SCT week: 14th - 16th Dec 04 Spine progress R. Bates University of Glasgow.

Slides:



Advertisements
Similar presentations
D-Cal production preparations in Japan Dec. 16, 2009, D-Cal meeting at CERN Tatsuya Chujo (Univ. of Tsukuba) for the D-Cal Project 1.
Advertisements

SCT BARREL PAR - RAL May 2003 Status of Barrel Mechanical Structures - Cylinder manufacture - Bracket and small components manufacture - Dry assembly.
Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
27 September 2005A.Ciocio - ID Week1 SCT Service Installation Overview Status of Type IV Cable Installation Type II/III Cable Installation Plan for the.
July 28, 2011 ITER Thomas J. Vanek Senior Policy Advisor Fusion Energy Sciences.
IHEPTrip Cherrill Spencer 12/20/05 1 Report on my December 2005 Trip to IHEP, Beijing to Monitor Fabrication of ATF2 Quads By Cherrill Spencer, SLAC, for.
Hd Status and Planning TRD Chamber Construction Meeting Clemens Adler.
MICE Video Meeting, 10 Jan 081 Spectrometer Magnet Progress Michael A. Green Lawrence Berkeley Laboratory.
29 November 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status of Type IV installation Connector in situ work Status of PP3 Testing.
Surgical Reprocessing (SRP) Performance Dashboard for Improved Service Team Members : John Rodriguez Jose Gonzalez Surgical Reprocessing Team Members Patricia.
TMDB delay and production plan Augusto. TMDB Prototype Status The prototype boards almost fully assembled should be delivered this week ( May 5 th ) First.
25 October 2005A.Ciocio - SCTSG1 Type IV Cables and PP3 Status & Plan.
J A Hill – EID RAL 1-2 September EE End Cap Mechanical Design ECAL EE End Cap Engineering CMS-UK Collaboration Meeting Brunel University September.
Challenges and Overview From Technical Coordination 27/08/2013 -FH1.
Crop Market Price Outlook Utilizing Cash Marketing Tools Selling Old & New Crop Corn & Soybeans Crop Market Outlook & Risk Management Strategies December.
Status of CERN M1R2 production LHCb Muon meeting sept.061Thomas Schneider -Beginning of 2006 two visits to Erbicol because of several reasons: -Material.
AGATA Pre-processing team report AGATA Week, July 2008.
ATF2 quads status 22Nov05- Cherrill Spencer 1 Status Report on the Design and Fabrication of 29 quads for ATF2 By Cherrill Spencer, SLAC, for ILC-BDS weekly.
Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.
ETI 301 Business Correspondence-II Neslihan Kansu-Yetkiner.
Status of AMS02 Integration Area in Building 867 January 10, 2007.
News on mechanics Photon veto F. Raffaelli INFN – Sezione di Pisa CERN, January r 02 th, Status of tender Anti Status of the supporting.
November 12, Professional Development Calendar: HU Cycle 1 Aug. 10Aug. 17Aug. 24Aug. 31Sept. 7 First week check- ins Campus specific PD PGP cycle.
Endcap Module Status Agreed Responsibilities Overall Production UK Situation Global Schedule Issues General Production Issues.
 YE+4 disks = 2 Nos. (12 Sectors each)  Support Structures = 2Nos.  AISI 1045 steel bar = 1 No. for checking dimension of 680 mm (0/-0.5)  Fasteners.
ATLAS Endcap Signal Feedthrough Project Status Report Pin carrier Procurement Summary Feedthrough Production QA/QC Shipment to CERN Reception Tests at.
1 HCAL production, QC and preparation for installation Overview of the status report Rustem DZHELYADIN (IHEP, Protvino)  The general status.
EMCal Status ALICE Technical Board November 20, 2008 News Schedule.
1 Norfolk Girls Softball Technical Operations Roles & Responsibilities November, 2011.
EUROPE Nov 27 –Dec 10 November 27 - Dec 10.
1 ME1/1 ODMB Production Readiness Review: Schedule and Budget Darien Wood Northeastern University For the ME1/1 Electronics Project.
Non Leap YearLeap Year DateDay NumberMod 7Day NumberMod 7 13-Jan Feb Mar Apr May Jun Jul
South East Fire & Rescue Services Regional Management Board Equalities Review Update 10 th October 2007.
A Vaccine Supply Update For The U.S. Market A Presentation At National Advisory Committee Meeting February 4, 2003 Dean Mason Chief, Program Support Branch.
D. Greenfield CLRC1 UK-V End-cap Engineering 15 July 2003 Debbie Greenfield, RAL.
Hi-Lumi Conductor Procurement A.Ballarino, B. Bordini, L. Oberli HL-LHC/LARP International Review of Superconducting Cable for the HL-LHC Inner Triplets.
LAr Week Feb 2000 M. Lefebvre Milestones and Schedule General Production Readiness Review  Passed in Jan 99 Leak Test Station and Electric Test.
Lavs Issues Lav 12. Tube Planning future activities. Conclusions.
This is an example text TIMELINE PROJECT PLANNING DecOctSepAugJulyJuneAprilMarchFebJanMayNov 12 Months Example text Go ahead and replace it with your own.
M. TYNDEL 1 LHCC Interactions May 2003 ATLAS SCT SCT Production Status ‘Snap-shot’ of the status of the SCT production (May 2003) 1. Barrel Modules 2.
Ian Crotty HPL (Bakelite) Low Eta TDR Up-Scope 05 Feb 10 HPL for the Up-Scope of the CMS RE Low Eta as per the 1997 TDR in CMS Contents Specification Contingency.
Module Assembly Jig Status Cambridge and DESY came to Liverpool Nov. 15 th -16 th for training on module assembly – A complete jig set was sent back with.
Hybrid and Module Status 1. Hybrid Delivery First hybrids over-etched and shrunk due to changes in design and mistakes in manufacturing – Shrinkage for.
Furniture Prequalification Scheme SCM0771 Briefing 17 th November 2014.
N. Dixon PH / DT Vladimir Elsha JINR Straw working group meeting Monday 6th April 2011 CERN1 Straw Material and development.
ESS WP4 Strategy for series production ESS TAC10 – 5th to 6th November Lund Sébastien Bousson WP 4 leader.
“Estimated” Corn Field Drying
BSS Prep work at CERN and Acceptance of Parts
Shipping (#4) of the components for 100’s Head welding.
CMS WEEK Sept. 24 Opening session CMS MUONS: Barrel Drift Tubes
R. Bates UK-V meeting Liverpool, 21/04/2004
LS1 Committee January 24th, 2014
SCHEDULE Nov 1st - Assembly Table Complete
Adjusting Entries Examples
Average Monthly Temperature and Rainfall
13-block rotation schedule
Module Production in Brussels
Shipping (#4) of the components for 100’s Head welding.
FY 2019 Close Schedule Bi-Weekly Payroll governs close schedule
PBIS Update November 2005.
PBIS Update December 2005.
2009 TIMELINE PROJECT PLANNING 12 Months Example text Jan Feb March
Agricultural Marketing
Month Rainfall (mm) Temp Jan Feb March 34 April 38 May June July
JUNE 2010 CALENDAR PROJECT PLANNING 1 Month MONDAY TUESDAY WEDNESDAY
How Does Your Company Handle This?
2009 TIMELINE PROJECT PLANNING 12 Months Example text Jan Feb March
Globus-M2 will be constructed by the end of 2015
PBIS Update January 2006.
Ft. Benning Office Hours
Presentation transcript:

SCT week: 14th - 16th Dec 04 Spine progress R. Bates University of Glasgow

SCT week: 14th - 16th Dec 04 Spines produced at IHEP AprilMayJuneJulyAugustSept.Oct.Nov. Outer Middle Inner Total Total% of orderTo make ISTCInc. new order Outer Middle Inner Overall

SCT week: 14th - 16th Dec 04 Spines to be produced at IHEP Dec. 04Jan. 05Feb. 05March 05 Outer Middle7667 Inner Total Inners of extra order required before ISTC finished, therefore IHEP will make extra inners early

SCT week: 14th - 16th Dec 04 Shipments from CERN Fall in Nov due to late delivery of shipment Nov + Dec = 194, all from IHEP November shipment Average per month since July (inc) –Outer : 77 –Middle : 59 –Inner : 42 –Total : 178

SCT week: 14th - 16th Dec 04 Cumulative total So far supply keeping up with demand – Just! –Very tight over Christmas period (CERN closed) –Extra mid-month delivery will ease delivery situation Totals: Outer:876 Middle:535 Inner:408 (note includes INTAS spines)

SCT week: 14th - 16th Dec 04 Yield Yield as observed at production sites (from database) –Outer88% –Middle92% –Inner84% Many causes –Bow is now rare, as is spacer damage in transit Far-end washer size now checked at Geneva –Occasionally Oversized (2.01mm) but appears un-damaged! Worried that quality will be affected at CERN due to extra work load caused by late shipments

SCT week: 14th - 16th Dec 04 Supply Delays in shipping from Moscow a serious problem with schedule Delay of 14 days in last shipment –Some spines delivered by hand but IHEP not keen on this –Adds extra work load on CERN based technician Added extra shipments to ISTC contract to allow 2 shipments per month Attempts being made to convey urgency of shipping problem to ISTC via senior management.

SCT week: 14th - 16th Dec 04 New Order All TPG required has been delivered ISTC contract adjusted to allow extra shipments (another 5 to go) ISTC contract adjusted to purchase extra ceramics Spine assembly contract in process of being signed –Work progresses regardless of slight delay