Procurement and Manufacture of LCLS Undulators FY 04 Activity: Complete design of Second Prototype Undulator This will include field control comb Procure.

Slides:



Advertisements
Similar presentations
1 LHC-DFBX Procurement Strategy Joseph Rasson LBNL Presented at the DFBX Production Readiness Review October 2002, LBNL Brookhaven - Fermilab - Berkeley.
Advertisements

Rodd Pope, SLAC Undulator System October 12-13, 2006 FAC Meeting 1 Undulator System Assembly Plans Rodd Pope, SLAC.
Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 1 Undulator System Assembly, Installation, and Integration.
Stephen Milton Undulator System 12 October 2004 Undulator System Update Stephen Milton, ANL.
Undulator Long Lead Procurements Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center.
FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science OECM Limited-External Independent.
Geoff Pile FAC Review - Undulator 12 November 2008 LCLS Undulator System Overview and Fabrication Geoff Pile.
David Saenz Facility Advisory October 30, 2007 CONVENTIONAL FACILITES MANAGEMENT.
Mark Reichanadter LCLS FAC April 20-21, 2006 Meeting of the LCLS Facilities Advisory Committee LCLS Project Management M.
M. White – June 28, 2004 LCLS Requirements Meeting In a project, we live or die by the schedule. After we’re “baselined” it is our plan for what we will.
LCLS Prototype Undulator Design LCLS Prototype Undulator Design Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory.
Jess Albino Facility Advisory October 29, 2007 FACILITY ADVISORY COMMITTEE PLENARY CONVENTIONAL FACILITIES UPDATE October.
Marion White Magnets & Supports April 16, 2007 Undulator Magnets and Supports Status.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
Stephen Milton Undulator System 14 November, 2004 Undulator System Overview Stephen Milton.
Marion M. White Undulator Prototype Status and 12 October 2004 LCLSLCLSLCLSLCLS Undulator Prototype Status and Measurement.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review1 Undulator for the LCLS project – from the prototype to the full scale.
LCLS Undulator Systems TDR Charge Linac Coherent Light Source Stanford Linear Accelerator Center Technical Review, March 3, 2004.
Geoff Pile LCLS Und. System Fabrication FAC 29 th, 30 th & 31 st October 2007 LCLS Undulator System Fabrication Schedule FAC.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
David Pindroh Procurement Overview LUSI DOE Review 8/19/08 – 8/21/08 p.1 LCLS Ultrafast Science Instruments (LUSI) David Pindroh – LCLS Procurement Manager.
Question 27: Outline the key steps for industrialization of machine components and the likely remaining vulnerabilities in achieving them. Achieving industrialization.
RF Cavity / Coupling Coil Module
David McGiven FAC: Construction April 2006 Facility Advisory Committee (FAC) Construction Procurement David.
11 T Dipole informal coil and assembly readiness review Long coil and fabrication tooling development status and plans September 22 nd, 2013 – F. Savary.
A SOUND INVESTMENT IN SUCCESSFUL VR OUTCOMES FINANCIAL MANAGEMENT FINANCIAL MANAGEMENT.
Magnetic Material Specification and Procurement Strategy Dawn Munson 1.
From Research Prototype to Production
Utility & Rail Coordination in Project Development Jennifer McCleve Utilities & Rail Branch Manager.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
LCLS Prototype Undulator Design LCLS Prototype Undulator Design Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory.
Mark Reichanadter LCLS FAC October 12-13, 2006 Report to the LCLS Facilities Advisory Committee LCLS Project Management.
David Saenz Readiness for Oct 12, 2006 # Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities.
1 | Program Name or Ancillary Texteere.energy.gov Water Power Peer Review Abrasion Testing of Critical Components of Hydrokinetic Devices Monty Worthington.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science Office of Science Review of the LCLS.
Pre-Construction Activities to include: - Provide effective overlap period and oversight of effort - Estimates during - CPM Schedule - Identify lead-time.
1 Global Design Effort: Controls & LLRF Controls & LLRF Working Group: Tuesday Session (29 May 07) John Carwardine Kay Rehlich.
Mark Reichanadter LCLS October 9-11, 2007 LCLS BCR Overview and EIR LOIs Project Progress / Status Revised Project Baseline.
MARINE CORPS INSTALLATIONS EAST CONTRACTING DIVISION DEFINING REQUIREMENTS.
Project X Working Group Meeting January 15, :00 PM Snake Pit.
SCU 3-Lab Review Meeting, Dec. 16, 2014 SCU Presentations Today Intro. & Performance Motivations (P. Emma, SLAC, 20+5) Conceptual Cryostat Design: Option-A.
Proposed LCLS-II SCU Schedule Soren Prestemon (LBNL) SCU 3-Lab Review Meeting December 16, 2014.
DOE Review of LARP – Feb 17-18, 2014 DOE Critical Decision Process Ruben Carcagno February 17,
CBETA Project ALD’s Cost and Schedule Review February 6, 2017
Meeting of the LCLS Facilities Advisory Committee
SIS100 quadrupole status S. Kostromin, H. Khodzhibagiyan, G. Trubnikov, FAIR 11th MAC, GSI, May,
Support Structure Fabrication
LSST Camera Detector Status
Undulator Assembly Procedure
ARCH 435 PROJECT MANAGEMENT
Undulator Scope, Management, and Organization
Details supporting the increase
Undulator Cost & Schedule Patric Den Hartog, ANL April 24, 2002
Project Management Issues John N. Galayda, SLAC April 24, 2002
LCLS Undulator System Production Management
Undulator Scope, Management, Organization
LCLS Vacuum System Plans (July 07)
Undulator Long-Lead Procurement Preparation
Department Of Energy Review Linac Coherent Light Source Project
Conventional Facilities
Undulator System Overview
Electron Beam Systems ETC and Methodology
Undulator Long-Lead Procurements (LLP) 10 May 2005
Undulator Assembly and Installation Planning
Undulator and Magnet Production Status 25 October 2006
Undulator Alignment Plan
Globus-M2 will be constructed by the end of 2015
DOE Status Meeting of the LCLS Project
Presentation transcript:

Procurement and Manufacture of LCLS Undulators FY 04 Activity: Complete design of Second Prototype Undulator This will include field control comb Procure Fabrication Engineering to manufacture the second prototype Build to specification. Model of undulator provided to vendor Vendor would perform value engineering on the ANL design, and make recommendations to improve assembly process and cost reductions The intellectual property for these improvements would belong to ANL and will be used for the production quantity One of the critical issues will be quality control Final magnetic measurements and tuning would be done at APS

FY 05 activities: Following measurements and review, complete the design of the production LCLS undulator Procure production quantities of the Ti strongback, magnet blocks, and magnet poles. Blocks and Poles should be delivered in FY 05. Strongback delivery completion is predicted for Dec. 05. Prepare a statement of work to procure the first article of the LCLS undulator Use “long lead procurement” funds Possibly award contracts to two vendors to manufacture first articles After evaluating the first articles, procure the remaining undulators. In the two vendor model, the quantity awarded to the vendor would depend on the productivity and cost demonstrated in the first article The vendors quality assurance plan will be a determining factor in making the award. Initial magnetic measurements and tuning will be done at APS. These measurements will provide calibration for the SLAC facility Construction of the magnetic measurement facility at SLAC should start this fiscal year

FY 06 activities: Award the contract (s) for manufacture of LCLS undulator Total quantity will be 40 including the first articles. Delays in FY 06 funding will hurt the delivery schedule Delivery should start in Feb 06 and continue through July 07. The estimated production rate would be 2 per month. Magnet measurements at SLAC could begin in Mar 06 and continue through Aug 07. The estimated measurement rate is 2 per month. It is forecast that the 33 undulators necessary for LCLS would be measured by May 07.

Resources would be drawn from the Experimental Facilities Engineering and Magnetic Devices Groups: Engineering and Design:Pat Den Hartog Emil Trahktenberg Bran Brajuskovic Mark Erdmann Magnetic Design and:Liz Moog MeasurementsShigemi Sasaki Isaac Vasserman Tom Powers Procurement:Glenn Lawrence Gary Edgell (ANL-Procurement) The assignments would require 100 % commitment for short duration.

Plan to Fabricate the Second Prototype Undulator Complete design changes to First Prototype:Trahktenberg12 weeks Brajuskovic Grabinski Prepare statement of work for Ti forgingLawrence3 weeks magnet blocks, and magnet poles, and procure Delivery of forge:8 weeks After design is complete: Prepare statement of work for Ti machiningLawrence3 weeks and procure Delivery of machined Ti strongback9 weeks Prepare statement of work for FabricationLawrence14 weeks Engineering contract to manufacture the second prototype and procure Delivery of second prototype16 weeks MeasurementsVasserman6 weeks Review1 week

Complete design for Production:Trahktenberg12 weeks Brajuskovic Grabinski Review for production: Prepare statement of work forLawrence3 weeks Ti strongback, magnet blocks, magnet poles, and procure Delivery of magnet blocks:15 weeks Delivery of magnet poles:18 weeks Delivery of strongbacks:37 weeks Prepare statement of work for:Lawrence12 weeks production undulators Plan, review and approval:5 weeks Delivery:86 weeks Measurements at SLAC:80 weeks Plan for Undulator Production

Because of the success of scientists and engineers in the MD and XFE groups in achieving specifications, the LCLS undulators are essentially procurement and quality control problems. There appears to be no technical barrier to achieving requirements for the LCLS FEL. The estimated schedule for procurement, from second prototype through production, does identify time constraints. If continuing resolutions occur in FY 05, the delivery of long lead items is threatened. This could choke undulator manufacture, especially for the Ti strongback. If a continuing resolution occurs in FY 06, the ability of manufacturing to meet the installation schedule is threatened. Procuring fabrication engineering services to manufacture the second prototype creates a problem for procurement of the production quantity. Under DoE acquisition regulations, the vendor that manufactures a prototype is typically excluded from bidding on the production contract. Since there are so few undulator manufacturers, this is a major problem. Discussions are continuing with the contract officer to resolve this barrier.