Mod Proposal 0281 - Prevention of "Timing Out" of Authority decisions on Modification Proposals Nick Reeves.

Slides:



Advertisements
Similar presentations
Code Governance Review: WWU views on potential changes to UNC and the Modification Panel Simon Trivella – 30 th March 2010 Governance Workstream.
Advertisements

Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Funding UKLink Process changes (User Pays). 2 Purpose of Presentation  Review of User Pays  Principles  Application to date  National Grid NTS observations.
NTS Exit (Flat) Capacity Charges – Credit Arrangements (UNC TPD V3.3.4) Simon Trivella – 14 th January 2009 Distribution Workstream.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Long Term Entry Capacity & User Commitment Transmission Workstream 7 th August 2008.
UNC Modification Proposal 0116 Reform of the NTS Offtake Arrangements Transmission Workstream 5 th October 2006.
The economic regulation of gas processing services Key issues and initial thoughts Ofgem presentation 18 June 2007.
Moving the QSEC and AMSEC Auctions National Grid NTS, Transmission Workstream.
Mod 0445 – Amendment to the Arrangements for Daily Metered Supply Point Capacity Ofgem Direction to Provide Further Evidence National Grid Distribution.
ADD PRESENTATION TITLE HERE (GO TO: VIEW / MASTER / SLIDE MASTER TO AMEND) ADD PRESENTER’S NAME HERE / ADD DATE HERE © Copyright EDF Energy. All rights.
Code Governance Review UNC Modification Proposals Chris Shanley - National Grid NTS.
MOD506 – Gas Performance Assurance Framework and Governance Arrangements.
Lessons Learned Process – A Strawman.  Lessons Learned  “To pass on any lessons that can be usefully applied to other projects”  “The data in the report.
Discretionary Release of Non Obligated NTS System Entry Capacity Transmission Workstream 1st May 2008.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Proposer: Hayley Burden Panel Date: 17th April : Mod Title: Imbalance Charge amendments required to align the UNC with the Network Code on Gas.
1 UNC Modification 429 Customer Settlement Error Claims Process – Guidance Document.
Force Majeure - Capacity Transmission Workstream 2 July 2009.
Exit Capacity Substitution and Revision Transmission Workstream meeting, 3 rd December 2009.
Environmental Standing Group. 2 Background  Ofgem issued an open letter on 15 th April 2008 to consider issues associated with carbon assessment for.
Proposer: Matthew Hatch Panel Date: 15 th May 0501: Treatment of Existing Entry Capacity Rights at the Bacton ASEP to comply with EU Capacity Regulations.
15 February 2006 TPCR second consultation: gas offtake Offtake Arrangements Workstream 15 February 2006.
Code Administrators Working Group (CAWG) Meeting 3, 29th October 2008.
Assignment of NTS Entry Capacity Transmission Workstream 02 July 2009.
Code Governance Review UNC Modification Proposals Beverley Viney - National Grid NTS.
Facilitating Release of Non-obligated Entry Capacity Draft – for discussion purposes only 22 November 2007.
DRSEC Update Transmission Workstream 06 November 2008.
PN UNC Workgroup Invoicing 10 th January Objectives of the Workgroups To determine business principles for future Invoicing processes –Consider/review.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Development Modification Proposal: Introduction of an Inter-day Linepack Product Review Group August 2010 Transmission Workstream 07/10/2010.
Supply Point Register 7th December 2011
Supply Point Register 21st November 2011
Supply Point Register 10th January 2012
Supply Point Enquiry Service
Proposer: Matthew Hatch Panel Date: 20/10/16
Credit Arrangements – Independent Assessments
Manifest Errors for Entry Capacity Overruns Workgroup 364
Review of UNC Section Q “Emergencies”
Code Governance Review UNC Modification Proposals
CAP190: Workgroup Report CUSC Modifications Panel, 26th August 2011
Proposer: National Grid NTS Panel Date: 17th April 2014
0350 – Combining the NTS entry capacity and exit capacity credit checks Chris Shanley.
NTS Entry Charging Review Update
Assignment Workshop 2 16th September 09, Solihull.
Development Modification Proposal 0337: Introduction of a Inter-day Linepack Product – OPEN LETTER Review Group August th November 2010.
0291 – NTS Licence Special Condition 27 – Balancing Arrangements
Exit Capacity Substitution and Revision
The Necessary Criteria for a UNC Modification Proposal
Consideration of issues raised by UNC Modification Proposal 0244
Chris Warner UNC Modification Panel 21 December 2017
0350 – Combining the NTS entry capacity and exit capacity credit checks Chris Shanley.
QSEC auction timetable
Proposer: Transporter /
Lessons Learned Process – A Strawman
Mod Proposal 0268 : AQ Backstop Date
Draft Mod: Update of default System Marginal Prices
Transporter Initiated SPA Confirmations on behalf of User Potential Impact Discussion with UK Link Committee.
Transmission Workstream 2nd December 2010
Richard Fairholme Transmission Workstream 4th September 2008
Modification proposal 330
Consideration of issues raised by UNC Modification Proposal 0244
Modification 0448 – European Driven Change Process Flow Diagram
Options for the Development of a Demand Side Response Mechanism
CUSC Amendment Panel Recommendation
CAM: Next Steps UNC Transmission Workgroup Lisa Martin 9 January 2014.
Capacity Access Review
How to complete a ReSPECT form
Presentation transcript:

Mod Proposal Prevention of "Timing Out" of Authority decisions on Modification Proposals Nick Reeves

Background  A mod is said to have “Timed Out” if Authority decision has not been made in time to allow implementation by the proposed date  “Timing Out” identified as an industry issue in 2007 following Balancing & Settlement Code (BSC) mods P198, P200, P203 & P204  Following “Timed Out” BSC mods, Judicial Review deemed that Authority lost ability to decide on “Timed Out” Mods  Ofgem sought views on potential solutions to eliminate risk of “Timing Out” re-occuring & recommended either changes to licenses or industry codes (May 09)  Mod represents National Grid NTS’ view on most efficient solution

Proposed Changes (1)  Change Mod Rules to include a more structured approach to including suggested implementation dates within mod templates;  A minimum of two suggested fixed implementation dates with the associated decide by dates, e.g.  Decide by 18 th February for implementation on 18 th March  Decide by 18 th April for implementation on 18 th May, and  One suggested flexible implementation date, e.g.  Two Calendar Months after an Authority Decision  Important to remember that both type of dates above are required if User chooses to include a suggested date within the proposal  Users will still be able to leave suggested date blank if not critical or practical to include

Proposed Changes (2)  Users wishing to include suggested implementation dates must include accompanying justification for chosen dates  Applies to all type of proposals  All implementation dates provided within proposals will continue to be “Suggested”  Suggested implementation dates will continue to be non-binding  Transporters will continue to confirm the implementation date at the time of the Authority decision has been made

Purpose & Expected Benefits  Ensure greater clarity of mod implementation dates to industry  Promote development of possible implementation options within Mod proposals  Provide consistent structure for presentation of suggested implementation dates  Promote development of justification to support suggested implementation dates  Stimulate industry debate of optimal implementation timings & costs (particularly relevant to User Pays proposals)  Apply industry best practise & promote consistency across industry codes  Remove risk to industry of “Timing Out”  Improved consideration of possible options to aid industry understanding  More detailed analysis of the most cost efficient implementation date  More informed representations and Authority decisions  Allows realisation of mod benefits at earliest opportunity  No wasted / duplicated effort in re- raising Mod proposal  Better facilitation of relevant objectives associated with mod process (A11.2 9) & UNC (A11.1 (f)) PurposeBenefits

Any questions / suggestions to aid clarity?  ??