DoE Review June 6-7, 2000 Installation and Commissioning of the D0 Detector Overview since last review Organization Current status Installation sequence,

Slides:



Advertisements
Similar presentations
Project Management Concepts
Advertisements

DoE Review June 6-7, 2000 Current Detector Configuration June 6, 2000  Solenoid, Central Preshower installed in central bore  A-layer MDTs installed.
All DØ Meeting December 1, 2000 Uncle DØ Needs you!!! Commissioning Status & Plans Jae Yu All DØ Meeting Dec. 1, 2000 What have we been doing? What is.
The LHCf experiment Measurement of Photons and Neutral Pions in the Very Forward Region of LHC Letter Of Intent: May 2004 Technical report: September 2005.
1 Timescales Construction LCR MICE Beam Monitoring counters + DAQ My understanding Jan 07 Feb 07 Mar 07 Apr 07 May 07 Jun 07 Jul 07 Aug 07 Sep 07 ISIS.
WBS 1.7: AFE II Project Cost and Schedule Alan Bross DZero Run IIb AFE II Director’s Review April 13, 2005.
13 January All Experimenters’ MeetingAlan L. Stone - Louisiana Tech University1 Data Taking Statistics Week of 2003 January 6-12 We had to sacrifice.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
NuMI NuMI Overview NBI 2002 S. Childress (FNAL) 14 March ‘02 NuMI / MINOS Overview.
Requirements Review – July 21, Requirements for CMS Patricia McBride July 21, 2005.
M. Gilchriese ATLAS Upgrade Introduction January 2008.
1 Kenneth Osborne, 9/14/07 Inter Group communications at the Advanced Light Source. Overview of the different methods of communication between different.
Silicon Inner Layer Sensor PRR, 8 August G. Ginther Update on the D0 Run IIb Silicon Upgrade for the Inner Layer Sensor PRR 8 August 03 George Ginther.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
November 18, 2008 John Haggerty 1 PHENIX In Run 9 John Haggerty Brookhaven National Laboratory.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
Collaboration Mtg Cotober 11, 2000 Installation Status Opening Remarks Overview, logistics Recent events, status Outlook, concerns Conclusions Jon Kotcher.
Tariq J. Solaija, NCP Forward RPC EDR, Tariq Solaija Forward RPC EDR The Standard RPC for low  regions Tariq J. Solaija National Centre for.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
09/03/2010 ADO-PO section meeting Beam Pipe Extraction/Insertion R. Vuillermet.
The Commissioning of the CLAS12 Detector V. Burkert, D. Carman, R. De Vita, D. Weygand CLAS12 workshop, June 21 st 2011.
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
22 June 2000 D  NIU Workshop S. Doulas From Detector to Ntuples: Muons Steven Doulas Northeastern University Boston, MA D0 Muon Upgrade Group.
M&O status and program for ATLAS LAr calorimeter R Stroynowski (on vacations)
Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer 8/12/2008 1David Lissuaer, Santa Cruz Meeting.
17 February All Experimenters’ MeetingAlan L. Stone - Louisiana Tech University1 Data Taking Statistics Week of 2003 February Dedicated some.
D0 Collab Mtg Feb 7, 2001 D0 Detector: Status for Run 2 Wistful reminiscences Near term: Roll in, detector status, next few weeks Latest from Beams Division.
Online Software 8-July-98 Commissioning Working Group DØ Workshop S. Fuess Objective: Define for you, the customers of the Online system, the products.
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
Fermilab PMG Jan 20, 2000 Reconsideration of the Installation at D0  Overview  Major constraints  Basics of old, new schemes  Some details on each.
Forward Muon Installation and Commissioning Dmitri Denisov Fermilab Director’s review 7/12/1999 Plan Forward muon detectors Mini-drift tubes installation.
L0 Technical Readiness Review-Electronics Installation Linda Bagby L0 Electronics Installation  System Electronics Overview u Low Voltage s Filter.
LHCf: installation & commissioning Measurement of Photons and Neutral Pions in the Very Forward Region of LHC Oscar Adriani INFN Sezione di Firenze - Dipartimento.
DØ Online16-April-1999S. Fuess Online Computing Status DØ Collaboration Meeting 16-April-1999 Stu Fuess.
D0 Status: 01/14-01/28 u Integrated luminosity s delivered luminosity –week of 01/ pb-1 –week of 01/ pb-1 –luminosity to tape: 40% s major.
All Experimenters MeetingDmitri Denisov Week of July 7 to July 15 Summary  Delivered luminosity and operating efficiency u Delivered: 1.4pb -1 u Recorded:
18 March 2002 All Experimenters’ Meeting Alan L. Stone Louisiana Tech University 1 DØ Status: 03/11 – 03/18 Week integrated luminosity –1.1 pb -1 delivered.
D0 PMG 6/15/00 PMG Agenda June 15, 2000  Overview (Tuts) u Detector status u Reportable milestones u Financial status u Summary  Response to DOE review.
Transversity Readiness and Timeline Xiaodong Jiang, March 17th, This document specifies the overall readiness for Hall A experiments E06-010/E
D0 Status: 04/01-04/08 u Week integrated luminosity –1.7pb -1 delivered –1.5pb -1 utilized (88%) –1.1pb -1 global runs u Data collection s global data.
DoE Review June 6, 2000 Cost Estimate  New Cost Estimate u Manpower Costs (Op. SWF) u Equipment Costs (Eq. M&S) u Contingency  Conclusions Mike Tuts.
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Kurt Krempetz (Director's Review - Dec. 7, 99) 1 Mechanical Infrastructure Kurt Krempetz Introduction Existing Systems New Systems Schedule Manpower Conclusions.
DoE Review January 1998 Online System WBS 1.5  One-page review  Accomplishments  System description  Progress  Status  Goals Outline Stu Fuess.
Detector Decommissioning Related Activities at DØ George Ginther Fermilab and University of Rochester 23 January 2012.
Muon Tracker Responsibilities This Year South arm commissioning through this year’s run Analysis Software oversight and development North Arm station 2.
Aurelio Juste (Fermilab) Rencontres de Moriond, March OUTLINE Tevatron Run 2 The upgraded DØ Detector Status Performance First Physics Results Outlook.
1 Integration and Milestones Elton Smith Hall D Detector Review October 20-22, 2004.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
D0 PMG February 15, 2001 PMG Agenda February 15, 2001  Overview (Weerts) u Detector status u Reportable milestones u Summary  Operations Organization.
D0 PMG 2/3/00 PMG Agenda Feb 3, 2000  Overview u Project Manager’s Report – Tuts u Fallback options – Weerts  Silicon Support Cylinder Modifications.
Upgrade PO M. Tyndel, MIWG Review plans p1 Nov 1 st, CERN Module integration Review – Decision process  Information will be gathered for each concept.
Installation of the T600 at Fermilab CSN2, September 22,
Director’s Review Dec 1999 DO Timeline Old Version J F M A M J J A S O N D J F M D Install silicon front-end ICD FPS Lum (L0) CFT install/hookup.
Collaboration Mtg April 14, 2000 DO Timeline J F M A M J J A S O N D J F M D Install silicon front-end ICD FPS Lum (L0) CFT install/hookup 1/2.
D0 PMG 4/19/01 Completed Reportable Milestones MilestoneBaselineActualVar. H Half-Wedge Fabrication 20% Complete 10/15/99 0 w 3 Chip Ladder Fabrication.
All Experimenters MeetingDmitri Denisov Week of July 22 to July 29 D0 Summary  Delivered luminosity and operating efficiency u Delivered: 3.1pb -1 u Live:
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
SPHENIX MECHANICAL D. Lynch August 21, /15/2014sPHENIX Mechanical Design.
Eric Prebys, Fermilab Program Director, LARP July 10, 2012.
Fernanda G. Garcia, Steve Dixon, Andy Stefanik, Justin Tillman, John Voirin SBN Far Detector Installation & Integration.
Online Software November 10, 2009 Infrastructure Overview Luciano Orsini, Roland Moser Invited Talk at SuperB ETD-Online Status Review.
SuperB Integration SuperB Experimental hall. Related topics of Slac D&D activities.
Nikhef Scientific Meeting 2000Onne Peters D0 Muon Spectrometer December 14-15, Amsterdam Onne Peters Nikhef Jamboree 2000.
Arnd Meyer (RWTH Aachen) Sep 8, 2003Page 1 Integrated Luminosity Total data sample on tape with complete detector > 200pb -1.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
21 Mar 2007ALICE - Paul Dauncey1 ALICE CR07: Installation and Commissioning Paul Dauncey Material from: L. Leistam: “ALICE Status” W. Riegler: “Commissioning.
Presentation transcript:

DoE Review June 6-7, 2000 Installation and Commissioning of the D0 Detector Overview since last review Organization Current status Installation sequence, logistics Schedule, timelines Commissioning status, plans Conclusions Jon Kotcher Brookhaven National Laboratory D0 Collaboration DoE Review Fermilab June 6-7, 2000

DoE Review June 6-7, 2000 Overview of Last Six Months  Director’s Review of Installation & Commissioning, December 7-8, 1999 u Extensive review s Detectors, electronics, infrastructure, DAQ, trigger, online,… u Much learned, useful exercise  Detailed reconsideration(s) of installation sequence in recent months u Split silicon allows installation with end calorimeters & end irons on platform s Removes constraint of remaining in “open” configuration for its installation –Large pieces can be put in final position earlier s Can be installed, serviced, removed (upgrades) in Assembly or Collision Hall –Same 39” gap between calorimeters exists in both locations, access not an issue u Uninterrupted hookup & commissioning time where it matters most s Full six months prior to roll in u Chosen sequence relieves pressure on end game s Resources, manpower needs distributed more evenly in time s Early confrontation of potential difficulties, recovery  Cognizance of fixed end date an important ingredient in our deliberations u March 1, 2001 taken quite seriously u Carefully optimize remaining time in order to roll in complete, physics-ready detector for Run 2

DoE Review June 6-7, 2000 Organization  Installation Core Group: u J. Kotcher (APM - Installation & Commissioning) u R. Hance (Project Engineer – Electrical) u K. Krempetz (Project Engineer – Mechanical) u D. Miller (Technical Supervisor)  Weekly Monday Installation Meeting u Attended by all primary players, including detector representatives, Commissioning Coordinator (J. Yu) s Schedule all jobs s Monitor progress s Track potential interferences (space allocation) s Allocation of manpower, other resources –Surveyors, welders, crane, engineering, … s Safety considerations, requirements, documentation u All work of significance requires presentation to this group ~ 1 month in advance before it can be scheduled s Any work in Assembly or Collision Hall requires our approval u Core group collaborates closely on all issues  Priorities set by Kotcher, with extensive input from many others u Ensure appropriate allocation of limited resources, space, etc. u Timely decision-making u Oversee global interest of getting full detector online

DoE Review June 6-7, 2000 Approach to Schedule  Durations/logistics discussed in detail with principals, including: u Detector installation, cabling, & checkout u Logistics/interleaving of electronics installation  Conservative assumptions in many durations, intended to compensate for: s Ramp-up of tasks s Possible delays in engineering/design completion, fabrication, etc. s Unforeseen difficulties  Reconsideration of durations associated with movement of large pieces s Put large pieces in place as soon as possible s Platform, trusses, Forward Muon octant installation, roll-in & hookup in Collision Hall, …  Competing needs for space taken into account wherever possible  Most remaining installation of Forward Muon octants assumed to be done serially u Crane availability u Unique needs, availability of specialized personnel  Double shifts assumed, will begin June 19 u Hand-picked four-man team dedicated primarily to Forward Muon installation s Limit scope of work: safety, etc. u Needed for timely completion of octant installation before roll-in u Durations of associated tasks reduced by 30% - quite conservative

DoE Review June 6-7, 2000 Installation Status  Solenoid u Installed, tested, mapped u Hall probes calibrated in situ  Central Preshower u Installed with solenoid  Central Muon u Inner A-  counters, cosmic cap scintillation counters, refurbished PDTs u Installed, being commissioned  Level 1 & 2 Trigger Framework u Installed, being exercised, commissioned  Forward Preshower, Inter-cryostat Detector, Luminosity Monitor u Mounted on faces of end calorimeters end April, 2000  Forward Muon u All (16) A-layer MDT octants installed on end irons u EMC trusses in Hi Bay, being prepped for move to sidewalk These are final Run 2 systems, in place, varying stages of hookup/commissioning

DoE Review June 6-7, 2000 Muon Detector Upgrade Bottom B/C Scint Central Trigger Scint ( A-  ) PDTs Forward Trigger Scint (Pixels) Forward Tracker (MDTs) Shielding

DoE Review June 6-7, 2000 Partial Installation Task List  Below represents ~ 10% of full Installation Task List  Each task discussed in detail in weekly meeting, status updated  List is priority ordered, maintained by Core Group DescriptionStatusAccesses Needed or Restricted Relevant Dates Repair Shielding Arms Miller – north truss complete. South done after brought to DAB. Load tests for north and south will be done together; awaits reweld of south arms. Hi Bay. Week of 6/5 for re- welding south arms Muon Shielding Mid-pieces : Re- assembly Miller – mid-pieces returned from vendor, lids almost complete Done in Hi BayAll pieces expected back wk of 6/5 Install VLPC Cryostat Rucinski – In progressWelding almost complete; push to commission system prior to platform move (7/11). Platform periodically inaccessible Installation begins week of 6/5 Replace solenoid mounts Krempetz, Miller - Returned to CFT group for final machining to accommodate FT mounts. Survey prior to mount removal, re- survey after new mounts are installed Must be completed before CFT install (6/19) Assemble north A- layer pixel plane on shield wall Miller – preparations underway for shield wall stabilizer. Spreader bar complete. Pit periodically inaccessible. Will remain on shield wall until installation on EFN (~ early Sep) Started week of 5/22. Install gas blocks and leak check WAMUS PDTs Miller – ongoingAccess to PDTs required Ongoing, with high priority

DoE Review June 6-7, 2000 Representative Completed Tasks TaskComments Reconfigure EF bus DC power flagsCompleted 2/4/00 Fabricate Muon Shielding AssemblyCompleted 2/11/00 FPD – 2/21 – near beginning of agenda – access to collision hall during Feb-May Complete 2/21/00 Fill EF HolesCompleted 2/11/00 Install A-Phi LED fiber blocks-West SideCompleted 2/18/00 Modify SAMUS hooksCompleted 2/18/00 Reorganize Hi-Bay area to accommodate trusses and blocks. Completed 2/18/00 Remove and replace hardware on 2 PDT chambers Completed 2/18/00 Leak check Be Beam TubeCompleted 2/18/00 Install Sci-counter cables (8)Completed 2/28/00 Replace BLS backplanes on the south platform Completed 2/18/00 Relocate racks PW4 and PW5 on platform west porch and add new rack to accommodate branch circuit panel for platform AC distribution. Completed 3/1/00 (also did likewise with other side of aisle) Presentation from Balm on turning on solenoid in April Completed 3/6/00

DoE Review June 6-7, 2000 C-layer MDT Being Assembled in Lab F  Size, weight, number of Forward Muon octants places significant demands on resources/labor  Critical sub-system during coming months

DoE Review June 6-7, 2000 Commissioning Status  Commissioning Coordinator appointed (J. Yu)  Weekly Commissioning Meeting attended by all principals u Progress reports, priorities set, monitoring of long- and short-term milestones, daily run plans u (3) mini-workshops in DAB s focus work toward achieving milestones  Commissioning considerations being integrated into installation priorities u Proper application of resources to ensure timely availability of crucial items s infrastructure, cabling, electronics installation, etc. u Installation & commissioning intimately linked  Recent accomplishments associated with March 15 and May 19 milestones: u Established multi-detector, multi-crate readout s Central Muon – scintillation detectors, PDTs s Calorimeter (instrumented with Run 1 electronics) s Prototype Level 1 muon trigger exercised in situ s Silicon front-end read out through VRBs s Implemented cosmic ray triggers u Two data paths exercised: s Primary data path, through Trigger Framework and Level 3 s Secondary path using crate control computers

DoE Review June 6-7, 2000 Commissioning Status (cont’d) u Established data transfer to DAB from SiDet u Additional Run 2 functionality being developed s Trigger Framework exercised s Centralized run and communication control s Online data shipped to Feynman Center, logged s Online event monitoring and displays s Development of SMT calibration system and databases s Training of DAQ experts s Documentation in place, maintained  Extensive system tests/commissioning at remote laboratories u SiDet (10% test) u Cosmic test (CFT, Preshowers) at Lab 3 u Critical training bed s Hardware, expertise, software applied directly to commissioning of experiment s Integral part of D0 commissioning effort

DoE Review June 6-7, 2000 Future Global Commissioning Milestones  Jun 15: Begin SiDet full readout test  Aug 01: Prepare front-ends for checkout during CFT waveguide installation u Implement multi-run DAQ u Complete necessary infrastructure (cabling, rack preparation, etc.) u Prepare necessary safety documentation (ORCs) for unattended running  Sep 15: Complete cabling and checkout of CFT-South u Begin DAQ long-term stability test u Commission Level 3 hardware, filters u Commission FAMUS-North A-layer MDTs  Dec 15: Begin cosmic ray commissioning of inner trackers (SMT-S, CFT), central muon u Track reconstruction u CFT + muon triggers u Commission quadrant of central calorimeter electronics

DoE Review June 6-7, 2000 Conclusions  Installation sequence well understood, many steps performed before by same people  Work carefully organized and monitored, excellent support staff  Schedule contains many conservative assumptions, still requires tightly choreographed series of steps  Commissioning aggressively being pursued, plans/needs taken into account in installation scheduling  Have not deviated from original plan to have complete detector hooked up in February, 2001

DoE Review June 6-7, 2000 Installation Fallback Options  CFT is done u Only detector that, delayed, would have prevented movement of large pieces into final configuration u Not an issue  Fully expect both halves of silicon to arrive as scheduled u Far prefer to install in Assembly Hall s Ease of access, more forgiving time constraints, etc. s Installation in Collision Hall would have to be scheduled u But don’t have to… s Infinite schedule contingency in this system  Full Forward Muon system should make it u Production lines set long ago to respect A, C, B installation sequence – will not be altered u Schedule is conservative, durations generous u If portion of B-layer can’t be mounted in time, roll-in without it s We believe this layer can be installed in Collision Hall, if necessary  Electronics can be installed after roll in, if needed u Short accesses required, accelerator ramp up u Have appropriate complement for detector hookup  Commissioning time prior to roll-in will be optimized as fully as possible u Will continue during initial exposure to beam

DoE Review June 6-7, 2000 Installation Approach  Installation is integrated part of each sub-project: u sub-detector design takes into account installation constraints, interferences, end game scenario u designs developed from extensive discussions between groups s A-  counter design based on detailed survey measurements s design of forward pixels/MDTs in part driven by proximity to end iron s FPS modular design motivated by installation/repair/access concerns s CFT connector design developed within very tight spatial constraints  Evolution of installation plan, activities in Assembly Hall, discussed in weekly meeting amongst principals u More specific, detailed issues discussed in sub-project or other integration meetings s Silicon, Fiber Tracker, Tracker Integration and Installation, Muon Commissioning,...

DoE Review June 6-7, 2000 Installation Approach (cont’d)  Installation of detector is spatially very tightly constrained u DØ is highly hermetic, sub-detectors very closely nested u Ways in which it can be assembled very limited  Choreography very well understood u done before by many of the same people (Level 2 sub-project managers and other physicists, technical staff) u collaboration has experience bringing complex detector system online quickly, efficiently s immediately started taking physics data upon roll-in for Run I with no engineering run  Appreciate complexity of Run 2 system, concomitant demands on planning and execution

DoE Review June 6-7, 2000 Organizational Overview  Developing integrated approach to installation and commissioning u intimately linked, natural way to approach it u facilitates establishing priorities, decision making, related to: s spatial considerations, interferences s availability of detectors, components, resources s order in which things are done  One person overseeing both operations at managerial level u physicists, project engineers responsible for individual inst/comm sub-tasks (commissioning, tracker installation, mechanical/electrical infrastructure) u sub-projects remain primary players in installation/commissioning of their individual sub-systems s detailed plan for their sub-detectors developed by them

DoE Review June 6-7, 2000 Tracking System Overview Forward Preshower Silicon Microstrip Tracker Fiber Tracker Solenoid Central Preshower All detectors in this volume use SVX II readout ~0.5 m ~1.3 m