© Services GmbH Project work plan 2/20/ St. Petersburg, May 18, 2011 Dr. Andrey Girenko
© Services GmbH Basic definitions The work plan shall be broken into work packages (WPs)… 2/20/ A work package is a major sub-division (sub-project, building block) of the proposed project with a verifiable end-point – normally a deliverable or a milestone in the overall project...
© Services GmbH Basic definitions A deliverable represents a verifiable output of the project. Deliverables are often Reports (technical and formal) Technologies (e.g. software, prototypes, demonstrators) Principle publications (e.g. White Paper, website, database, etc.) Etc. 2/20/2016 3
© Services GmbH Basic definitions A milestone is a Control point where decisions are needed with regard to the next stage of the project. Examples: End of requirements analysis End of evaluation trial Moment of obtaining one of the core technologies 2/20/2016 4
© Services GmbH Features of a WP Size of a WP shall correspond to the size of the project (STREP – 7-12 WPs, IP – 10-18, etc.) Reasonable number of deliverables (2-6) Can/should be broken into TASKs Size of WPs within a project shall be balanced (no super-WP, no micro-WP) Logics underpinned by the goals of the project Do not forget standard WPs (MNG, DISS) Try to avoid mono-participant WPs Think of knowledge transfer and timing 2/20/2016 5
© Services GmbH Coming back to our “dummy” project… The overall goal: To improve Math education in Europe, especially for transition from schools to Universities… The basic idea: Game-based collaborative TEL tools for learning Math in social networks. (A STREP project, with 8 partners, budget ca. 4 Meuro) 2/20/ Start thinking – what is needed to make it happen?
© Services GmbH Principle blocks… 1. Requirements analysis 2/20/ Pedagogical scenarios 3. Learner modeling 4.Flexible user interfaces 5. Assessment tools 6. Integration 7. Testing and Evaluation 8. Dissemination and exploitation 9. Management and Coordination
© Services GmbH Connections… Requirements analysis 2/20/ Pedagogical scenarios Learner modeling Flexible user interfaces Assessment tools Integration Testing and Evaluation Dissemination and exploitation Management and Coordination
© Services GmbH Pert Chart example: IP 2/20/2016 9
© Services GmbH Timing: Gantt Chart 2/20/ Milestone
© Services GmbH User centred design (optional) 2/20/ ISO standardized approach
© Services GmbH Gantt chart: IP using UCD (MS Office) 2/20/
© Services GmbH Conclusions… Be practical, try to imagine how you will run the project While shaping WPs, try to make them easy-to-manage WP titles – try to highlight most innovative aspects of the project Highlight complementarity of activities For every WP try to keep in mind a Leader Use eye-catching graphical presentations Finally, try to get some “external” evaluation of the WP structure 2/20/ Work plan is one of the important aspects defining the overall success