Proton Improvement Plan (PIP) William Pellico Fermilab Annual Science and Technology Review September 5-7, 2012
PIP Outline Brief Overview Startup of PIP Organization Documents FY12 Summary Milestones Budget labor Plans – FY13 Focus FY13 Goals Milestones Beyond FY13 William Pellico, Fermilab Annual S&T Review, Sept. 5-7,
PIP – Planning Basis William Pellico, Fermilab Annual S&T Review, Sept. 5-7,
PIP FY12 Official startup year for PIP Several Tasks underway were incorporated into PIP Items identified by Task Force/PIP review made into Tasks WBS Structure and managers identified Management Plan and Design Handbook Resource Loaded Schedule (RLS) was basedlined Tracking of labor and M&S Regular updates and planning meetings Early effort to re-adjust labor and M&S to meet milestones Significant changes to PIP funding Labor Charges now included in budget allocation Reduction in FY12 M&S Labor Constraints William Pellico, Fermilab Annual S&T Review, Sept. 5-7,
PIP Startup Timetable 5 August 2010Task Force Report December 2010Proton Source Workshop February 2011Proton Source Improvement Plan Proposal August st Proton Improvement Plan Manager Meeting October 2011Proton Improvement Plan FY12 M&S Uploaded January 2012 Proton Improvement Plan Design Handbook Proton Improvement Plan Management Plan Proton Improvement Plan RLS Base lined June st Proton Improvement Plan Quarterly Report August st Proton Improvement Plan PMG William Pellico, Fermilab Annual S&T Review, Sept. 5-7, 2012
PIP Technical and Managerial Control Documents Beams Doc # Title Author(s)Date 3660 Proton Source Task Force ReportW. Pellico2010/08/ Proton Source Task ForceW. Pellico2010/10/ Proton Source Improvement PlanV. Lebedev, D. McGinnis, W. Pellico, B. Webber2011/02/ PIP Project Management PlanF.G. Garcia, K. Gollwitzer, W. Pellico, E. Peoples, B. Zwaska2012/01/ PIP Design HandbookF.G. Garcia, K. Gollwitzer,W. Pellico, E. Peoples, B. Zwaska2012/01/ Booster Notching and Absorber Review S. Chaurize, I. Tropin, V. Sidorov, I. Novitski, A. Drozhdin2012/03/03 N/A PIP FY12 Q1Q2 ReportF.G. Garcia, K. Gollwitzer, W. Pellico, E. Peoples, B. Zwaska2012/06/01 N/A PIP FY12 Q3 ReportF.G. Garcia, K. Gollwitzer, W. Pellico, E. Peoples, B. Zwaska2012/08/01 William Pellico, Fermilab Annual S&T Review, Sept. 5-7,
PIP Organization William Pellico, Fermilab Annual S&T Review, Sept. 5-7, Proton Improvement Plan Bill Pellico Bob Zwaska, Deputy Elmie Peoples-Evans, Project Controls Mary Convery, Installation Coordinator Valeri Lebedev, Senior Physicist Linac Fernanda G. Garcia 200 MHz RF Power System Fernanda G. Garcia High-Level RF J. Steimel Linac Modulator Trevor Butler 7835 Procurement Fernanda G. Garcia Accelerator Physics Valeri Lebedev Simulations & Studies Valeri Kapin Linac Notch Creation Dave Johnson Instrumentation Craig Drennan Beam Position Monitors Nathan Eddy Utilities Patrick Karns Power Distribution Ryan Crawford Vacuum System Dave Augustine Booster Keith Gollwitzer RF John Reid Anode Supply Ryan Crawford Bias Supply Pat Sheahan Cavity Test Stand Pat Sheahan Cavity & Tuner Refurb. Matt Slabaugh New Tuners Matt Slabaugh New Cavities Bob Zwaska Cavity 1013 Matt Slabaugh John Reid Accelerator Physics Bob Zwaska Simulation & Studies Bob Zwaska Alignment & Aperture Kiyomi Seiya Booster Notcher Salah Chaurize Booster Cogging Kiyomi Seiya Booster Collimation Valeri Lebedev Radiation Shielding Peter Kasper Instrumentation Craig Drennan Beam Position Monitors Nathan Eddy Dampers Nathan Eddy Utilities Todd Sullivan Low-Conductivity Water System David Hixson Power Distribution Ryan Crawford Vacuum System Dave Augustine Solid State Upgrade John Reid Power Amplifier Steve Kotz Driver Module Tom Kubicki Modulator Rene Padilla Installation Rene Padilla Steve Kotz RFQ Injector C. Y. Tan
PIP RLS William Pellico, Fermilab Annual S&T Review, Sept. 5-7, We currently have 30 WBS level 4 assignments being managed Most tasks have multiple charge codes Every task was reviewed, base lined, fully burdened and entered into the PIP RLS. Tasks were categorized then inputted into the RLS Budget PIP Goals Labor Engineering Constraints Several of the tasks are still being developed Options being developed/reviewed
PIP FY12 Milestones WBSActionMilestone Level DescriptionDate Jan 2012 Current Jul Installation Installation of RF Stations in East Gallery 1 Upgraded Booster RF stations in east gallery July 2012June High Level RF Determine course of action 1Select the best option.Jul 2012 Aug RFQ Injector Beam ready for operations 0Reliably deliver beam to downstream machines. Oct 2012 Nov Linac Modulator Determine course of action 1Select the best option.Nov 2012 William Pellico, Fermilab Annual S&T Review, Sept. 5-7, WBSMilestone Level DescriptionFY12 TotalCompletedConcernExplanation(s) 1.12Linac4 4none 1.22Booster8 6LowMoved due to funding 1.32RFQ-Injector4 3LowInstall underway
RFQ Injector Beam Tests RFQ Injector Diagnostic Line Opened RFQ Einzel Lens (Front of RFQ) New RFQ Injector RFQ Injector
Spare Cavity Ferrite Testing Cavity Modeling Refurbished Solid State Cavity Tuner Rebuild Failed Tuner Connection Booster RF Repaired Tuner Connection
Power Distribution Create Site Wide Monitoring Network PIP HQ PIP PIP FY12 UTLILITES LCW Upgrade Old Linac Transformer New Linac Transformer New LCW Strainer System New LCW Return System Updated Roughing Pumps Vacuum
William Pellico, Fermilab Annual S&T Review, Sept. 5-7, Booster Notched Beam Absorber and Short Kickers Fast Short Kickers New Notched Beam Absorber Tunnel Layout Power Loss Beam Loss
William Pellico, Fermilab Annual S&T Review, Sept. 5-7, New New Notched Beam Absorber Simulations Current CollimatorsNew Absorber
PIP Budget Tables (FY12 and FY13) William Pellico, Fermilab Annual S&T Review, Sept. 5-7, PIP + RFQFY12FY13FY14FY15FY16FY17 Funding $ $6,745,97 9 $6,726,380 $11,979,42 0 $12,836,06 6 $6,789,400$0 Labor (FTE) FY12 PIP OBL BUDGET K$ OBL BUDGET YTD OBL8/12 RIPBUDGET BAL M&S 6,793 5,313801,400 Labor 6,403 5, FY12 Sums13,19611,249961,947 Base Lined PIP Budget Table : Labor cost not included Current FY12 : HLRF Ferrites
PIP – Budget and Planning Going Forward
Budget Changes 2011 PlanDesign Handbook (Jan. 2012) Present Plan with FY12-13 cuts Direct M&S (M$) Labor (FTE) Direct M&S (M$) Labor (FTE) Direct M&S (M$) Labor (FTE) FY FY FY ?32 ? FY ?31 ? FY ?32 ? FY ?28 ? FY ?5 ? Total ?183? William Pellico, Fermilab Annual S&T Review, Sept. 5-7, 2012 Budget is pushing the schedule through at least FY
Effects of FY13 Budget Reduction Break out effects by the pillars of PIP: 1. Pulse rate 2. Proton Throughput (losses) 3. Reliability 4. Modernization (addressing obsolescence) Above ordering used to prioritize for accommodating FY13 cuts These items are interconnected, e.g.: Pushing rep rate can reduce reliability Components are less reliable until modernized William Pellico, Fermilab Annual S&T Review, Sept. 5-7,
FY13 Milestones – Under Current Budget Planning WBSActionLevelDescriptionDate Jan 2012 Current Aug Power Amplifier Assemble Second 14 Power Amplifiers 1Assembled and tested second 14 power amplifiers Apr Installation Installation of RF Stations in West Gallery 1Upgraded all Booster RF stations in west gallery May Driver Module Assembled Relay Racks 1Assembled relay racksJul Modulator Assemble 12 Modulators 1Assembled and tested second 12 modulators Oct 2013 Dec 2013 William Pellico, Fermilab Annual S&T Review, Sept. 5-7, The Booster solid state upgrades were given priority and remain on schedule after the FY13 budget cuts to PIP.
PIP Major Milestone Outlook PIP has not been funded as we would have liked – outlying milestones/schedule will be impacted PIP Baseline Schedule Major Milestone Summary MilestoneProposed Date Schedule Date 12 Hz OperationMay 2013Aug 2014 * 15Hz OperationJanuary 2016 Jun 2015 * Double ThroughputJanuary 2016March 2016 * > 85% ReliabilitySeptember 2016December 2016 ** William Pellico, Fermilab Annual S&T Review, Sept. 5-7, * New estimates to be determined in September ** Completion depends upon funding profile 7.5 Hz: Out of the Shutdown 1 e17 / hr: Out of the Shutdown Solid State /Rep Rate Testing Cavity Refurbishment Selection Aperture Scans
PIP Summary Organizational structure completed PIP goals and management controls completed and documented All level 0,1 milestones for FY12 will be completed Resource Loaded Schedule – control process underway Booster Solid State given priority and on schedule RFQ injector – initial issues resolved and install started Budget issues have and will continue to drive schedule FY13 will be difficult (>50 % budget reduction) An updated RLS will be generated in FY13 Q1 William Pellico, Fermilab Annual S&T Review, Sept. 5-7,
William Pellico, Fermilab Annual S&T Review, Sept. 5-7, Wise people once said….