1 A SDB contractor was awarded a $6.2 million contract to construct two buildings in Hawaii that were 300 yards apart and 700 yards from the ocean. The.

Slides:



Advertisements
Similar presentations
Construction Contracting
Advertisements

CARLIN LAW GROUP, APC Grounds for Additional Time and/or Compensation A.Express Changes B.Constructive Changes C.Differing Site Conditions D.Express Suspension.
Change Order Missouri Local Programs How to Complete a Change Order & Get it Approved.
Construction Engineering 380 Subsurface Conditions.
Modern Application of the Spearin Doctrine
NMDOT 2013 Specifications- Section 100 Presented by: Rod Billingsley Billingsley Engineering, P.C. Las Vegas, NM.
LECTURE 7 CLAIMS RELATED TO SUB-CONTRACTORS
John Boon ZUT November Procurement Systems The organisation of the interaction between the purchaser of a new building and the suppliers of goods.
1 MOSS ADAMS LLP | 1 Case Studies in Contract Close Out Audits May 2014.
772 ESS Lesson Learned Briefing
Section 3 Steed Robinson – Office of Community Development  9/4/2014.
Foundations of Real Estate Management BOMA International ® Module 1: Real Estate Administration Contracting for Goods and Services ®
“In the vast area of legal jurisprudence, there are undoubtedly many instances where being the first, or only, jurisdiction to grant rights to persons.
DPW General Conditions Articles 32 through 37. Articles Covered Today  32 Owner’s Right to Withhold Payment  33 Owner’s Right to Stop Work and Terminate.
Darren R. Krattli Eisenhower Carlson PLLC Mechanics’ and Materialmen’s Liens: Start to Finish RCW Main: (253) Direct: (253)
Community Facility Loans/Grants Architect Flow Chart Owner has need for project. RD Area Office is contacted. RD visits project site and discusses project.
Project Close Out CTC-470.
Construction Contract Administration (ENGC 6363) ( FIDIC Chapter 15) EMPLOYER BY TERMINATION Presented by: Mustafa Al tayeb.
ESTIMATING By Laith Jacob.
Construction Industry Development Board development through partnership Construction Procurement documents 2c.
1 Construction Engineering 221 Construction Insurance.
Construction Engineering 221 Cost Estimating and Bidding.
1. Identify Stakeholders 2. Establish the Criteria 3. Identify Potential Sites 4. Initial Screening/ Evaluations & Short List 5. Specific Site Study 6.
Construction Engineering 380 Contract Changes. Types of changes –Cardinal change- drastic change, either single direction or accumulated change in scope.
Mikael Wahlgren NCC Construction Sverige AB ESCL Conference August 25th 2006 – Risk in Construction and how to deal with them. Duty for the contractor.
1 A SDB contractor was awarded a $6.2 million contract to construct two buildings in Hawaii that were 300 yards apart and 700 yards from the ocean. The.
CIVL202 Construction Engineering I Tutorial 2 T1Mon11:00 – 11:50 T2Wed09:00 – 09:50.
1 Contractual Risk Allocation Provisions Presented by: Rolly Chambers & Gene Rash Smith, Currie & Hancock, LLP March 5, 2013.
Construction: Legal Issues. Legal Issues In the Bidding Process Timing of various activities has legal implications. During the bidding process: –A bid.
Nabil dmaidi1 Bid Submission Documents A LATE BID IS NO BID.
Construction Defect Mitigation Construction Cost Recovery Construction Litigation Consultants, LLC Jerry Peck Slide 1 of 12 slides / Total.
Facilities Institute July , 2012 Houston, Texas CONSTRUCTION AND RENOVATION WARRANTY/GUARANTEE What Do You Get And When Does It.
Dr. Ralph Ellis Click to edit Master title style Click to edit Master subtitle style 1 Dispute Review Board Value Contributions Ralph Ellis, P.E., Ph.D.
Case Study on “Conflict of Interest” Reference: Feasibility Study (adopted from NSPE Case No. 88-1)
CIVL202 Construction Engineering I Tutorial 3 T1Mon11:00 – 11:50 T2Wed09:00 – 09:50.
S10 CONS5Q25 Lara Tookey. Review of estimators workings Decision on what margin to apply Bid submission details Submit your Tender.
CONSTRUCTION CONTRACTS – MASTER CHART
Cargo Dock 16: Pre-Bid Meeting Presentation June 13, 2013.
Risk Assignment in The Delivery of a Project  RISK! –Construction projects have lot of it –Contractors manage it –Owners pay for it.
CONSTRUCTION CONTRACTS PRIME CONTRACTS Format and Major Components CHAPTER - 4.
General Condition THE EMPLOYER Construction Law Supervised By : Dr. Kamalain Shaath Prepared By : Eng. Fawzy El.farra.
CHANGE ORDER & BACKCHARGES PREPARED BY ABDULAZIZ M. AL-BESHR ID# PREPARED FOR Dr. ABDULAZIZ BUBSHAIT.
Chapter 15 Payments. Payments typically made monthly. Retainage typically withheld (5% - 10%) Project payment: –series of periodic payments –single final.
Managing Construction Chapter 16. Contractor Projects are overseen by a contractor who owns and operates a construction company. Projects are overseen.
THE TETON DAM FAILURE.
You passed the Bond or secured some funds What do we do now? 2014.
Public Works Department Hot In Place Bituminous Pavement Recycling August, 2011.
Pre-Construction Activities to include: - Provide effective overlap period and oversight of effort - Estimates during - CPM Schedule - Identify lead-time.
Chapter 18: Revenue Recognition Intermediate Accounting, 11th ed. Kieso, Weygandt, and Warfield Prepared by Jep Robertson and Renae Clark New Mexico State.
1 CONTRACTING. 2 WHAT IS CONTRACTING ? CONTRACTING IS BASICALLY AN AGREEMENT BETWEEN TWO PARTIES, ONE CALLED THE CONTRACTING PARTY AND THE OTHER THE CONTRACTED.
LECTURE 5 FORMULATION & PRESENTATION OF OTHER CLAIMS
Differing & Unforeseen Conditions Differing Site Conditions- actual conditions differ from the representation made in the contract documents (MSP airport)
Somerset Village Playground KEENE’S POINTE CAMDEN TOT LOT Lake Burden Playground Bedford Village Playground Community Activity Area Proposed Camden Village.
Change Orders, Extras and Claims Presented by Geoffrey Cantello, City of Ottawa.
Table Discussions 2015 SE Meeting. Scenario #1-Project Completion A $1 million bridge replacement project has a completion date of August 1 th. This date.
Helen S. Henningsen Department of Veterans Affairs Office of General Counsel.
© Hendrick, Phillips, Salzman & Flatt, P.C. – March 8, 2016 What Roofing Contractors Should Look Out For and Include in Contracts and Warranties March.
Building Capacity of SMEs for Participation in Public Procurement Draft Presentation for Training of Trainers June 2014.
Request For Proposals. Request for Proposals Book 1 Contract Book 2 Project Requirements Book 3 Applicable Standards Reference Information Documents (RID)
USAID Afghanistan Engineering Support Program (ESP) Pre-Bid Meeting July 14, 2015.
MACDC Intercounty Drain Procedures Training
City of San Jacinto 7th Street Pavement Repairs
Reconstruction site Investigation, Planning, Scheduling, Estimating and Design Eng. Fahmi Tarazi.
REPAIR FALL PROTECTION PROJECT
Chapter 19: Revenue Recognition
Speaker: Sarah Chambers, Esq. Claims Counsel| Professional Liability
Certificates JCT 11 SBC allows for 10 different kinds of certificates.
Claims during contracts and the idea of the Claim Institution
Allocation of Risk Arising from Subsurface Conditions
Directed Change Constructive Change
Presentation transcript:

1 A SDB contractor was awarded a $6.2 million contract to construct two buildings in Hawaii that were 300 yards apart and 700 yards from the ocean. The contractor did not visit the site before submitting its bid; rather, it relied upon eight soil borings that were included in the bid package. The contractor presumed that the borings were representative of the site, even though they were all taken at only one of the building sites. The actual conditions at the other building sites were substantially different, resulting in the contractor incurring additional costs for piling, delays and dewatering operations. Consequently, the contractor sought an equitable adjustment for a Type I differing site condition. Case 1: Buildings in Hawaii In H.B. Mac, Inc., 153 F.3d 1338 (Fed. Cir. 1998)

Type I Claim Proof 1.representations of subsurface conditions are indicated in the contract 2.the contractor has reasonably interpreted the representations in the contract 3.the contractor reasonably relied on the representations in the contract 4.the subsurface or latent physical condition encountered is materially different from the representations in the contract; 5.the subsurface or latent physical condition encountered was unforeseeable; and 6.the additional costs to the contractor are solely from the materially different subsurface or latent physical condition. 2 Youngdale & Sons Construction Co., Inc. v. United States, 27 Fed. Cl (1993).

3 questions to ask: 1.Did the government/owner make a representation as to the subsurface conditions? 2.If not, how reasonable was it to encounter the actual condition based on the circumstances, and would a site inspection indicate a potential problem? 3.Was the unforeseen subsurface condition the actual cause of the additional expenses or delay? 3

Type II Claim Proof 1.the subsurface or latent physical condition was unknown; 2.the subsurface or latent physical condition was unusual and could not be reasonably anticipated based on a review of the contract documents and site inspection; and 3.the encountered condition was materially different from those ordinarily encountered and generally expected in the type of work to be performed. 4 Youngdale & Sons Construction, 27 Fed.Cl. at 537.

5 A contractor on a sewer project was required by the contract to install pipe in an open trench above the Genesee River. The contract anticipated that contaminated soil may be encountered and included a provision for containment of contaminants. After the award, the contractor proposed and the county accepted a modification to install the pipe in a tunnel 30 feet beneath the riverbed at no additional cost. Digging the tunnel, the contractor encountered toxic creosote leaking into the tunnel, which resulted in a work stoppage. The county refused to pay for the cost of removal alleging that, by proposing the modification, the contractor assumed the risk of differing site conditions. Case 2: Sewer Project in New York Reliance Ins. Co. v. County of Monroe, 604 N.Y.S.2d 439 (App. Div. 1993)

6 A contractor was awarded a Corps of Engineers contract to construct a levee along the Mississippi river in 150 days. The nature of the work required that it be performed from a barge; however, a barge could not be used if the depth of the water was below a certain level (the “low water level”). The Corps controlled the depth of the water through locks and dams. Bidders were provided a historical record of the depths of the river in the area where the project was located over a sixteen year period. The records showed that the depth of the water often fell below the low water level for prolonged periods of time. The contractor testified that he did not believe that the Corps would allow the depth of the river to fall below the low water mark during the performance of the project because the contract did not allow any extra time for shut downs. The Corps dropped the depth of the river to below the low water lever soon after the contractor started work, which resulted in the contractor shutting down its operations for 69 days. The Corps granted the contractor a time extension, but refused to increase the contract price. Case 3: Mississippi River Levee Meyers Cos., Inc. v. U.S., 41 Fed. Cl. 303 (1998)

7 A re-paving contract required a contractor to accept responsibility for disposal of all removed asphalt. The contractor planned to recycle the removed asphalt, but it later discovered that the existing asphalt could not be recycled because it contained contaminants. At the completion of the project, the contractor sought an equitable adjustment for the additional costs to purchase uncontaminated asphalt, alleging that the existence of the contaminants was a Type II differing site condition. Case 4: Pavement Recycling Martin Paving Co. v. Widnall, ,1998 WL

8 A subcontractor sought to recover the additional cost of removing 12,000 feet of rigid ducts and insulation on a renovation project. The specifications required the removal of all existing duct, but the plans did not show these particular ducts. Ceiling grilles and registers for these ducts were in plain view and the bidding documents indicated that the original drawings for the building were available to bidders. The subcontractor did not realize that the grilles indicated the existence of the ducts, nor did it review the original plans for the structure. It brought a pass-through claim against the owner for the recovery of its additional cost of removing both the insulation and the ducts, alleging that they constituted a differing site condition because they were not shown on the renovation plans. Case 5: Duct Work Hoffman Constr. Co., 40 Fed. Cl. 184

9 A subcontractor was placing piles on a job and encountered “quicksand-like materials.” The owner’s soil tester’s statement at the pre-bid hearing and his report indicated that the subsurface conditions were dry (i.e., should not encounter “quicksand-like conditions”). The soil report contained a disclaimer that “the report is not a warranty of subsurface conditions, nor is it a part of the Contract Documents.” In preparing his bid, the subcontractor visited the site and observed drilling on an adjacent lot. Case 6: Quicksand-Like Conditions Millgard Corp. v. McKee/Mayas, 49 F.3d 1070 (5th Cir. (Tx) 1995)