By: Matthew Forbes DO 1: PROJECT MANAGEMENT
Taking last weeks do 1 to the next level Duration and completion Planned expenses To be able to know more systems, I used Merlin PURPOSE
SCHEDULE
?- indicates this is an estimation and not net completed Only A-C have been completed The total duration is 65 days SCHEDULE EXPLANATION
The critical Path is A-B-D-E-F-H Before work started C was on the critical path in the place of A A’s work took 4 weeks (not 2) C’s work took 3 weeks (as expected) CRITICAL PATH
PERFORMANCE
Total expected duration is 17 weeks 2 weeks behind schedule A took 1 week longer than C B took 1 week longer Expected duration for activities D-H is 11 weeks PERFORMANCE
The critical path can be altered from the duration projection to what the actual completed time It is important to use Project Management to keep track of any changes This was the first time we also planned ahead with money INTROSPECTION