Field Period Assembly Wayne Reiersen SC Project Review PPPL May 2006.

Slides:



Advertisements
Similar presentations
COIL & ASSEMBLY READINESS REVIEW, SEPT 2013 D. Smekens.
Advertisements

1 MC Assembly via Test Cell Crane FPA Stage 3 Peer Review August 12, 2005 T. Brown.
FDR Station 3 lift fixture, laser screens and brackets T. Brown and L. Morris with analysis support from A. Brooks December 3, 2007.
NCSX Vacuum Vessel Overview Paul Goranson WBS 12 Manager Vacuum Vessel Manufacturing Study Kickoff meeting April 29, 2003.
Update of the ARIES-CS Power Core Configuration and Maintenance Presented by X.R. Wang Contributors: S. Malang, A.R. Raffray and the ARIES Team ARIES.
NCSX NCSX Planar Coil "ASIPP" Presentation 1 December 8-10, 2005 Michael Kalish NCSX TF and PF Coils.
NCSX May 12, 2005 ACC Review- Station 5 J.H. Chrzanowski - 1 ACC Review Of Modular Coil Manufacturing Facility Station No. 5 [VPI] the NCSX Manufacturing.
I&T and Operating and Support Hazards Martin Nordby Chief Mechanical Engineer LSST Camera Safety Review August 18, 2015 R1.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
1 Stage 3 Peer Review October 26, 2006 T. Brown. 2 Field Period Assembly (FPA) 1.Make sure the requirements for the tooling is well defined (including.
NCSX Vacuum Vessel Joint Design Mike Viola PPPL July 1 st, 2003.
1 Dimensional Control for the National Compact Stellarator Experiment R. Ellis, A. Brooks, T. Brown, W. Reiersen, S. Raftopoulos, B. Stratton Presented.
1 NCSX Modular coil winding pack To shim or not to shim? NCSX WBS 1 Engineering Meeting July 7, 2004 What is requirement? What is baseline winding pack.
1 Stage 3 Peer Review October 26, 2006 T. Brown. 2 Field Period Assembly (FPA) – Stage 3 1.Make sure the requirements for the tooling is well defined.
1 BROOKHAVEN SCIENCE ASSOCIATES Abstract Magnet and Girder Integration Lewis Doom, NSLS-II Project National Synchrotron Light Source II (NSLS-II) will.
10/31/2007Mike Viola1 NCSX Field Period Assembly + + = October 31, 2007 Mike Viola Field Period Assembly Manager.
Modular Coil Assembly Bolted Joint PDR 2/22/07. Objectives The review objectives include... Define the location of additional inboard bolts Finalize the.
NCSX NCSX Design Review Guide May 27, 2005 Wayne Reiersen NCSX.
12/2/04Module 2D1 The NCSX Engineering Web – An Overview Part IV Engineering Management & Systems Engineering and Other.
NCSX A. Brooks, P. Fogarty, G. Lovett, D. Williamson June 3, 2005 Modular Coil Type-C Final Design Review – Part II.
10/31/2007Mike Viola1 NCSX Field Period Assembly + + = October 31, 2007 Mike Viola Field Period Assembly Manager.
NCSX VACUUM VESSEL PL Goranson Thermal Insulation Final Design Review July 31, 2006 WBS12 NCSX.
Metrology Milestones Metrology Task Force –Vacuum vessel manufacture - P. Goranson –Mod. Coil Form manufacture - D. Williamson –Mod. Coil winding- S. Raftopoulos.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62)
1 MC Assembly over the VV FPA Station 3 FDR Review July 17, 2007 T. Brown.
NCSX NCSX TF Coil Procurement 1 February 3, 2006 Michael Kalish NCSX TF Coil Procurement.
Conceptual Design Requirements for FIRE John A. Schmidt FIRE PVR March 31, 2004.
10/31/2007Mike Viola1 NCSX Field Period Assembly + + = October 31, 2007 Mike Viola Field Period Assembly Manager.
NCSX Systems Engineering Management Plan Peer Review Bob Simmons May 15, 2003.
ITER- TBM Planning and Costing Activity DCLL TBM Mechanical Design ( ) & TBM-Port Interface ( ) Presented by Mo Dagher December
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
NSTX Response to the Lessons Learned Report NSTX TF Coil Repair Review September 3-4, 2003 Al von Halle.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
NCSX Field Period Assembly (FPA) Operations, Cost and Schedule, Staffing, and Metrology Utilization Mike Viola Field Period Assembly Manager NCSX FPA Peer.
11/2/2005Mike Viola1 November Lehman Review November 2, 2005 NCSX VVSA NCSX Vacuum Vessel Fabrication Major Tool and Machine – S F 3 120° segments.
F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 PF, TF, & Trim Coil Supports (WBS-15) Core Base Support Structure (WBS-17) F. Dahlgren NCSX Coil.
1 NCSX WBS HANDLING/SUPPORT UPDATE PLG 7/23/03 STATUS Study is for 120 degree VVSA field period assembly. Vessel Installation Support Concept.
NCSX Field Period Assembly (FPA) Operations, Cost and schedule, staffing, and metrology utilization Mike Viola Field Period Assembly Manager NCSX FPA Peer.
1 Field Period Assembly Office of Science Project Review Princeton Plasma Physics Laboratory Princeton, NJ November 2, 2005 T. Brown Princeton Plasma Physics.
1 MC Assembly over the VV FPA Station 3 FDR Review July 13, 2007 T. Brown.
NCSX NCSX Project Meeting Wayne Reiersen 15 December 2004.
10/31/2007Mike Viola1 NCSX Field Period Assembly + + = October 31, 2007 Mike Viola Field Period Assembly Manager.
SC Project Review of NCSX, April 8-10, 2008 NCSX Field Period Assembly Mike Viola NCSX Field Period Assembly Manager NCSX Project Review April 8-10, 2008.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62) Manager.
SC Project Review of NCSX, April 8-10, 2008 NCSX Machine Assembly E. D. Perry.
1 Stellarator Core Metrology issues NCSX WBS-1 Meeting April 2, 2003 What are we measuring? When? How do we take the measurements? How do we correlate.
1 Assembly Tooling PU Workshop on NCSX Cost & Schedule Princeton Plasma Physics Laboratory Princeton, NJ Mar 1-4, 2007 T. Brown Princeton Plasma Physics.
AWB Dimensional Control Requirements for the Modular Coils and TF coils Field Period Assembly Peer Review October 11-12, 2006 Art Brooks.
NCSX VACUUM VESSEL PL Goranson Final Design Review November 17, 2005 Man Access Port /Lateral Supports NCSX.
1 FPA Stage 2 Peer Review May 12, 2006 T. Brown. 2 FPA Stage 2 Status Summary of Stage 2 activities Review current design status Review schedule details.
NCSX 21 March 2003 Reiersen - 1 PDR Preparations Wayne Reiersen NCSX Engineering Meeting 21 March 2003.
1 Modular Coil Assembly Fixture (MCAF) Information Meeting February 23, 2005.
DRAFT Cost and schedule, staffing, metrology utilization 10 AM October 12, 2006 Mike Viola Field Period Assembly Manager.
9/28/20051 Mike Viola 1, T. Brown 1, P. Heitzenroeder 1, F. Malinowski 1, W. Reiersen 1, L. Sutton 1, P. Goranson 2, B. Nelson 2, M. Cole 2, M. Manuel.
10/31/2007Mike Viola1 NCSX Field Period Assembly + + = October 31, 2007 Mike Viola Field Period Assembly Manager.
Engineering Operations Outage Status: New shielding of HHFW/in-vessel components has been completed. Fit-ups of OH bus lead upgrades to reduce error fields.
Preparations for working on Station 1 November 22, 2005.
SEPT 20, 2006 T. Brown, M. Cole, P. Fogarty, P. Goranson, K. Freudenberg, D. Williamson NCSX STAGE 2 COIL TO COIL ASSY.
8/15/2007Mike Viola1 NCSX Field Period Assembly + + = August 15, 2007 Mike Viola Field Period Assembly Manager.
12/19/2006Mike Viola1 December Lehman Review December 19, 2006 Mike Viola Field Period Assembly Manager NCSX Field Period Assembly + + =
NCSX VVSA / MCWF FDR A Systems Engineering Perspective Wayne Reiersen Bob Simmons NCSX VVSA / MCWF FDR May 19-20, 2004 PPPL.
1 FPA Stage 2 MC Flange Assembly Issues and Design Proposals June 20, 2006 T. Brown.
Stellarator Core Machine Configuration NCSX Project Meeting Dec 19-20, 2000 B. Nelson, M. Cole, P. Fogarty P. Goranson, G. Jones, D. Williamson O AK R.
1 WBS 1 Preparation for FDRs NCSX WBS 1 Engineering Meeting March 17, 2003 What establishes the plan? What are near term deliverables? How will we status.
1 VV Support Fixture FPA Stage 1 PDR Review August 10, 2005 T. Brown.
1 NCSX VV Assembly Joint Issue B. Nelson 17 Mar 2005.
1 NCSX Construction Overview NCSX Team (presented by L. Dudek) March, 2008.
SC Project Review of NCSX, April 8-10, 2008 C. A. Gentile NCSX Startup (WBS 85) C.A.Gentile NCSX CD-4 Startup.
NCSX Vacuum Vessel Fabrication
CDS-EL IRR Closeout 28 March 2019 J.G. Weisend II, Chairman.
Presentation transcript:

Field Period Assembly Wayne Reiersen SC Project Review PPPL May 2006

Reiersen / 2 Preparations for FPA have been going well FPA processes have been defined in the MIT/QA Plan Magnetic alignment of coils into field periods has been adopted Facility-level planning and safety documentation is in place –Manufacturing Facility Operations Plan updated to include FPA activities –Project Hazard Analysis approved by the PPPL Safety Review Committee The firs VVSA has arrived We are ready for the ACC review of Station 1 –MIT/QA Plan is being signed –Receipt inspection and assembly procedures written –Turning fixtures fabricated Preparations for subsequent stations are on track

Reiersen / 3 Field period assembly process

Reiersen / 4 Turning fixtures fabricated for Station 1 Two turning fixtures fabricated to allow parallel operations Provide easy access for installation of components A ratchet locking system has been added to enhance safety

Reiersen / 5 Assembly procedure written for Station 1 Magnetic loops (65-80 flux loops, 4 toroidal loops), coolant lines (64), heater tapes, and thermocouples will be installed

Reiersen / 6 Modular coils assembled into 3-packs in Station 2a The coils will be positioned based on inspection data using three adjustable spherical seats Custom shims will be placed between the flanges Coils will be secured with insulated bolts Adjustable support stand Type-C assembly being lowered in place Completed half-period assembly

Reiersen / 7 6-pack completed using magnetic alignment in Station 2b Second support fixture allows assembly of the mating half- period using magnetic alignment Magnetic alignment involves nulling symmetric differences in mutual inductances Requires an array of pick-up coils symmetrically placed about the symmetry plane Reduces the risk of unacceptable field errors relative to using physical measurements alone 6-pack disassembled into two 3- packs for installation over the VV Fiberglass tube with 20 wire loops on each side of the parting plane. Symmetric alignment of Type A coils

Reiersen / 8 Modular coils installed over VV in Station 3 The use of the overhead crane for rotating the modular coils over the VV described at previous SC review After installation with overhead crane, modular coils are supported by a rolling ground support system The interfacing Type-A flanges are then shimmed and bolted together into a full field period and VV support hardware installed

Reiersen / 9 TF coils are assembled into 3-packs in Station 4 TF coils wedged together in an accurately machined fixture TF coils retracted slightly in the radial direction (~1/4 in) to provide clearance during the final machine assembly Temporary structures are needed for upper and lower structure for TF half-period assembly and final field period assembly

Reiersen / 10 Final field period assembly in Station 5 Two stations planned for final field period assembly provide schedule robustness Assembly sequence –Weld ports on MC/VVSA subassembly –Rotate TF coil half-period assemblies into position –Install external trim coils –Install temporary blocking around vacuum vessel to inhibit movement during transport Completed field periods transported to the NCSX Test Cell at C-site for final assembly Ports welded on TF coils rotated into position Completed field period

Reiersen / 11 Station 1 is ready for the ACC review The MIT/QA Plan is out for signature - it provides… –A description of the FPA sequence including a process outline –A description of each station including tooling and fixtures –A listing of specifications (which identify applicable drawings and models, define requirements, and verifications) for each station –A listing of procedures and documentation requirements for each station The procedure for material receipt and verification is approved The assembly procedure for installing the magnetic diagnostics, coolant tubes, heater tapes, and thermocouples has been drafted Installation of the flux loops has been prototyped on the PVVS Hoisting and rigging will be performed per PPPL’s Hoisting and Rigging Program (ENG-021) Two turning fixtures have been fabricated The first VVSA has arrived

Reiersen / 12 Preparations for other stations are on track Tooling is being designed for Stations 2 and 3 –Models have been completed for tooling required on Stations 2 and 3 –A magnetic alignment system is being designed for assembling modular coils into 6-packs –The design of the coil-to-coil interface hardware (a WBS 14 activity) is also planned for this FY Detailed design of tooling for Stations 4 and 5 will begin after design activities on Stations 2 and 3 are completed

Reiersen / 13 Next steps ACC will review readiness of Station 1 for operation and provide a report which addresses the charge questions –Have the facility hazards for the work on Station 1 been appropriately identified, e.g. in the Manufacturing Facility PHA? –Have appropriate safety controls, e.g. those identified in the identified in the Manufacturing Facility Operations Plan, been implemented for the work on Station 1? –Has personnel safety been adequately addressed in the design of the turning fixture? –Has adequate training been provided (or planned to be provided in a timely manner) for the work to be conducted safely? NCSX will respond to any issues raised by ACC When issues have been resolved to the satisfaction of the Project Manager (Neilson) and RLM (Dudek), the RLM will provide authorization to the ATI (Viola) to commence operations on Station 1