Fehr & Peers | March 13 th, 2012 Traffic Access and Circulation Analysis Pinole Valley High School Reconstruction.

Slides:



Advertisements
Similar presentations
Transportation Impact Analysis Presented By Katy Flynn, P.E. Fehr & Peers February 19, 2008.
Advertisements

How Costcos Mega Gas Station Will Create Traffic Congestion An Analysis: Text and Pictures.
What is the S-48 Corridor? Study Area What’s Happened So Far? Previous Tasks  Project InitiationJune 2005  Existing ConditionsOct  Planning.
NICHOLS SCHOOL TRAFFIC OPERATIONS STUDY. Existing Operations Examined Data Collection  On-site Count Collection of Representative Traffic Conditions.
Bailey Hill Road Safety Coalition Report to Churchill Area Neighbors Julia Pommert and Sue Palsbo January, 2008 Contact:
City of Omak Central Avenue Bridge Replacement Project Prepared by Highlands Associates Photos by FlyBy Photos.
1 Support Graphics for Traffic and Circulation Princeton Junction Redevelopment Area Township of West Windsor September 8, 2008 Urbitran | DMJM Harris.
General Overview of Parking Requirements. Standard 8 ½ x 17 feet Parallel 22 x 6 ½ feet 8.5 feet 17 feet 6.5 ft 22 feet.
West Contra Costa Unified School District
What are “Pinch Points” PPinch Points are areas identified on the Highways Agency network of roads that experience high levels of congestion TThe.
Reston Master Plan Thoughts on transportation. Focus is important Without the proper transportation groundwork other plans will fall through.
TRANSPORTATION CORRIDOR OVERLAY DISTRICT ROUTE 29.
Redwood Road & 35th Avenue Traffic Study. Problems Observed: High collision rate along the corridor was found at McArthur Boulevard intersection, with.
NORTHFIELD COMMUNITY SCHOOL Elementary School Entrance Cedarbridge Road Side NORTHFIELD POLICE NJ 1.
Idaho Public Driver Education Urban & Freeway Driving.
1 Evaluation of Ports of Entry (POE) for the International Border in the El Paso MPO Study Area.
Wimbledon Station - a station fit for Chris Chowns (Principal Transport Planner) Nick Greenwood (Transport Planning Manager) LB of Merton Transport.
Route 28 South of I-66 Corridor Safety and Operations Study Technical Committee Meeting #2 June 25,
1 Channelization and Turn Bays CE 453 Lecture 31.
Miller Road Feasibility Study & Reconstruction Project Information and Kick-off Meeting Presented by: The Corradino Group of Michigan, Inc. ROWE INC. Genesee.
NORTHFIELD COMMUNITY SCHOOL Middle School Entrance Mill Road Side NORTHFIELD POLICE NJ 1.
Transport.tamu.edu Northside Parking Garage Study TSAC April 3, 2013.
Evaluating Robustness of Signal Timings for Conditions of Varying Traffic Flows 2013 Mid-Continent Transportation Research Symposium – August 16, 2013.
Going from 4 Lanes to 3 Lanes Jefferson City’s McCarty Street Project.
Traffic improvements around a school. Horseshoe Lane West Create drop-off / pick-up point at side of road so that road doesn’t get blocked with traffic.
Lexington Town Center Streetscape Project Page 1 Battle Green Improvements Project Intersection of Bedford Hancock Street / Harrington Road Board.
Greenwood Transit and Sidewalk Project N 90th St to N 105th St Community Open House Sarah Butler, Project Manager September 14, 2015 Presentation begins.
From EMME to DYNAMEQ in the city of MALMÖ. THE COMPANY Founded in early 2011 Currently located in Stockholm, Gothenburg and Malmö Small company (currently.
Orem City Roundabout Feasibility Study Brigham Young University and the City of Orem Determination of available land Roundabout parameters established.
South Parkway Refinement Plan F Context of the plan F Goals of the plan F Major issues F Parkway/Third Street alternatives F City of Bend, ODOT assess.
BRT in India Delhi Case study. What is Delhi HCBS Delhi HCBS is not a BRT system. It is primarily a road infrastructure project. It was not conceived.
Tshwane Line 1 Traffic Simulation Results October 2012.
Route 1 Project Study Report Overview. A report that describes the transportation problem and identifies the project scope, schedule and estimated cost.
Roosevelt Road: State to Columbus Public Meeting September 22, 2015.
Outside Behavior. Be Respectful Play fair – so that others will want to play with you again.
Transportation and Transit Committee 4 December 2002 Albion Road Corridor Study.
Freeway Congestion In The Washington Region Presentation to National Capital Region Transportation Planning Board February 15, 2006 Item # 9.
1. Variety of modes (types) of transport (public and private) 2. Density of transport networks more nodes and.
Signs Signals and Pavement Markings
DVRPC TMIP Peer Review Dynamic Traffic Assignment (DTA) Oct. 29 th, 2014.
Fern Valley Interchange Project Development Team Meeting February 3, :00 – 11:00 p.m.
TEAM Presentation January 21, Overview Top MoDOT Priority Top MoDOT Priority A Funding challenge A Funding challenge Desperately needed Desperately.
Introduction Study area Existing problem Objective Methodology Results and Conclusions Recommendations.
Intersections.
September 15, 2011 Presented by: Clay Harris, PMP - City of Austin Federico Mendoza, PE, PTOE – Brown & Gay Engineers, Inc. Todd Lane Alternative Geometric.
Rainier Avenue South Pilot Project Update Seattle Bicycle Advisory Board Project Manager Jim Curtin September 2, 2015.
FACILITIES MASTER PLAN FMP Review October TIME LINE 2014November 2015 February March April May October / November December Education / Facility.
Travel Reliability – Reliable traffic flow is more important than reducing congestion – traffic congestion is often a sign of an area’s economic vitality.
COUNTY ROAD 517 Improvements from State Highway 172 to Howe Drive DECEMBER 16, 2015 At Tribal Multipurpose Facility.
© 2014 HDR, Inc., all rights reserved. North Country Access Improvements Stakeholder Advisory Committee Meeting No. 9 January 19, 2016.
Fehr & Peers | December 13 th, 2011 Traffic Access and Circulation Analysis Pinole Valley High School Reconstruction.
Signs, signals,& Road Markings
INTEGRATING ASSESSMENT OF THE ECONOMIC BENEFITS OF TRANSPORTATION IMPROVEMENTS IN PROJECT-LEVEL ALTERNATIVES ANALYSIS Meiwu An, Pikes Peak Area Council.
SPEED TABLES FOR CORONADO ROAD BETWEEN 7 TH STREET AND 10 TH STREEET.
SEPARATED BIKE LANE PLANNING AND DESIGN GUIDE. Separated Bike Lane Planning and Design Guide Context Conforms to federal and state standards and guidelines:
 May 1, 2012 City Council approved lease of premises at MLK to the Lycée Français La Pérouse (the “Lycée Français”)  Under section 16.5, Traffic and.
District VI, Florida Department of Transportation SE 2 nd Avenue and SE 4 th Street/Biscayne Boulevard Way March 25 th, 2014 Bicycle/Pedestrian Advisory.
FOOTHILL ELEMENTARY TRAFFIC PROBLEM SOLVING May 19, :30 p.m.

Montana Driver Education and Training Traffic Control Devices and
Macro / Meso / Micro Framework on I-395 HOT Lane Conversion
JUAN DE FUCA PEDESTRIAN CROSSING Transportation and Public Infrastructure Committee Colwood, BC 1 October 2012.
Study Goals Analyze traffic operations along the corridor and at the two study interchanges Provide safety enhancements Improve multimodal performance.
Citrus Park Drive Extension
Advisor: Prof. Yue Liu A Microscopic Agent-based Simulation System for Sustainable Off-street Parking facilities Yun Yuan Advisor:
Traffic Impact of Pedestrianisation in Stellenbosch
Traffic Flow Improvement at the Gate 1
WELCOMES YOU TO THE COMMUNITY OPEN HOUSE OCTOBER 2018.
Colorado Avenue University of Colorado, boulder
Module 6 A 21st Century Transportation Network
Presentation transcript:

Fehr & Peers | March 13 th, 2012 Traffic Access and Circulation Analysis Pinole Valley High School Reconstruction

Scope of Work 1.Data Collection and Field Observations 2.Existing Conditions Traffic Model Development/Validation 3.Development of Access/Circulation Alternatives 4.Analysis of Alternatives 5.District and City Review 6.Selection of Preferred Alternative 7.Construction Period Traffic and Parking Management Plan

Data Collection and Field Observations February 9, 2011 Counted autos, pedestrians, bicyclists, buses 7:00 – 9:00 AM, 2:15 – 4:00 PM Observed directionality, parking behavior, traffic queuing, jaywalking, and unsafe maneuvers AM Peak Hour Observations Traffic queues extend back to shopping center Unsafe pedestrian movements Poorly regulated traffic flows – drop-off’s occur in travel lane PM Peak Hour Observations Traffic jams on-site Traffic queues from north end to Ramona Unsafe pedestrian movements Poorly regulated traffic flows

Existing Observations

Development of Access/Circulation Alternatives Reduce congestion during peak periods Accommodate drop-offs and pick-ups on-site Accommodate more parking on-site Separate ingress and egress traffic flows Separate traffic flows to/from parking lot and to/from drop-off aisle Provide for safe, controlled pedestrian crossings on Pinole Valley Road Goals:

Alternatives Analysis All alternatives have a new signal at the northern parking lot driveway Alternative 1 : Traffic signal at School Exit/Estrella only Alternative 2 : Traffic signal at Shea/Granada only Alternative 3 : Traffic signal at School Exit/Estrella and Shea/Granada Alternative 4 : No traffic signal at School Exit, Shea/Granada as existing

Current Plan: Alternative 3

Simulations Alternative 3 Alternative 3 : Traffic signal at School Exit/Estrella and Shea/Granada Alternative 4 Alternative 4 : No traffic signal at School Exit, Shea/Granada as existing