Target Status Report Chris Booth & Paul Hodgson Sheffield 18 th Sept ember2008.

Slides:



Advertisements
Similar presentations
MICE Magnetic Investigation of T2 MICE/ISIS Target Meeting 17 th September 2010 P J Smith – University of Sheffield.
Advertisements

MICE MICE Target Mechanism Paul Smith University of Sheffield 8 th June 2010 (Based upon talk given by Chris Booth at CM26)
MICE Target Report Chris Booth (for target team) Sheffield 23 rd April 2009.
Progress on Target Design Chris Booth Sheffield 2 nd August 2004.
MICE Target Status Chris Booth 30 th March Chris BoothUniversity of Sheffield 2 The challenge ISIS beam shrinks from 73 mm to 55 mm radius during.
Target Operation and Status Report Chris Booth for Target Team 20 th October 2008.
MICE MICE Target Status P J Smith CM 25 Wed 4 th November 2009.
MICE TARGET HARDWARE C. Booth, P. Hodgson, R. Nicholson, P. J. Smith, Dept. of Physics & Astronomy University of Sheffield, England. 1 - The MICE Experiment.
MICE Target Development Chris Booth Sheffield 8 th June 2006.
MICE Target Report Chris Booth (for target team) Sheffield 7 th May 2009.
MICE Target Schedule Chris Booth Sheffield 12 th June 2006.
Progress on Target Design Chris Booth Sheffield 14 th July 2004.
Target: K. Long, 16Nov2009. Schedule for T2 re-instatement: T2#2: – Inspection of T2#2 documented in MICE Note 272 Some issue with Notes site … couldn’t.
MICE Target Report Chris Booth (for target team) Sheffield 24 th March 2010.
MICE Target Status Chris Booth Sheffield 10 th May 2006.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
Target Update – Mico Meeting Monday 21 st April 2008 General Expect to obtain new coils for stators anytime New Shafts at RAL for metrology. Will be back.
Stator Plan & Schedule Chris Booth 2 nd March stators to construct for mid-April. One complete coil assembly recovered from ISIS drive. Coils recoverable.
MICE Target Review Chris Booth Sheffield 12 th June 2006.
A Tale of Two Targets … 7 th September 2009 Chris Booth The University of Sheffield.
Target: K. Long, 16Nov2009. Schedule for T2 re-instatement: T2#2: – Next steps: Non-DLC bearings: – Delay in material delivery: » Torlon delivery expected.
Target: K. Long, 16Nov2009. Schedule for T2 re-instatement: T2#2: – Next steps: Non-DLC bearings: – Continuing delay in material delivery! » Vespel and.
Target Assembly and Installation Update 20 th August 2009 Paul Hodgson The University of Sheffield.
MICE TARGET WORKSHOP – SHEFFIELD 2 nd December Target vibration and general design issues 2. Simple Vibration - causes and forces. 3. Not so simple.
1 MICE Magnets Contents: Background Refurbishment Testing Installation & survey Current status Upstream beamline Open issues & concerns MICE Beamline Review,
(FEA) Analysis P J Smith University of Sheffield 27 th November 2008.
Charging System Fundamentals
MICE Target Report Video Conference 05/07/07 Chris Booth Sheffield 5 th July 2007.
Target Design – Status and Plans Chris Booth Sheffield 12 th January 2005.
Griner Drilling Service
Target Operation and Status Report Chris Booth for Target Team 13 th January 2009 Outline Current target performance Investigation of demonstrator failure.
MICE Target Mechanical Design l Jason Tarrant – STFC »Working on upgrade of Target Mechanics l Contents »Main features of upgrade design »Progress & schedule.
Electromagnetic Induction
MICE Target Mechanism P J Smith University of Sheffield MICE CM 18 RAL June 2007.
MICE status. Mice layout Beam line elements (including channel magnets) Detector components Civil Engineering Software target Decay Solenoid Beam Stop.
Target Report Introduction Chris Booth Sheffield 20 th November 2008.
MICE Target Mechanical Design l Contents »Status of modelling and drawing »Work being undertaken at RAL on shaft and bearing prototypes »Procedure for.
Office of Railroad, Pipeline & Hazardous Materials Investigations Mechanical.
MICE Beam-line and Detectors Status Report 16 th October 2009 Chris Booth The University of Sheffield.
Status of installed target Preparation of “demonstrator” target Chris Booth Sheffield 25 th January 2008.
MICE Target - Risk Lara Howlett University of Sheffield.
Why Maintenance Tasks are Important Produced by Joe Marchese.
Target Status Target installed in ISIS “Demonstrator” target in R78 Chris Booth Sheffield 7 th February 2008.
Target Status CM19 RAL October 2007 P J Smith – University of Sheffield.
MICE Target Mechanical Design l Status of Target ref. Schedule »Drawings –Drawing list created (see next slide) includes inventory –Drawings being released.
MICE Target l Jason Tarrant – STFC l Investigative work on T2 with plastic bearings »Stopped after >2 million cycles »Disassembly with photographic investigation.
Status of Target Design Chris Booth Sheffield 28 th October 2004.
Clutches.
Holding Down and Chocking The engine must be securely fixed to the ship. For this the engine is mounted on resin or cast iron chocks and bolted to the.
1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.
MICE Target Installation Chris Booth & Paul Smith Sheffield 26 th July 2007.
Target tests 1 st – 2 nd Nov. Chris Booth Sheffield 7 th December 2006.
Target Commissioning Target installed in ISIS “Demonstrator” target in R78 Initial commissioning plans Chris Booth Sheffield 11 th February 2008.
Clutches Basic purpose Used to disengage engine from input shaft Flywheel –Bolted to crankshaft –Provides surface for clutch disc to work on Clutch disc.
Chris Booth & Paul Smith Sheffield 16 th August 2007 MICE Target Installation.
Electric Field Lines Contents: Basic Concept Field Lines and point charges Field Lines and conductors.
Magnetic Field Task Dietrich Liko. Overview A lot of progress in the last two weeks I try to summarize the status Discussion on additional.
MICE Target – Status & Plans Chris Booth Sheffield 28 th February 2006.
Target Status 27 th August 2009 Chris Booth The University of Sheffield.
Target Installation Plan
P. J. Smith on behalf of the MICE target team.
MICE Target Mechanical Design
MICE Target Report Video Conference 29/11/07
Manual Drivetrains and Axles
Status of Target Design
Electricity & Magnetism
Coupling alignment. Outline:  Introduction  Types of coupling and installation  Preparation of alignment  Tools and types of alignment  Alignment.
Electricity & Magnetism
Electricity & Magnetism
Presentation transcript:

Target Status Report Chris Booth & Paul Hodgson Sheffield 18 th Sept ember2008

Chris BoothUniversity of Sheffield 2 Current Status Two new target drives delivered to RAL late July. One ran in R78 – failed after ~340K actuations. Serious damage to shaft & bearing surfaces. Significant abraded material, though little fell through lower bearing. Same stator had run with old shaft & bearings for >500K actuations in Sheffield without problem. Earlier shafts with DLC coatings run >5M cycles. Unclear why failed setup was different. Weekly meetings Sheffield/RAL to try to identify cause of problem and best way forward.

Chris BoothUniversity of Sheffield 3 Possible failure causes Misalignment of bearings and shaft. Partial demagnetisation of permanent magnets causing non-axial forces. Distortion of coils causing non-axial forces. Poorer quality DLC coatings on shaft and/or bearings. Dynamic or static distortion of shaft. All the above are addressed in the following slides. Several experts from RAL, Sheffield Materials and outside companies have been consulted and provided valuable expertise.

Chris BoothUniversity of Sheffield 4 Tests of possible failure causes (1) Misalignment of bearings and shaft  Bearings have sharp edges. Misalignment of bearings would cause edges to cut into shaft. Metrology at RAL have checked both stators. Both are well aligned. Distortion of coils causing non-axial forces ? With improved electrical insulation, recent coils have looked less uniform. Tom Bradshaw/Jim Rochford will try to map field inside stator with (low) DC current. Difficult job – high spatial precision needed. Will take time to prepare. But this stator ran well with other shaft! Implies not likely to be a stator problem!

Chris BoothUniversity of Sheffield 5 Tests of possible failure causes (2) Partial demagnetisation of permanent magnets  Field at surface of sectored magnets measured in Sheffield. (Not easy, because of small scale!!) No sign of significant azimuthal asymmetry.

Chris BoothUniversity of Sheffield 6 Tests of possible failure causes (3) Distortion of shaft ? Static: Metrology will perform precise measurements, but shafts are NOT perfectly straight. Always true? (Ti not rigid enough.) Dynamic: Wing Lau to model behaviour under acceleration. Andy to try to get high-speed camera. Poor DLC coatings ? Discussions with coating company (TecVac), who have seen photos of failed parts. QC sample indicates adherence normal, but thickness 2-3 μm cf 5-6 μm normal. Could be surface contamination or inadequate polishing prior to coating – most likely explanation according to TecVac. Sheffield surface expert: wire erosion damage causes poor adhesion. RAL metrology & Sheffield expert: may be better to have dissimilar materials in contact (not both DLC).

Chris BoothUniversity of Sheffield 7 Way forward Some things can be checked quickly. Others need a detailed study. Two likely problem areas are rigidity of shaft and surface coatings. We have 1 shaft (DLC coated, same batch as failure!) plus spare bearings (coated & uncoated). Will remove sharp edges from uncoated bearing set, electropolish to remove erosion damage, electroless nickel plate – very hard, smooth bearing surface. Company found who can do this within 2 weeks. Run existing shaft, new bearing. Inspect frequently for any start of damage. Preliminary result by Collaboration Meeting. In parallel, RAL engineering effort to look at improvements to design of shaft (rigidity, mass) and other components for more robust design.