Update: QA Build Out project All QA Build Out project activities are scheduled to be completed by 7/24/06 MarkeTrak testing is on-schedule and is moving.

Slides:



Advertisements
Similar presentations
Retail Market Subcommittee Update to TAC Kathy Scott January 28,
Advertisements

MarkeTrak Orientation July 30,  Antitrust Admonition  Introductions  MarkeTrak Flight Test Orientation  Why Do We Test?  Overview  API vs.
Update to RMS April 7, RMGRR – Guidelines for Notification of Invoice Dispute  The revision will align the Retail Market Guide with current market.
HMIS User Group Agenda Welcome and Introductions (Lawrence) Offered/Available Trainings (Heather) Known Issues (Lawrence) Leveraging Central Intake/Client.
Update to RMS January 6, RMGRR – Revision to Customer Rescission Completion Timeline The revision will implement a written standard in the Retail.
MarkeTrak Update Retail Market Subcommittee December 6, 2006 Adam Martinez & Karen Farley.
SMART METER TEXAS Status Update July 29, AGENDA Release 1 Smart Meter Texas Online Portal Update – SMT Solution Update – Registration Statistics.
Information Systems OUR MISSION: align, deliver and run IS like a business Northwestern Mutual Data Center Dave McGuffey Managed Deploy & Application Checkout.
Purchasing Director’s Meeting MFMP 2.0 Upgrade Status February 15, 2007.
Objectives: Upgrade Siebel to a supported application Upgrade Oracle database to current version Deliver all existing user functionality with no degradation.
Market Coordination Team Update to RMS.  MCT Kick-off Meeting Update… –1 st MCT Meeting was held on 3/2 (Austin) Twenty five people were in attendance.
Update to RMS March 3, RMGRR129 – Revision to Customer Rescission Completion Timeline - VOTE The revision will implement a written standard in the.
1 TDTWG Update to RMS June 2, MarkeTrak API Performance Metrics Review ERCOT continues work with CenterPoint and Oncor to refine/revise the MT API.
MyFloridaMarketPlace CRB Meeting
SMART METER TEXAS Status Update June 3, AGENDA Release 1 Smart Meter Texas Online Portal Update – SMT Solution Update – Registration Statistics.
Update to RMS June 2, RMGRR131 – Guidelines for Notification of Invoice Dispute – VOTE  The revision will align the Retail Market Guide with current.
Objectives: Develop a solution to either enhance or replace the FasTrak tool Scope/Why is this important?: Increase the transparency for issues that are.
RMS Update to TAC May 8, RMS Update to TAC ► At April 9 RMS Meeting:  Antitrust Training  RMS Voting Items: ► NPRR097Changes to Section 8 to Incorporate.
Update to RMS May 5, RMGRR131 – Guidelines for Notification of Invoice Dispute – MOTION TO TABLE  The revision will align the Retail Market Guide.
1 Market Trials Outage Scheduling Weekly Update July 09, 2010.
Enhancements to FasTrak PR Project Update Retail Market Subcommittee November 8, 2006 Adam Martinez Mgr, Market Operations DPO.
1 NPRR 484/554 – Revisions to Congestion Revenue Rights Credit Calculations and Payments Market Call ERCOT Public July 31, 2013.
Retail Market Subcommittee Update to COPS Kathy Scott July 16,
MarkeTrak Phase II Task Force Update to RMS April 9, 2008.
 Advanced Metering Working Group (AMWG) Update to RMS 1 August 5, 2014.
Retail Market Subcommittee Update to COPS Kathy Scott May 13,
MarkeTrak Lessons Learned Summary Report Retail Market Subcommittee February 14, 2007 Adam Martinez & Scott Egger Market Operations Division Projects Organization.
Update to RMS January 14, MarkeTrak – Release 3 Release 3 was successfully migrated the weekend of December 13 th Stabilization period – Dec 13.
Objectives: Develop a solution to either enhance or replace the FasTrak tool Scope/Why is this important?: Increase the transparency for issues that are.
Objectives: Upgrade Siebel to a supported application Upgrade to Oracle 9i database Deliver all existing user functionality with no degradation in performance.
1 Market Trials Outage Scheduling Weekly Update June 25, 2010.
MP Failover DNS Option 1 for API Failover The same DNS structure that allows ERCOT to fail over services between sites can also be used to allow MPs to.
1 C urrent Market Release TX SET V2.0 / Solution to Stacking.
Retail Business Processes PR 50121_07 Project Update Retail Market Subcommittee September 13, 2006 Adam Martinez Mgr, Market Operations DPO.
Texas SET Version 3.0 Production Implementation Plan.
1 Market Trials Outage Scheduling Weekly Update July 02, 2010.
PR50121_07 Retail Business Processes (RBP) Project Update Retail Market Subcommittee November 8, 2006 Adam D. Martinez Mgr, Market Operations DPO.
Update to RMS November 3, 2015 ERCOT Retail Market Training Task Force Co-Chairs: Deborah McKeever, Oncor Tomas Fernandez, NRG Energy Sheri Wiegand, TXU.
© 2015, Florida Department of Education. All Rights Reserved. FLAGS Florida Grant System June 17, 2015.
Objectives: Develop a solution to either enhance or replace the FasTrak tool Scope/Why is this important?: Increase the transparency for issues that are.
Lead from the front Texas Nodal 1 EDS 4 Outage Scheduler EDS Market Call May 30, 2008.
1 Market Trials Outage Scheduling Weekly Update June 11, 2010.
Outage Scheduler Transition Plan Kenneth Ragsdale NATF.
Role of Account Management at ERCOT Market Engagement and Readiness (MER) Nodal Training Project TPTF Update – January 24, 2007 Market Education.
Objectives: Upgrade Siebel to a supported application Upgrade Oracle database to current version Deliver all existing user functionality with no degradation.
Update to RMS December 18, Project(PR) 010_03 SCR756 Part B – High Level Timeline DRAFT:  Planning Phase: ~ (End of 2013) ◦ Business requirements.
1 ERCOT Retail Release Overview. 2 How Are Changes Managed? Retail Testing Business Teams Development Teams Release Management Management of: Migration.
Update to RMS June 3, Project(PR) 010_03 SCR756 Part B High Level Timeline  Planning Phase - complete  Execution/Development - complete  Testing.
1 Market Trials Outage Scheduling Weekly Update August 13, 2010.
Update to RMS January 10, Project(PR) 010_03 SCR756 Part B – High Level Timeline DRAFT:  Planning Phase: ~ (End of 2013) ◦ Business requirements.
Enhancements to FasTrak PR Project Update Retail Market Subcommittee September 13, 2006 Adam Martinez Mgr, Market Operations DPO.
Update to RMS March 1, 2016 ERCOT Retail Market Training Task Force Co-Chairs: Deborah McKeever, Oncor Tomas Fernandez, NRG Sheri Wiegand, TXU Energy.
Objectives: Add remaining fields to the ESIID Look Up functions requested in PRR312. Scope/Why is this important?: Allow users to have improved access.
Lead from the front Texas Nodal 1 Early Delivery System Testing Environments & Planning – Involving Market Participants TPTF May.
SCR786 Retail Market Test (Sandbox) Environment January 2016.
MyFloridaMarketPlace CRB Meeting MFMP 2.0 Upgrade Status February 01, 2007.
Alternative Proposal SCR786 Retail Market Test Environment September 2015.
Update to RMS April 5 th, 2016 ERCOT Retail Market Training Task Force Co-Chairs: Deborah McKeever, Oncor Tomas Fernandez, NRG Sheri Wiegand, TXU Energy.
Update to RMS May 1 st, 2016 ERCOT Retail Market Training Task Force Co-Chairs: Deborah McKeever, Oncor Tomas Fernandez, NRG Sheri Wiegand, TXU Energy.
1 Single Entry Model (SEM) Go-Live Update TAC Update August 6, 2009.
UL/URC Meeting Friday, April 16, Agenda Updates Training and registration Implementation information April/May readiness work Questions?
MarkeTrak Project Update Adam D. Martinez Mgr, Market Ops Divisional Projects Organization ERCOT RMS Meeting May 10, 2006.
August 9, 2006 Retail Market Subcommittee Meeting MarkeTrak Update.
ERCOT Retail Market Training Task Force
January 10, 2017 Retail Market Subcommittee (RMS) Update to COPS
January 10, 2017 Retail Market Subcommittee (RMS) Update to TAC
March 1, 2016 Retail Market Subcommittee Update to TAC
ERCOT Retail Market Training Task Force
Shared Financial System March 13, 2002
GRP Progress & Plans The GRP project was established to deliver an updated design utilising fully supported hardware and software for Gemini. GRP is replacing.
Presentation transcript:

Update: QA Build Out project All QA Build Out project activities are scheduled to be completed by 7/24/06 MarkeTrak testing is on-schedule and is moving forward Do not anticipate any negative impacts to the MarkeTrak project Update: QA Build Out project All QA Build Out project activities are scheduled to be completed by 7/24/06 MarkeTrak testing is on-schedule and is moving forward Do not anticipate any negative impacts to the MarkeTrak project Summary of Project Status PR Enhancements to FasTrak As of July 5, 2006Page 1

MarkeTrak Project Schedule June JulyAugust QA Build-out Project Lock Down (UAT & CERT Test Environments unavailable for 5 wks) 6/26-6/30 CERT Connectivity Test 7/17 Train the Trainer Sessions Start (2 wks) 8/11 Final User Guides Avail 8/7 Mkt CERT Testing Start (2 wks) 7/10 API & Bulk Insert UAT Start (3 wks) 8/25 MP’s complete Internal Training 8/26 Go Live 6/2 GUI/Siebel interface UAT Complete 7/31 Train the Trainer Sessions End 7/13 API & Bulk Insert CERT Migration

API Connectivity Testing Performed the testing during the week of June 26 th 5 MPs registered for this testing The purpose of the test was for the MPs to connect to the MarkeTrak URL and properly authenticate its digital certificate 4 out of 5 MPs performed a successful test API Connectivity Testing Performed the testing during the week of June 26 th 5 MPs registered for this testing The purpose of the test was for the MPs to connect to the MarkeTrak URL and properly authenticate its digital certificate 4 out of 5 MPs performed a successful test PR Enhancements to FasTrak As of July 5, 2006Page 3

MarkeTrak Training Houston training is July at CenterPoint Dallas training is July at TXU Energy Austin training is July 31 st at ERCOT Taylor All training sessions will run from 9:00am to 4:00pm Individuals only need to attend one session Each session in Houston and Dallas is limited to 24 individuals Austin session at ERCOT Taylor is limited to 20 individuals MarkeTrak Training Houston training is July at CenterPoint Dallas training is July at TXU Energy Austin training is July 31 st at ERCOT Taylor All training sessions will run from 9:00am to 4:00pm Individuals only need to attend one session Each session in Houston and Dallas is limited to 24 individuals Austin session at ERCOT Taylor is limited to 20 individuals PR Enhancements to FasTrak As of July 5, 2006Page 4

MarkeTrak Testing MarkeTrak Testing API/GUI: 8/7/06 – 8/18/06 Testing Participants API testing is required (5 MPs) GUI testing is voluntary (4 MPs) API and GUI combined testing participants (3 MPs) Additional API ad-hoc testing will be permitted during testing period (8/7/06 – 8/18/06) only when ALL MPs have successfully complete API test scripts LIMITED ERCOT resources will be made available for API ad-hoc testing MarkeTrak Testing MarkeTrak Testing API/GUI: 8/7/06 – 8/18/06 Testing Participants API testing is required (5 MPs) GUI testing is voluntary (4 MPs) API and GUI combined testing participants (3 MPs) Additional API ad-hoc testing will be permitted during testing period (8/7/06 – 8/18/06) only when ALL MPs have successfully complete API test scripts LIMITED ERCOT resources will be made available for API ad-hoc testing PR Enhancements to FasTrak As of July 5, 2006Page 5

Project Cutover Plan Highlights  Prior to Migration Weekend  Reports of Issues >6 months old ERCOT will provide a report to MPs of issues older than 6 months  Closing Issues >12 months old Two weeks prior to product migration ERCOT will close issues greater than 12 months old and make available a report to MPs  Migration Weekend  Disable Entry of New Issues in FasTrak At 4:00pm on Friday prior to implementation, ERCOT will disable entry of new issues in FasTrak  In-progress Issues in FasTrak MPs will have the ability to work in-progress issues in FasTrak  MarkeTrak is Operational in Production  Entry of New Issues ERCOT will start accepting new issues into MarkeTrak on Monday, August 28th Project Cutover Plan Highlights  Prior to Migration Weekend  Reports of Issues >6 months old ERCOT will provide a report to MPs of issues older than 6 months  Closing Issues >12 months old Two weeks prior to product migration ERCOT will close issues greater than 12 months old and make available a report to MPs  Migration Weekend  Disable Entry of New Issues in FasTrak At 4:00pm on Friday prior to implementation, ERCOT will disable entry of new issues in FasTrak  In-progress Issues in FasTrak MPs will have the ability to work in-progress issues in FasTrak  MarkeTrak is Operational in Production  Entry of New Issues ERCOT will start accepting new issues into MarkeTrak on Monday, August 28th PR Enhancements to FasTrak As of July 5, 2006Page 6

Project Cutover Plan Highlights - cont.  FasTrak Data  FasTrak Availability ERCOT will keep the FasTrak tool on-line (view and update only) for 90 calendar days after MarkeTrak is implemented  Shutdown of Access to FasTrak One month prior to shutdown of FasTrak ERCOT will provide MPs a report of remaining open issues One week prior to shutdown of FasTrak ERCOT will close remaining open issues and provide report to MPs  Request for FasTrak Data After Shutdown  ERCOT will maintain FasTrak data for a period of no longer than 7 years MPs can request FasTrak data from ERCOT after MarkeTrak implementation Lead times for these types of requests will be 7-10 business days Project Cutover Plan Highlights - cont.  FasTrak Data  FasTrak Availability ERCOT will keep the FasTrak tool on-line (view and update only) for 90 calendar days after MarkeTrak is implemented  Shutdown of Access to FasTrak One month prior to shutdown of FasTrak ERCOT will provide MPs a report of remaining open issues One week prior to shutdown of FasTrak ERCOT will close remaining open issues and provide report to MPs  Request for FasTrak Data After Shutdown  ERCOT will maintain FasTrak data for a period of no longer than 7 years MPs can request FasTrak data from ERCOT after MarkeTrak implementation Lead times for these types of requests will be 7-10 business days PR Enhancements to FasTrak As of July 5, 2006Page 7

Questions? PR Enhancements to FasTrak As of July 5, 2006Page 8