MICE CM39 St Catherine’s, Oxford, 26 June 2014 Paul Soler Instrumentation Global Commissioning Plan.

Slides:



Advertisements
Similar presentations
Detector Systems Update MICO March 17, MICE Detector Systems  CKOV u Mississippi RAL  TOF0/1 u Hamamatsu PMT assemblies show an increasing.
Advertisements

MAUS Update Adam Dobbs, MICE Project Board, 16 th April 2015.
Software Summary Database Data Flow G4MICE Status & Plans Detector Reconstruction 1M.Ellis - CM24 - 3rd June 2009.
MICE Collaboration meeting May 31 st – June 3 rd 2009 RAL Tim Hayler, Andy Lintern DRAFT SEQUENCE OF EVENTS STEPS
Linda R. Coney – 24th September 2009 MOM Update End of Sept Run Linda R. Coney 05 October, 2009.
Mar 31, 2005Steve Kahn -- Ckov and Tof Detector Simulation 1 Ckov1, Ckov2, Tof2 MICE Pid Tele-Meeting Steve Kahn 31 March 2005.
Online Reconstruction Update Linda R. Coney UCR Mar 25, 2010.
Online Reconstruction Update Linda R. Coney UCR Dec 17, 2009.
Luminosity Monitor Commissioning MICE Collaboration Meeting March 2010 Paul Soler, David Forrest Danielle MacLennan.
Linda R. Coney – 24th April 2009 Online Reconstruction & a little about Online Monitoring Linda R. Coney 18 August, 2009.
MICE: The International Muon Ionization Cooling Experiment Diagnostic Systems Tracker Cherenkov Detector Time of Flight Counters Calorimeter Terry Hart.
1 Analysis code for KEK Test-Beam M. Ellis Daresbury Tracker Meeting 30 th August 2005.
Y. Karadzhov MICE Video Conference Thu April 9 Slide 1 Absolute Time Calibration Method General description of the TOF DAQ setup For the TOF Data Acquisition.
Detector Systems Update MICO March 3, MICE Detector Systems  CKOV u CKOV humidity (HIH4000) and temperature (LM35) sensors in hand for installation.
Pierrick Hanlet MICO June 6, 2011 MICE Operations Manager Report.
TOF calibration Y. Karadzhov. Y. Karadzhov, MICE CM26 24 March Slide 2 TOF Calibration - Trigger TOF1 TOF 0 TOF 1 TOF 2 The blue line encloses the calibrated.
1 G4MICE Analysis of KEK Test Beam Aron Fish Malcolm Ellis CM15 10th June 2006.
Jun 27, 2005S. Kahn -- Ckov1 Simulation 1 Ckov1 Simulation and Performance Steve Kahn June 27, 2005 MICE Collaboration PID Meeting.
Detector Systems Update MICO March 10, MICE Detector Systems  CKOV u No update  TOF0/1 u Tests with laser injection system progressing. u Tests.
CMPB Alain Blondel 14 April STATUS OF MICE.
Detector Systems Update MICO Feb 25, MICE Detector Systems  CKOV u CKOV installation planned during March shutdown u Cable issues resolved. Geneva.
1 M. Bonesini - CM 25 RAL 5/11/09 PID status report M. Bonesini Sezione INFN Milano Bicocca.
MICE magnetic measurements Sequence of events and MICE hall movements Alain Blondel – 10-April 2012 revision from 13 December 2012.
Physics Program and Runs: Autumn 2011 & Step IV V. Blackmore MICE Project Board, 08/03/12.
1 HBD Commissioning (II) Itzhak Tserruya HBD group meeting November 28, 2006 Progress from October 3 to November 28, 2006.
Emittance measurement: ID muons with time-of-flight Measure x,y and t at TOF0, TOF1 Use momentum-dependent transfer matrices to map  path Assume straight.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
Detector Systems For May/June Run MICE Video Meeting April 24, 2008.
MICE Beam-line and Detectors Status Report 16 th October 2009 Chris Booth The University of Sheffield.
ICHEP 2012 Melbourne, 7 July 2012 Paul Soler on behalf of the MICE Collaboration The MICE Beam Line Instrumentation (Trackers and PID) for precise Emittance.
Tracker Summary Alan Bross MICE CM October 10, 2007.
Alain Blondel MICE VC 12 March 2009 Brief MICE news 1. Decay solenoid: operations will restart in early July. Criteria for acceptance have been specified.
11 Nov 2008PC Analysis PC Schedule 2008 Tuesdays fortnightly 9 September  23 September  2 October  CM22  11 November  25 November 9 December.
Online Reconstruction 1M.Ellis - CM th October 2008.
D0 Status: 01/14-01/28 u Integrated luminosity s delivered luminosity –week of 01/ pb-1 –week of 01/ pb-1 –luminosity to tape: 40% s major.
1 KEK test-beam software progress Malcolm Ellis MICE Video Conference 4 th May 2005.
1M. Ellis - NFMCC - 31st January 2007 MICE Analysis.
1 A first look at the KEK tracker data with G4MICE Malcolm Ellis 2 nd December 2005.
Transversity Readiness and Timeline Xiaodong Jiang, March 17th, This document specifies the overall readiness for Hall A experiments E06-010/E
Linda R. Coney – 5 November 2009 Online Reconstruction Linda R. Coney 5 November 2009.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
FPD STATUS Carlos Avila Uniandes/UTA 1. FPD overview 2. Roman pot and detector status 3. FPD readout integration status 4. Software status 5. Stand-alone.
Database David Forrest. What database? DBMS: PostgreSQL. Run on dedicated Database server at RAL Need to store information on conditions of detector as.
CLAS12 CalCom Activity: a progress report V. Burkert, D. Carman, R. De Vita, D. Weygand CLAS12 meeting, June 14 th 2012.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
SPOKESMAN’S UPDATE K. Long Imperial College London/STFC.
M. Bonesini – CM 291 PID detectors summary M. Bonesini Sezione INFN Milano Bicocca.
Luminosity Monitor Design MICE Collaboration Meeting 31 May 2009 Paul Soler.
Low Momentum dE/dx Testbeam H.P. 7/24/98. Goals for Spectrometer are based on tracking and PID –Multiparticle correlation –production of particle species.
Software Overview 1M. Ellis - CM21 - 7th June 2008  Simulation Status  Reconstruction Status  Unpacking Library  Tracker Data Format  Real Data (DATE)
ch/~bdl/lepc/lepc.ppt 1 MICE Status and Plans Rikard Sandström Université de Geneve International Scoping Study CERN,
NBI2006 Starting OPERA data-taking with the CNGS beam D.Autiero IN2P3/IPN Lyon 5/9/2006.
1 Updated Run Plans. K.Tilley, MICO, 07/02/08 - pre-commissioning - Target, - beamline functionality - detectors, particle production - decay solenoid.
1 paul drumm; Date; Title …project report …more comments paul drumm february 2005.
MAUS Status A. Dobbs CM43 29 th October Contents MAUS Overview Infrastructure Geometry and CDB Detector Updates CKOV EMR KL TOF Tracker Global Tracking.
Linda Coney MICO June 6, 2011 MICE Online Report.
1 UK Project Finance & Schedule. Overview Finance  Budget Setting 2013/14  June Finance  Forward look to complete stepVI Schedule  Overview 2.
Project Managers Report CM38 – Napa Roy Preece 24th February 2014.
Calorimeter Status Electronics Installation and Commissioning
L. Coney UC Riverside MICE CM32 – Glasgow – June 2012
Online Monitoring : Detector and Performance check
Commissioning and Calibration Strategies for Micromegas Vertex Tracker
MICE Collaboration Meeting Saturday 22nd October 2005 Malcolm Ellis
Chris Rogers, ASTeC, Rutherford Appleton Laboratory
Luminosity Monitor Status
Chris Rogers, ASTeC, Rutherford Appleton Laboratory
MICE Collaboration Meeting
Global PID MICE CM43 29/10/15 Celeste Pidcott University of Warwick
Chris Rogers, ASTeC, Rutherford Appleton Laboratory
How to turn on MICE Step IV
Presentation transcript:

MICE CM39 St Catherine’s, Oxford, 26 June 2014 Paul Soler Instrumentation Global Commissioning Plan

2 Commissioning Plan o We need to provide an instrumentation commissioning plan before October to report to the MICE Project Board (and for our sake) −We need to define any remaining hardware that needs to be carried out in each detector −We need to define any calibrations, alignments... −We need to specify what software still needs to be implemented to be able to commission −We need to define the commissioning tasks for each detector −I will give examples of items that might go in MICE CM39, 26 June 2014

3 TOF o Remaining hardware: −Might need to shield with Armco plates TOF1 – need to carry out simulations to check field −Make more permanent support structure o Software: −Already in good shape o Calibrations: −Procedures well defined: ~10 hours data o Commissioning: −No special commissioning required since already working routinely MICE CM39, 26 June 2014

4 CKOV o Remaining hardware: −No expected changes to hardware o Software: −Need to implement digitisation o Calibrations: −Need pedestal run −Typical pion calibration P D2 =280 MeV/c −Electron runs for 1PE and multi-PE distributions o Commissioning: −Equalise gains of PMTs −Might need to monitor gains during data taking

5 KL MICE CM39, 26 June 2014 o Remaining hardware: −No expected changes to hardware −Support EMR, KL – remove iron channel plates o Software: −Need to implement digitisation and compare data o Calibrations: −KL pedestal stability with cosmics (trigger TOF2) −Electron runs for energy calibration? o Commissioning: −No special commissioning since operational −Might need to monitor pedestals and gains during data taking

6 EMR MICE CM39, 26 June 2014 o Remaining hardware: −Change PMTs in October −Support EMR, KL – remove iron channel plates −Move electronics to approved rack in hall o Software: −Need to implement digitisation and compare to data o Calibrations: −Three weeks of continuous cosmics running to calibrate 2832 channels −Electron runs for energy calibration? o Commissioning: −Detailed commissioning plan required

7 Tracker MICE CM39, 26 June 2014 o This is the detector that requires the most work o Remaining hardware: −Installation of tracker in spectrometer and hall – detailed plan developed o Software: −Validation reconstruction ongoing o Calibrations: −Need to develop detailed calibration and alignment plan −Running with cosmics for a few weeks −Running with straight and curved tracks for alignment o Commissioning: −Detailed commissioning plan required

8 Commissioning Plan Document MICE CM39, 26 June 2014 o I will set up a document that will become the commissioning plan document for each detector, with relevant sections: −TOF: Maurizio? −CKOV: Lucien? −KL: Domizia? −EMR: Alain/Francois/Yordan (assume Ruslan left)? −Tracker: Melissa/David Adey/Alan Bross/Adam Dobbs/ o General editor: PS (you will hear from me) o Timeline: ~August?