09/07/07Shutdown’07 Week 5 F.G. Garcia1 MTA beam line installation Weekly Report September 07, 2007 Period covered: August 31 st to September 7 th (Week.

Slides:



Advertisements
Similar presentations
Hargrave Street Pumpstation – Site Preparation July 2014.
Advertisements

F.G. Garcia X37981 chopper Linac cable tray Cable penetration Overall View from the Linac Bridge Beam direction.
MTA Installation Progress Report June 8, MTA Installation Web Page F.G. Garcia AD/Proton.
NSS Requirements Review: Utilities Michelle Everett Lab Coordinator Scientific Activities Division November 12, 2014.
MONALISA installation at the ATF2 ATF2 weekly meeting.
1 Installation of Delphi Frame  ITS Installation.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
A. Bross MTA RF WS August 22, Welcome MTA RF Workshop.
Proton Source Task Shutdown 2014 RFQ Injection Linac Tank 1 to 2 emmittance probe and Collimator NTF Beam Line Repair 400 MeV Turbo Station Replacement.
LINAC LASER NOTCHER READINESS REVIEW August 5 th, 2014 Kevin Duel – Mechanical Support Engineer.
Internal Cryomodule Instrumentation Sensors, Actuators, Heaters, and Wiring ERL Main Linac Cryomodule 9/5/2012 Peter Quigley Internal Design Review.
08/24/07Shutdown’07 Week 3 F.G. Garcia1 MTA beam line installation Weekly Report August 24, 2007 Period covered: August 17 th to August 24 th (Week 3)
EATM12-08 Contribution NA62 Francois Butin, Lau Gatignon / EN-MEF 4 September 2012.
Preparation for May-2013 Review of UCN Beamline March 27, Date: May 2-3, 2013 Review Committee finalized Scope – Overall concept, focusing on 2014.
PIP Update Linac Utilities for 2014 shutdown Matthew Gardner, 4/23/14.
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
F HINS Schedule of Activities in Meson During FY08 Bob Webber AD Safety Meeting December 5, 2007.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting Approved Labyrinth Fresh air pulled through “chicken wire” gate.
Bubble Chamber Installation Kick-Off Meeting May 28, 2014, Grames Let’s discuss two jobs between the cryounit and injector gate. Bubble chamber (5D) New.
CLASSE prototype: mechanical concepts G. De Michele, EPFL-PSI-CERN on behalf of CERN team SLAC, 16 th April, 2012.
MC Beamline Tom lackowski L1 Manager. Project Organization Jan. 2013T. Lackowski - MC Beamline2.
09/28/07Shutdown’07 Week 8 F.G. Garcia1 MTA beam line installation Weekly Report September 28, 2007 Period covered: September 24 th September 28 th (Week.
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
08/31/07Shutdown’07 Week 4 F.G. Garcia1 MTA beam line installation Weekly Report August 31, 2007 Period covered: August 24 th to August 31 st (Week 4)
Proton Improvement Plan Keith Gollwitzer January 5th, 2015 All Experimenters’ Meeting 11/5/2015Gollwitzer AEM.
The Stripping Foil Test Stand in the Linac4 Transfer Line
TAS at IP5 Present situation and plans François BUTIN TS/LEA.
Proton Plan PMG 9/27/07 E Prebys 1 Proton Plan Status Eric Prebys.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
Proton Improvement Plan Bill Pellico April 19, 2013 NOvA collaboration Meeting Bill Pellico NOvA.
SBS Magnet and Infrastructure Status Robin Wines July 2015.
PASI OsC meeting 12th July 2012
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
Booster L12/Noker-L13/Absorber Update PIP Update Talk August 15, 2012 Salah Chaurize.
MTA Installation Meeting March 7, 2007 Agenda 1)Progress report (Fernanda) 2)Water skid discussion (Maurice) 3)Alignment needs (O’Sheg + all) 4)AOB Key.
Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before.
1 BROOKHAVEN SCIENCE ASSOCIATES CF Coordination with Technical Divisions Ove Dyling Conventional Facilities Advisory Committee Review October 5-6, 2010.
SEPT 20, 2006 T. Brown, M. Cole, P. Fogarty, P. Goranson, K. Freudenberg, D. Williamson NCSX STAGE 2 COIL TO COIL ASSY.
MTA Installation Meeting February 21, 2007 Agenda 1)Progress report (Fernanda+Carol) 2)Floor Plan layout (Fernanda+Larry) 3)AOB Key Red – critical Orange.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
LINAC3 UPGRADE Source and LEBT modifications for YETS and recommissioning timetable 28/10/2015 Ville Toivanen.
Mike Andrews May 10, Week 54 NuMI Activities Initial test controls on the MI65 RAW exchange skid Complete hydrostatic test of the MI65 exchange.
March 7 th Shutdown Shutdown Begins: Monday morning, March 7 th :00 Beam OFF Safety System Testing 08:00 Rack out KRSS, switch MI house power to.
09/21/07Shutdown’07 Week 7 F.G. Garcia1 MTA beam line installation Weekly Report September 21, 2007 Period covered: September 14 th September 21 th (Week.
PIP Shutdown Status 9/17/2014. RIL/Linac Jobs L1 Transformer ◦Rigging complete ◦Electrical work started ◦Turn on this coming weekend Laser notcher flange.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
Operations meeting on FY07 Shutdown Date: June 27, W.B. Christie Outline Brief Overview of Shutdown Plan Details/discussion of next few weeks Comments.
RAMI Paul Aden. RAMI Analysis Reliability Visual inspection during each shutdown Service schedule for necessary components Majority of components to have.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
Work in the Tevatron A0 D0 B0 C0 E0 F0 Separators A49 Separator B48 TEL 2 installation A0 Xtal Collimator 1.5 m collimator A48 Shimming 6 magnets/day At.
MI/RR Shutdown 2012 Dec Gev Lines/Injection region: Staging equipment, cleaning and prepping new part to start vacuum work. Preparing to modify the.
10/3/2014 Proton Source Update. RIL Update Source B is back in place and under vacuum It will be baked over the weekend It will be started early next.
Mike Andrews January 31, Weeks Activities Target Pile Fan Upgrades Install piping for new cooling coil units Install controls for new coil.
All Experimenters Meeting PIP Report Fernanda G. Garcia on behalf of PIP team 10/06/2014.
Proton PMG May 7 th 2015 Cons Gattuso AD Shutdown Manager.
Status of Mechanical Design of LEBT Rich Andrews, Matt Alvarez, Tim Hamerla, Danny Snee.
Vacuum System P. Chiggiato TE-VSC
Status of ATF/ATF2 and machine schedule in this fall
SHMS Downstream Beamline Large SHMS/HMS Angles (Config-1)
Two-beam Test-stand Design and Construction Status
APTM and GRID interface requirement PBIP and PBW
Target Safety System Interfaces
SC1R Cold Box PDR Assembly Sequence
Overview of the TARGET Monolith Rough Vacuum
Linac4 Connection Broken Line 07/08/19
Presentation transcript:

09/07/07Shutdown’07 Week 5 F.G. Garcia1 MTA beam line installation Weekly Report September 07, 2007 Period covered: August 31 st to September 7 th (Week 5) MTA – Week3

09/07/07Shutdown’07 Week 5 F.G. Garcia2 MTA Weekly Report – Week 5  Shielding underneath hatch area is complete Restacking complete on 09/04 Finalizing some safety requirements:  Added cover plates to aid S&S  Retrofit cover plate over the utility penetration  Re-used the slug of concrete to plug in the beam pipe penetration  Electrical Work Cable pull ongoing  Load cables estimate to finish by Monday  Immediately start pulling instrumentation cables Next week: Continue with cable pull.  Mechanical Installation All magnets have been stationed in place  Next step will be alignment! Moving along with MW stands (45% complete).

09/07/07Shutdown’07 Week 5 F.G. Garcia3 MTA Weekly Report – Week 5  Alignment Outside corner of the concrete blocks were shot by surveyors Next week: Rough alignment starts Monday, Sep 10 th  LCW work Copper pipe installation complete (Linac side)  Brazing/installing taps Next week: Contractors will be moving to the MTA side  Vacuum work Making as much progress as possible with the assortment of the spool pieces and flanges Ion pumps stands are complete Beam pipe support stands are complete