Impacts and Actions Resulting from the August 14, 2003 Blackout Minnesota Power Systems Conference November 2, 2003.

Slides:



Advertisements
Similar presentations
August 14, 2003 Blackout Summary Based on Interim Report of the
Advertisements

2004 NERC, NPCC & New England Compliance Programs John Norden Manager, Operations Training, Documentation & Compliance August 31, 2003 RC Meeting.
NERC Policies Introduction
WECC Board of Directors April 21-23, 2004 Seattle, Washington WECC Procedure for Reporting of System Events Disturbance Reports Rod Maslowski OC Vice Chairperson.
NERC TPL Standard Issues TSS Meeting #146 Seattle, WA August 15-17, 2007 Chifong Thomas.
Notice of Proposed Rulemaking on Standards WECC Board of Directors Meeting December 7-8, 2006.
NERC Reliability Readiness The Next Steps Mitch Needham NERC Readiness Evaluator September 24, 2007.
Key Reliability Standard Spot Check Frank Vick Compliance Team Lead.
NERC Compliance An NWP Perspective
The Mathematics of the Great U.S. Blackout August 14, 2003 Ralph Fehr, P.E. Engineering Consultant.
August 14, 2003 Blackout Final Report
1 MISO Business Plan: Enhanced Reliability, Customer Service & Market Implementation James P. Torgerson, President & CEO Midwest ISO December 17, 2003.
1539pk 2003 MAJOR POWER GRID BLACKOUTS IN NORTH AMERICA AND EUROPE Copyright © P. Kundur This material should not be used without the author's consent.
NERC and Regional Efforts to Ensure Reliability Dave Nevius, NERC Sr. VP David Cook, NERC VP & General Counsel Louise McCarren, WECC CEO Don Benjamin,
System Operator Conference NERC Standards Review for: Simulator Drill Orientation 2014 System Operator Conferences Charlotte NC & Franklin TN SERC/SOS.
Environmental Management Systems Refresher
Applying a Systems Approach EPA Regions 9 & 10 and The Federal Network for Sustainability.
ERCOT’S COMPLIANCE ASSESSMENT PROGRAM Mark Henry Compliance Manager March 23, 2005.
Electric Power Infrastructure: Status and Challenges for the Future Mark Lauby Director, Reliability Assessments and Performance Analysis.
Review of Power Blackout on Telecom P. J
August 2003 Blackout Review Brant Eldridge Executive Manager - ECAR.
1 Blackout 2003 See:
Averting Disaster - Grid Reliability Issues and Standards National Energy Restructuring Conference April 1, 2004 Washington, DC.
ERCOT Compliance Audits Robert Potts Sr. Reliability Analyst March 23, 2005.
Determine Facility Ratings, SOLs and Transfer Capabilities Paul Johnson Chair of the Determine Facility Ratings Standard Drafting Team An Overview of the.
Recommendations from 2011 Southwest Outage Heather Polzin, FERC Office of Enforcement Dave Nevius, Senior Vice President, NERC Member Representatives Committee.
Basics of OHSAS Occupational Health & Safety Management System
Nuclear Power Plant/Electric Grid Regulatory Coordination and Cooperation - ERO Perspective David R. Nevius and Michael J. Assante 2009 NRC Regulatory.
APPA RELIABILITY STANDARDS & COMPLIANCE SYMPOSIUM Case Study: City Utilities of Springfield, MO January 11, 2007.
Implementing the New Reliability Standards Status of Draft Cyber Security Standards CIP through CIP Larry Bugh ECAR Standard Drafting Team.
VISUALIZATION WHY WE NEED SYNCHROPHASOR TECHNOLOGY IN OPERATIONS John Ballance – EPG Presented to ERCOT Phasor Technology Workshop – November 16, 2012.
Page 0 Eastern Interconnection Phasor Demonstration Enhanced Wide-Area Visibility In the Eastern Interconnection for Reliability Management Transmission.
FERC’s New Reliability Initiatives Kevin Kelly Director, Policy Analysis, OMTR Federal Energy Regulatory Commission NARUC Annual Meeting Nashville, TN.
Actions Affecting ERCOT Resulting From The Northeast Blackout ERCOT Board Of Directors Meeting April 20, 2004 Sam Jones, COO.
1 Texas Regional Entity 2008 Budget Update May 16, 2007.
Overview of WECC and Regulatory Structure
Status Report for Critical Infrastructure Protection Advisory Group
1 August 14, 2003 Blackout MAC Meeting October 8, 2003 Paul Murphy IMO.
Item 5d Texas RE 2011 Budget Assumptions April 19, Texas RE Preliminary Budget Assumptions Board of Directors and Advisory Committee April 19,
February 26, 2013 Board of Directors Meeting 2012 ERCOT Region Reliability Update.
ISO Outlook Summer 2005 and Beyond Senate Energy, Utilities and Communications Committee February 22, 2005 Jim Detmers Vice President of Grid Operations.
Bill Lewis, Compliance Team Lead NERC Reliability Working Group May 16, 2013 Texas RE Update Talk with Texas RE April 25, 2013.
1 RIC 2009 Nuclear Power Plant/Electric Grid Regulatory Coordination and Cooperation George Wilson NRR/ADES/DE/EEEB March 11, 2009.
RELATIONSHIP BETWEEN COMPETATIVE POWER MARKETS AND GRID RELIABILITY PJM RTO EXPERIANCE vis – a – vis PRACTICES FOLLOWED IN INDIAN GRIDS.
Draft Reliability Standards Development Plan Ryan Stewart, NERC Manager of Standards Development Texas RE NSRS August 17, 2015.
©2004 PJMwww.pjm.com 1 PJM's Perspective on Reliability – Summer 2004 and Beyond Karl Pfirrmann President -- PJM Western Region FERC Summer Reliability.
COMPLIANCE ROLLOUT Vann Weldon Compliance Training Administrator March 23, 2005 NERC FUNCTIONAL MODEL REVIEW.
Moving Forward Overview of the 2003 Blackout. Overview Power system restored within 30 hours Conservation efforts avoided rolling blackouts once power.
NERC Event Analysis Overview ERCOT ROS Meeting Austin, Texas May 15, 2006.
Grid Reliability Metrics by Jim Dyer Electric Power Group, LLC January 29, 2004 Washington, DC Transmission Reliability Research Review.
1 Texas Regional Entity Report November Performance Highlights  ERCOT’s Control Performance Standard (NERC CPS1) score for September –
1 Power System Restoration. 2 Not Active 3 4 Compliance Audit Process APPA E&O Technical Conference – Atlanta April 16, 2007.
1 MOSC Presentation Grid Collapse 2003 September 22/2004 Information is preliminary subject to ongoing investigations Certain material is from NERC and.
Compliance Update Larry Grimm ERCOT Compliance To The ERCOT Board of Directors September 20, 2005.
FRCC Regional Entity Webinar NERC Reliability Standard Development Projects and Situational Awareness and Event Analysis October 30, 2013, 1:00 p.m. –
Role of Account Management at ERCOT 2006 TAC Subcommittee Review ERCOT Board February 21, 2006.
PJM©2014www.pjm.com A System Operator’s Resilience Wish List Tom Bowe Executive Director Reliability and Compliance PJM Interconnection
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
Maryland Public Service Commission 2006 Summer Reliability Status Conference May 16, 2006 Baltimore, MD.
1 Early Intervention Monitoring Wyoming DDD April 2008 Training.
SEMINAR PRESENATATION ON WIDEAREA BLACKOUT (AN ELECTRICAL DISASTER) BY:Madhusmita Mohanty Electrical Engineering 7TH Semester Regd No
Reliability Standards Committee 2009 Scope and Plan Judith James Manager, Reliability Standards.
NERC Reliability Readiness The Next Steps
NERC Lessons Learned Summary
Joint U.S.-Canada Power System Outage Investigation
NERC Cyber Security Standards Pre-Ballot Review
Cold Snap Task Force Update
Impacts and Actions Resulting from the August 14, 2003 Blackout
Blackout Investigation Organization
Blackout Investigation Organization
Presentation transcript:

Impacts and Actions Resulting from the August 14, 2003 Blackout Minnesota Power Systems Conference November 2, 2003

Summary of August 14 Blackout ● Impacts  Over 50 million people  60-65,000 MW  30 hours to restore  Manufacturing disrupted  400+ Generators tripped ● Statistics  Line trips began at 3:05 PM  Cascading began at 4:06 PM  Lasted approximately 12 seconds  Thousands of discrete events

1:31:34 p.m. August 14, 2003 What Happened? 765kV DC Voltage Montreal Ottawa Toronto Detroit Cleveland Akron Canton Buffalo New York Pittsburg Toledo 2:02 p.m.3:05:41 to 3:41:33 p.m.3:45:33 to 4:08:58 p.m.4:08:58 to 4:10:27 p.m.4:10:00 to 4:10:38 p.m.4:10:40 to 4:10:44 p.m.4:10:44 to 4:13:00 p.m.

Every Blackout has Impacts ● November 9, 1965 – NY Blackout  30,000,000 people and over 20,000 MW of demand – up to 13 hours ● July 13, New York City  9,000,000 people and 6,000 MW of demand – up to 26 hours ● July 2, 1996 – Western US  2,000,000 customers (10 % of the Western Interconnection) and 11,850 MW of demand for up to several hours ● August 10, 1996 – Western US  7,500,000 customers; 28,000 MW of demand for up to 9 hours

Recommendations ● The three Ts  Tools  Trees  Training Need to implement throughout the industry

Investigation Organization Overview Steering Group MAAC/ECAR/NPCC Coordinating Group MAAC ECAR NPCC MEN Study Group Project Planning and Support Sequence of Events Data Requests and Management Investigation Team Lead System Modeling and Simulation Analysis NERC & Regional Standards/Procedures & Compliance Transmission System Performance, Protection, Control Maintenance & Damage Operations - Tools, SCADA/EMS Communications Op Planning System Planning, Design, & Studies Root Cause Analysis Cooper Systems Generator Performance, Protection, Controls Maintenance & Damage U.S – Canada Task Force Vegetation/ROW Management Frequency/ACE Restoration Investigation Process Review

Causes of the August 14 Blackout ● Inadequate situational awareness ● Ineffective vegetation management ● Inadequate diagnostic support ● Failure to follow NERC Operating Policies and Planning Standards

Near-Term Actions ● Voltage and Reactive Management  Ensure sufficient voltage support for reliable operations ● Reliability Communications  Strengthen and implement communication protocols between Control Area Operators, Reliability Coordinators, and ISOs ● Failures of System Monitoring and Control Functions  Review, update, and train on plans for loss of monitoring and control systems

Near-Term Actions ● Emergency Action Plans  Review, update, and train on emergency plans and actions ● Train for Emergencies  Conduct emergency training drills ● Vegetation Management  Confirm that ROWs are clear of obstructions

Other Key Findings ● Inadequate system planning and design studies, operations planning, facilities ratings, and modeling data accuracy ● Operating with insufficient reactive margins ● More effective system protection and controls could slow or minimize spread of cascading outage

Other Key Findings ● Compliance requires objective measurements and concrete actions to resolve violations ● Problems from prior blackouts were repeated

NERC Blackout Recommendations ● Corrective Actions ● Strategic Initiatives ● Technical Initiatives Goals: 1. Correct root cause deficiencies 2. Address contributing factors 3. Identify objective and measurable actions

Corrective Actions: FE ● Voltage criteria and reactive resources ● Operational preparedness and action plan ● Emergency response capabilities and preparedness ● Control center and operator training

Corrective Actions: Reliability Coordinators ● PJM  Communications protocols and procedures ● MISO  Reliability tools  Visualization tools  Operator training  Communications  Operating agreements

NERC Strategic Initiatives ● Strengthen compliance ● Readiness audits ● Vegetation-related outage reporting ● Track implementation of recommendations

Performance Reviews ● Strengthen NERC Compliance Enforcement Program  Regions to submit results to NERC  Provide list of non-compliant entities ● Confidential reports to the NERC Board  Specific violations  Results of audits ● Release of confirmed violations  Identification of violators

Readiness Audits ● Audit control areas and reliability coordinators ● Conduct on a 3-year cycle ● Report to the Board

Readiness Audit Program Status ● On target to audit one-third of control areas and reliability coordinators in 2004 ● Audits Completed as of October 14, 2004  43 Control Areas  4 Reliability Coordinators  1 Transmission Operator

Vegetation-Related Outage Reports ● Report tree contacts to the Regions (230+ kV) ● Regions report to NERC ● Regions to conduct and report on annual vegetation management surveys

Recommendations Tracking ● NERC and Regions will track:  Implementation of recommendations  Compliance audits  Readiness audit recommendations  Lessons learned from system disturbances  Use regional processes as model

Technical Initiatives ● Forward looking to prevent future blackouts  New standards, procedures, protocols  Existing technologies to be considered  New technologies  Changes in system planning, design, and assessment  Changes to operator training programs

Next Steps ● Implement strategic initiatives and recommendations ● Readiness audits ● Enact reliability legislation – mandatory standards and compliance enforcement