31 January 2006A.Ciocio - SCTSG1 Type ii-iii and PP1 Production Timescale for installation Plan PP1and Testing.

Slides:



Advertisements
Similar presentations
Endcap assembly update C Buttar UK-SCT-MB RAL 2 nd Sept 04.
Advertisements

Status of EC-C assembly at Liverpool C Buttar EC PAR, Nikhef Nov 04.
Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
27 September 2005A.Ciocio - ID Week1 SCT Service Installation Overview Status of Type IV Cable Installation Type II/III Cable Installation Plan for the.
SCT Power Supply Installation Schedule Jan Bohm, Prague AS, 4 th November 2005 The SCT Power Supply System will be installed in 22 LV&HV racks situated.
16/5/2003SCT PAR, Georg Viehhauser1 Assembly of Modules to Cylinders Georg Viehhauser.
SGI Confidential Copan 400 Installation. SGI Confidential Installation Overview The approximate minimum time to complete this procedure is.
A.Nichols CLRC1 SCT HEX PRR ( ) Layout & Installation of Barrel off-detector HEX circuits From barrel cooling loop to PPB1 l Barrel Hex is a plain.
Opto Harness FDR 19/10/01 T. Weidberg1 Opto Harness FDR Scope and aims of review, system overview Available documentation Status of Project & Schedule.
Walls crates cables gas chambers electronics CERN adb.
BLM FOR THE INJECTORS PROJECT CABLING NON-CONFORMITIES LIU-PSB Working Group Meeting (15/08/2013) Christos Zamantzas
31 January 2006A.Ciocio - SCTSG1 Type IV cables and PP3 Installation Type IV installation Connector in situ work Status of PP3 Testing.
29 November 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status of Type IV installation Connector in situ work Status of PP3 Testing.
Chiho Wang ATLAS TRT Duke University CERN, Feb TRT Barrel assembly status & schedule Feb. 9, 2005.
14 February 2006A.Ciocio - ID Week1 SCT Services Procurement & Installation Type IV PP3 Type II-III and PP1 Fibres Heaters DCS Testing MTF Workpackage.
Electrical Safety.
Update on alignment kit and stave 250 frame M.Gibson (RAL) 1.
25 October 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status & Plan.
ID week - 26 September 2006 A. Ciocio1 SCT Services Installation SCT Cables Web page
ATLAS Upgrade ID Barrel: Services around ‘outer cylinder’ TJF updated According to the drawing ‘Preparation outer cylinder volume reservation’
Pippa Wells25 October Procurement and manpower for service installation Services readiness dates Planning for type ii/iii Fibre installation dates.
ATLAS Pixel Detector March 2004 Video Conference E. Anderssen LBNL PP1 Opto Connector and Fiber Routing Updated with notes from 23-March Meeting E. Anderssen,
Activities Status and Plan for the week D. Giugni / INFN Milano D. Giugni Monday Meeting
Malte HildebrandtDC Status Report, Dear MEG Committee,PSI, April 14 th 2009 this is the first report concerning the drift chamber status as.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
1a.  Exposed part  Live or energized part  De-energized part 1a.
CMS ECAL End Cap Meeting CERN 19 June to 23 June 2000 A.B.Lodge - RAL 1 ECAL End Cap High Voltage Cards and 2000 Electrical/Thermal Model. Progress on.
V. Cindro, Jožef Stefan Institute, Ljubljana, Slovenia DAQ, DCS, Power Supply and Cables Review CERN, March Electrical PP1 Basic features Electrical.
Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling on YB Fabio Montecassiano INFN PH/CMM.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
8 June 2006A.Ciocio - SCTSG1 SCT Services Installation Type IV PP3 Type II-III and PP1 Testing & Installation Plan Workpackage
13 June 2013Laurent Roy Optical Fibers / Electronics Upgrade -Fibers need for Upgrade -> Installation ? -Two techniques possible for multi fibers installation.
ATLAS SCT End-Cap C Integration 1.Introduction: to the SCT within ATLAS 2.End-Cap C Reception at CERN 3.Final Assembly 4.Integration with the TRT 5.Combined.
r1Fabio Montecassiano INFN PD & CERN PH/CMM1 Status of cabling YB+2 and YB+1, extension to minus wheels and YB0, cables between UXC55 and USC55.
18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page
CMS ECAL End Cap Meeting CERN 18 Oct to 22 Oct ECAL End Cap High Voltage and Fibre Optic Monitoring Systems Progress. Progress on High Voltage and.
Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer 8/12/2008 1David Lissuaer, Santa Cruz Meeting.
JCOV 24 NOVEMBER 2005 J.Godlewski EP-ATI 1 JCOV NOVEMBER 2005 ATLAS cooling systems installation plans Jan Godlewski CERN EP-ATI The H.Niewodniczanski.
16/04/20031PNPI / LHCb Muon EDR Wire Pad Chambers PNPI design for regions R4 in Stations M2,M3,M4  4 gas gaps of 5mm±70µm;  Active area: 1224x252.8 mm².
14 December 2005A.Ciocio - SCTSG1 Services and Patchpanels Installation Type IV installation Connector in situ work Status of PP3 Type II/III Testing.
November 04 Jason Tarrant CCLRC1 SCT EC Interconnects l Progress of SCT EC Interconnects »Services (Required for Disc Insertion 2004 / Integration 2005)
7 March 2006A.Ciocio - SCTSG1 SCT Services and Patch Panels Type IV PP3 Type II-III and PP1 Fibres Heaters DCS Testing Workpackage
9 May 2006A.Ciocio - SCTSG1 SCT Services Installation Type IV PP3 Type II-III and PP1 Fibre Cables DCS Testing & Installation Plan Workpackage
SCTSG - 17 October 2006 A. Ciocio1 SCT Services Installation Update Recent Full Report: September ID week SCT Cables Web page:
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
D. Greenfield CLRC1 UK-V End-cap Engineering 15 July 2003 Debbie Greenfield, RAL.
25 October 2005A. Ciocio - SCTSG1 Type II/III Cables and PP1 Status & Plan.
TC Straw man for ATLAS ID for SLHC This layout is a result of the discussions in the GENOA ID upgrade workshop. Aim is to evolve this to include list of.
8 June 2006A.Ciocio - SCTSG1 Status of Type IV Cables Cables production –resumed in February after 3 months stop –See ID week February ‘06 Delivery of.
1. Take HV harnesses with label (IHV2) and transfer on the Stacking table. 1.1 Inspect HV harnesses visually. 2.1 Insulate HV Flex with 3M™ VHB™ Tape.
M1 Central Part Cable Routing R3 FAR R2 CLOSE R2 FAR + GEM A3 B From chain GEM R2 CLOSE R2 FAR A1 20 A1 A1 A2 A CHAIN Access Front Dané.
Executive Committee, Toronto August 3, 2005 TRT Barrel WBS 1.2/3.2 Harold Ogren Indiana University.
August 04 Jason Tarrant CCLRC1 SCE EC Design & Manufacture l Progress of SCT EC »Support Structure (Required for Disc Assembly 2004) »Services (Required.
Endcap assembly update C Buttar, R French UK-V Cluster RAL 8 th Sept 2004.
MQXFB design, assembly plans & tooling at CERN J.C Perez On behalf of MQXF collaboration team MQXF Workshop on Structure, Alignment and Electrical QA.
LV-HV cable reuse for the Si Tracker Being worked out with S. Wenig.
Steinar Stapnes, LHCC June The ATLAS inner detector TRT endcap A+B TRT endcap C TRT barrel SCT barrel SCT endcap Pixels uWhole ID sits inside bore.
1 PST Heater Panel Design The PST heater panels are internally redundant resistive circuits printed onto a Kapton sheet with an aluminum backing. They.
Level 1 Diploma in Electrical Installation © 2014 City and Guilds of London Institute. All rights reserved. 1 of 13 PowerPoint presentation Stripping and.
Cryomodule Interconnect Installation Issues A Comparison of XFEL to LCLSII Karen Fant 7/29/2015.
QXF Coil Fabrication & Tooling Reaction / Impregnation
End-cap Mechanics FDR Overview of the Project
HF Test station at P5 A.Mestvirishvili.
Services – First Considerations Sigi Wenig / Nicolas Massol ATLAS Tracker Upgrade Workshop Valencia December 2007 Existing services (in cryostat.
Services Layout – Update
Nearly the end of a long story...
ATLAS ITk CO₂ Cooling pipe routing Common Mechanics meeting
ATL-IC-ES new version available - approval starts
Electrical Safety.
Limited Streamer Tube Project Summary
Presentation transcript:

31 January 2006A.Ciocio - SCTSG1 Type ii-iii and PP1 Production Timescale for installation Plan PP1and Testing

31 January 2006A.Ciocio - SCTSG2 Type II/III Production (INEO/St Genis, Thurmelec/Alsace) –Pippa/Sandra/Pepe Bernabeu/Maarit White (prepare tables of lengths, QA of qualification samples, mapping and labels) –Martin Postranecky/Pepe Bernabeu (testing samples of double harnesses at CERN) TC management: Nicolas Massol, Sigi Wenig and team (Russians, Czechs) Installation of dummy PP1 and type II cables –Lars Lindquist (Uppsala) & Neil Fletcher (Liverpool) – new technicians are getting familiar with detector in SR1 Lars is installing DCS cables –Andy Nichols, Janet Fraser, Jason Tarrant, Patrick Werneke to advise on installation/labeling of first examples Routine tests after installation –Sandra/Petr and shift crews

31 January 2006A.Ciocio - SCTSG3 Timescale for Type II Services Since calorimeter moved to z=0 (November) access to the cryostat is possible –ID requests should be via Nicolas Massol Sector 5 (top) and Sector 13 (bottom) –heater cables, and DCS cables –Should be finished this week Sector 3 – was supposed to follow sector 5, but was held up by problems with arches above detector and muon chamber installation –likely to follow Sector 9 Sector 9 – horizontal towards USA15 to be installed next –SCT fibres and SCT power cables (886 cables + spares) –Barrel cables (side A and C) tried last week –a small number of fibres (end cap) should be tried this week Sequence in a sector is: –Tubes, fibres, heater cables, SCT cables, (Muon chambers), –TRT cables, pixel cables

31 January 2006A.Ciocio - SCTSG4 Sectors

31 January 2006A.Ciocio - SCTSG5

31 January 2006A.Ciocio - SCTSG6

31 January 2006A.Ciocio - SCTSG7 Plan for Type II/III cables INEO/Thurmelec are at present making double length harnesses with type II cable and type II connectors on both ends. –Work is proceeding to schedule (we are late) –Problems with raw cable quality so far – minor –We needed to order about 4km more type II (sector 9 longer) and 10-20km more type III (cables generally longer than expected) –Barrel cables (sector 3) will have the type II ends remade to reduce the tolerance on the strip back length to the JST/FCI connectors to 2mm Samples of the FCT (type III) connector have been qualified Almost all cable trays are in place and we could measured lengths of type II/III harnesses with trial cables before FCT cables are trimmed and FCT mounted on type III ends. Found extra (more than extra) length to trim off Company will then take 2-3 weeks to do this type III work –Labels are defined and have been printed for sector 3 (but we don’t need them now) and for sector 9 which is next –Mapping is defined – drawings for installation are being made –First barrel dPP1 are at CERN and have been verified with production cables and the Ljubljana test box –Experts must verify that mapping is transferred to the cryostat bore Will install PP3s in racks to which type III cables arrive with highest priority PPB1 – need small clamps, cable tray covers etc. PPF1 – more parts needed. Cable clamp redesigned by NIKHEF. Other parts on order via RAL. We just received a box with parts. Patrick will try to put them together then we can run test cable.

31 January 2006A.Ciocio - SCTSG8 PP1 and Testing Type II-III cables are tested at reception (only samples of delivered batches) –After installation all tested row by row as they are in the cable tray Method of testing depends if PP3 and type IV already connected (test at the PP3 or at the PS end Grounding issues discussed with Ned Spencer, Ljubljana and SCT PS community Pay attention to ESD suggested by Richard and investigated by Ned –1. ESD-protective covering or protective caps on external terminals, interconnecting cables, and connector assemblies shall not be removed until necessary to permit the installation. 2. The cable connector pins and cable shield (connector outer shell) shall be grounded prior to engaging a de-energized connector and cable with a mating receptacle connected to an ESDS item. The Type II cable does not have well defined potentials before inserting into PP1 therefore recommended using a shorting plug on the cable connectors before inserting into real PP1, since the cable could be: a) unplugged at PS or PP3, b) be energized, c) have open conductors, d) be experiencing a minor fault to a high potential The test fixture (PP1) connectors for the JST are the main problem. PP1 are used to test cables before installation (it could be 1000 plug ins). PP1 are used for both mechanical (check the stripback length) and electrical tests –Many use cycles on the very thin gold plating of a test fixture could create a surface that is too abrasive for comfort on the Type II cable connector itself. –David Howell chose 50 cycles as his changeout spec. –The FCI looks more robust -> a changeout at cycles of ~1000 –Either build a mechanically similar adapter or use a DPP1 as a test fixture 20 times, and then swapping it out, and using the part as installed DPP1.