1 Provincial Treasury Western Cape NCOP Select Committee on Finance Public Hearings Conditional Grant and CAPEX 20 November 2006
2 Outline Conditional grant, infrastructure and capital expenditure 2005/06; 2006/07 second quarter expenditure; Business plan 2006/07 and 2007/08 process; and Monitoring provincial expenditure.
3 Conditional Grant, Infrastructure and Capital Expenditure 2005/06
4 CG Expenditure 2005/06 Conditional Grant Expenditure – 2005/06 2 nd and 4 th quarter
5 CG Expenditure 2005/06 (2) Although expenditure was below notional benchmark of 50 per cent for some conditional grants at the end of the 2nd quarter of 2005/06, by the end of the financial year all grants had performed well.
6 Capital and Infrastructure Expenditure 2005/06 Adjusted4th quarter expenditure R000'sbudgetR'000% Education % Health % Agriculture % Transport and Public Works % Total % Total4th quarter expenditure R000'savailableR'000% Payments for capital assets % 2005/06 - Infrastructure and capital expenditure Infrastructure and capital expenditure was at an acceptable level at the end of the 2005/06 financial year
7 2006/07 2nd Quarter Expenditure
8 CG Expenditure - Agriculture DORA 2006 Transfers received Spent by Province spent as % of DORA Spent as % transfers received Land care programme %91.4% Comprehensive Agricultural Support Programme %44.5% Provincial Infrastructure Grant %299.1% Total %50.6% Agriculture – Conditional Grant Expenditure as at 30 September 2006
9 CG Expenditure – Agriculture (2) Challenges to Overcome –Land Care Programme Expenditure is season dependent as invasive plants grow in summer and the eradication thereof can only take place once crops have been harvested –Comprehensive Agriculture Support Programme Difficult to get community agreement on project plans Delay in tender process
10 CG Expenditure - Education DORA 2006 Transfers received Spent by Province spent as % of DORA Spent as % transfers received FET College Sector Recapitalisation %100.0% HIV and Aids (Life Skills Education) %118.7% National School Nutrition Programme %84.8% Provincial Infrastructure Grant %59.9% Total %84.4% Education – Conditional Grant Expenditure as at 30 September 2006
11 CG Expenditure – Education (2) Challenges to Overcome –National School Nutrition Programme Grant The reduction in the number of school days as a result of the winter school holidays has resulted in lower than expected expenditure –Provincial Infrastructure Grant A number of projects are in the tender and awarding phase Seasonality of the Western Cape impacts infrastructure expenditure Department projects to spend entire budget by the end of the financial year
12 CG Expenditure - Health DORA 2006 Transfers received Spent by Province spent as % of DORA Spent as % transfers received National Tertiary Services %101.0% Health Professions Training and Development %100.0% Comprehensive HIV and Aids %106.2% Forensic Pathology Services %25.1% Hospital Revitalisation %79.3% Provincial Infrastructure Grant %74.1% Total %96.0% Health – Conditional Grant Expenditure as at 30 September 2006
13 CG Expenditure – Health (2) Forensic Pathology Services –Constraints in the appointing of staff for the Forensic Pathology Services Unit Hospital Revitalisation Grant –Slow progress has been reported on large projects (Worcester, Paarl and Khayelitsha) –The Department projects to spend the entire budget by the end of the financial year Provincial Infrastructure Grant –Expenditure slow as a result of projects being put on hold in 2005/06 –Experienced professionals are leaving the department –Seasonality of the Western Cape impacts infrastructure expenditure –The Department projects to spend the entire budget by the end of the financial year
14 CG Expenditure – Local Government and Housing DORA 2006 Transfers received Spent by Province spent as % of DORA Spent as % transfers received Integrated Housing and Human Settlement Development %100.6% Local Government and Housing – Conditional Grant Expenditure as at 30 September 2006 Expenditure on the IHAHSDG is higher than transfers received
15 CG Expenditure – Transport and Public Works DORA 2006 Transfers received Spent by Province spent as % of DORA Spent as % transfers received Provincial Infrastructure Grant %48.5% Transport and Public Works – Conditional Grant Expenditure as at 30 September 2006 Challenges to Overcome Provincial Infrastructure Grant - A large number of projects are in the tender and design stage -Seasonality of the Western Cape impacts infrastructure expenditure -Department projects to spend entire budget by the end of the financial year
16 CG Expenditure – Cultural Affairs and Sport DORA 2006 Transfers received Spent by Province spent as % of DORA Spent as % transfers received Mass sport and Recreation Participation Programme %45.5% Cultural Affairs and Sport – Conditional Grant Expenditure as at 30 September 2006
17 CG Expenditure – Cultural Affairs and Sport (2) Challenges to overcome –Mass Sport and Recreation Participation Programme 20 new hubs funded from April 2006/07 Currently, stipends only being paid for 11 hubs which are already in place Payment of stipends for 20 new hubs will commence in October 2006, backdated to August 2006
18 Infrastructure and Capital Expenditure Infrastructure and capital expenditure as at 30 September 2006 *Infrastructure expenditure includes maintenance which is recorded as current expenditure in SCOA AdjustedSecond Quarter Expenditure R000'sbudgetR'000% Education % Health % Agriculture % Transport and Public Works % Total % Total1st quarter expenditure R000'savailableR'000% Payments for capital assets %
19 Infrastructure and Capital Expenditure Challenges to Overcome –Bottlenecks in the procurement process, IDIP aims identify these bottlenecks and identify means to overcome them; –Inefficiencies in the link between planning; budgeting and implementation; and –Skills shortage. Measures instituted –Promotion of earlier planning cycle (IDIP).
20 Conditional Grant Business Plans 2006/07 Financial Year
21 CG Business Plans Business plans 2006/07 –All business plans for 2006/07 have been approved Business plans 2007/08 –Department of Agriculture Land Care Grant –Business plan submitted, awaiting feedback from National Department. Comprehensive Agriculture Support Programme –Business plan submitted to the national department
22 CG Business Plans 2007/08 –Department of Education HIV and Aids (Life Skills Education) Grant –Business plan submitted, awaiting feedback from National Department of Health National School Nutrition Programme Grant –Business plan submitted, feedback received from national department Further Education and Training –DORA requires submission to be made by 25 November 2006, first draft will be ready for submission by 22 October 2006
23 CG Business Plans 2007/08 –Department of Health Comprehensive HIV and Aids Grant –Business plan submitted, awaiting feedback from the national Department of Health Forensic Pathology Services Grant –Business plan completed in consultation with national Department of Health and submitted 23 October 2006 –Signed copy submitted 17 November 2006 National Tertiary Services Grant –Awaiting Service Level Agreement from National Department of Health Health Professions Training and Development Grant –Business plan format in process of finalisation by Department of Health
24 CG Business Plans 2007/08 –Department of Local Government and Housing Integrated Housing and Human Settlement Development Grant –Business plan submitted, awaiting feedback from national department –Department of Cultural Affairs and Sport Mass Sport and Recreation Participation Programme Grant –Business plan submitted, awaiting feedback from national department –National Treasury Provincial Infrastructure Grant –Consolidated infrastructure plan submitted to National Treasury
25 Monitoring Provincial Expenditure
26 Monitoring Provincial Expenditure Continuous engagements with departments in a cooperative manner to jointly seek solutions; Quarterly reports to Top Management, Exco and Legislature; Frequent interaction with departments on spending performance and general issues as highlighted by monthly IYM’s; Quarterly narrative reports to AO’s and CFO’s; Quarterly meetings between MEC’s for finance, education, health and public works to discuss infrastructure spending and other difficulties; Specific provincial initiatives to ameliorate the March spike; and CFO intergovernmental forums.
27 Discussion