, pipe sizes Methods of QC/QA 5. Regulations and directives 6. Other Intermediate Tests (SM18) Intermediate Tests (SM18) Assembly Procedures Assembly Procedures Instrumentation Instrumentation Cost Cost R&D needs R&D needs Talk # 102 by Laurent Tavian Talk # 105 by Ofelia Capatina Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

6 Helium Vessel UK 4-Rod Cavity Cavity in He Vessel Parts of the Vessel Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury Courtesy : Graeme Burt and Ben Hall, ULAN Saclay-II type tuner SPS beam pipe LHC (dummy) beam pipe

7 Cryoperm magnetic shields OVC to coupler ISO K 500 spool pieces Tuners 2 Phase He line Top fill LHe line Bottom fill LHe line Motor magnetic shield LHe level probes Pipework for liquid nitrogen connections Thermometry and wiring for entire string Fully Assembled Cavity String (4R) Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury Courtesy : Tom Jones (STFC)

8 Helium Vessel ODU Dipole cavity BNL Double QW cavity Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury Courtesy : HyeKyoung Park (ODU) Courtesy : Ofelia capatina (CERN)

Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury 9 Cryomodule Schematic (P&ID) Courtesy : Andy May (ASTeC)

mm 800mm 1520mm Cryogenics interface Additional ports for LOM extraction/instrumentation 2mm thick Mu Metal Magnetic shield Module positioning system 1050 Aluminium Thermal shield (80K) Cooling loop TBD Cryomodule Concept More details in - Conceptual design of a Cryomodule for Crab Cavities for HiLumi-LHC S. Pattalwar, et al, MOP 087, SRF 2013, Paris More details in - Conceptual design of a Cryomodule for Crab Cavities for HiLumi-LHC S. Pattalwar, et al, MOP 087, SRF 2013, Paris Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury Design features simplifies the assembly procedures provides sufficient access to internal components during assembly and after installation FPC is used as the main support for the cavity string.

Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury11 Compatibility with SPS Infrastructure Requirements Concept Design

12 1Clean Room Operations Assemble cavity string Couplers assembled at 90 o Beam pipe closed with gate Valves 2Outside the clean Room Load the cavity String from Side 3Align the string with the vacuum chambe r 4. Lift and assemble with top plate of the vacuum chamber Assembly Sequence – Proposal 1 (Side Loading) Assembly Sequence – Proposal 1 (Side Loading) Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

13 ISO K clamp 80K 300K Mu Metal magnetic shield (blue). 80K thermal shield (green). 20mm allocated for MLI Final Assembly Final Assembly Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

1Clean room Operations Cavity, Coupler and Beam pipe 2Outside the clean Room Mounting on the top plate 3 Outside the clean Room Assembly of the cold parts 4 Load from the top into the vacuum chamber Assembly Sequence – Proposal 2 (Top Loading Assembly Sequence – Proposal 2 (Top Loading 14Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury Courtesy : Ofelia capatina (CERN)

Final Assembly (Top Loading ) 15Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

16 RF Input Cryo services Sliding support table Cryomodule in SPS Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury Conclusion First level constraints defined by SPS layout have been successfully overcome The design appraocah simplifies the assembly procedures provides sufficient access to internal components during assembly and after installtion reduces overall manufacturing cost

Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury17 Common Design Approach UK 4-Rod US Dipole US Double QW Conclusion – A common design approach to accommodate all the 3 cavity designs has been successfully developed. External Envelope Cryogenic Interface Cryogenic Process Alignment (external and Internal) ……. Challenges – Couplers and Tuners and their locations for the three designs are different. For illustration only

18 Work In Progress Coupler designs for HOMs and LOMs and their integration with Infrastructure Magnetic Shielding Alignment Integration with Cryogenics and heat load management Switch over with the SPS BY-PASS or with other cryomodule Safety, Pressure Vessel Regulations etc. Tests at SM Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

19 Heat Load Budget

Compliance with Regulations - PED 20 Maximum LHe volume < 100 L Maximum Operating Pressure 0.8 barG Max He pressure 0.43 barG Max pipe diameter (ID) < 25 mm Max Pressure 5 bar?? Category 0 for LHC Category 1 for SPS tests CC in LHC Pmax 0.5 bar Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

21 Concept DesignEngineering Design Manufacturing Acceptance Tests March 2014 Commissioning Future Plan (Expectations) Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury Jan 2016

22Conclusion 1. First level constraints defined by SPS layout have been successfully overcome 2.A common design approach to accommodate any of the 3 cavity designs has been successfully developed 3.Overall design process is at an advance stage. 4.Most of the remaining issues are well understood and solutions are being worked out through collaborative efforts 5. WP4 Global collaboration is working well and advancing in a right direction Shrikant Pattalwar 3rd Annual Hi-Lumi Meeting Nov 11-15, 2013 Daresbury

Thank You 23/