Pevatron status Sunday 29 th November 2015 Coordination: John Jowett, Mike Lamont, Jan Uythoven Access Loss maps Physics.

Slides:



Advertisements
Similar presentations
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
LHC progress week 19 Monday 11 th May 2015 Coordination: Jan Uythoven, Massimo Giavannozzi, Mike Lamont.
Monday 4 th to Friday 8 th Technical stop  Coordination: Katy Foraz  Machine back to Operations Friday evening on schedule Major cryogenics intervention.
Wednesday 12 th September Pumping, removal of vacuum equipment from tunnel in the morning TOTEM & ALFA, RP movement tests: OK 11:50 pre-cycle started,
MD#2 News & Plan Tue – Wed (19. – 20.6.) DayTimeMDEiCMP Tue06: GeV  4 TeV: Ramp for chromaticity - missed A 08:00Ramp down 10: GeV: Large.
Friday 23 rd November - morning Coming out of loss maps over night Thu – Fri  in shadow of MKD problem in SPS (and CMS cryo recovery) 07:35 Start pre-cycle.
21/05/2012LHC 8:30 meeting Overview Week 20 Injectors, LHCb polarity, Beam-Beam Coordinators: Bernhard Holzer, Jan Uythoven.
LHC – week 48 finishing up the ioning Coordination: Gianluigi Arduini & Mike Lamont.
5/11/2012LHC 8:30 meeting Summary of Week 44 Coordination: Mike Lamont & Jan Uythoven.
Weekly summary Summary Week /19.07 M. Lamont & J. Wenninger for the OP team and for all colleagues from the various groups 8:30 meeting 1.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
17/09/2012LHC 8:30 meeting LHC Summary Week 37 Coordination: Jorg Wenninger & Jan Uythoven.
07-JUL-2003LEADE / JW1 Satellite bunches in the LHC Satellite “definition” Satellite luminosity Satellite detection & tolerances J. Wenninger AB/OP.
CONTENT: Beam characteristics and parameters Filling schemes Operational settings OP procedure and COLL setting Planning Shift breakdown To define the.
Plan for start-up with beam Friday  19:00 Machine closed. Ramp for powering tests & pre-cycle  22:00 Pilots through nominal cycle up to collisions. Measure.
ION COMMISSIONING REVISITED 1 Thanks to: John Jowett, Walter Venturini. Matteo Solfaroli.
Saturday 25/11/10 & Night 12:24 Dump fill #1523 after more than 8 hours in physics It takes some time to get back:  Parallel sequences: Fewer clicks to.
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
LHC progress Report LHCC Wednesday 23 rd March 2011.
Tuesday 17 th April 04:00 Prepare second fill for v/d Meer scans. 06:22 Stable beams, v/d Meer scans for Alice and LHCb. 13:20 End v/d Meer scans.Dump.
LHC 8:30 meetingEBH 11 Thursday 24 November 2011.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
00:15: Stable beams fill 1883, 1.1E33 cm-2s-1.  Seems the 144 bunches beam 1 doe not fit properly on the injection kicker waveform. Systematically the.
Wednesday ● 02h04: Stable beams # b x 121b. – Peak luminosity 1.2e25 cm-2 s-1 ● 08h32: Beams dumped on request. – Length=6h28. Rampdown.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
Friday 2 nd November 08:45 Stable beams Fill 3253 Initial luminosity ~7.3e33 cm-2s-1 09:45 Increase RF voltage from 10 MV to 12 MV 12:00 ADT to wideband.
09:25 Operator dump fill #2178, integrated lumi 107/108/18 nb-1. Trip of RQ4.R6 (fire heaters discharged) just after the beam dump but the QPS gave no.
Goal of the week: Stable beams with trains of 200 & 248 bunches 1 OP summary of week 40 R. Bailey, J. Uythoven & J. Wenninger.
:00 meetingEBH 11 Saturday :00 meetingEBH 2  7:58 Fill 2483 (264 bunches) dumped by reference orbit set to zero in.
– Machine closed. Ramp for powering tests & pre-cycle – Pilots through nominal cycle up to collisions. Measure chroma during squeeze. Check dump of pilots.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
Injection status W. Bartmann, C. Bracco, B. Goddard, V. Kain, A. Macpherson, M. Meddahi, S. Redaelli, J. Uythoven, J. Wenninger LIBD Meeting, 20 th Sept.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Lumi scan limits checked (in preparation for next fill VdM scans).  Trims of up to 150 um per beam in IP1 & IP2 both planes both beams were done (IP5.
28/01/2013LHC 8:30 meeting Summary of Week 4 pPb physics Machine Coordination: Mike Lamont & Jan Uythoven Ion coordination: John Jowett.
LHC Status Sat Morning 30-June Bernhard Holzer, Jan Uythoven Status Friday Late: preparing restart some issues... LHCb dipole tripped / router problem.
Wednesday 8.9 External crossing angles:
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
Friday 07:00 Power glitch on the EDF network. Point 8 affected.
LHC summary week 32 Coordination: Mike Lamont & Jan Uythoven
Coordination: G. Arduini, E.B. Holzer, J. Jowett
Overview LHC Operation Week 47
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
Fill 1410 revisited Peak luminosity 1.4e32 Beam current 2.68/2.65 e13
Wednesday /Thursday 09-11:00 Verification of the LSS6 interlocked BPMs: took longer to fill due to some problems with RF cavities in the PS. In the mean.
LHC Morning Meeting - G. Arduini
Tuesday 23/11/10 8:00 Physics fill #1511 dumped
Summary of week 44 Aims of week 44 J. Wenninger & J. Uythoven
Sunday morning Recovering from 400 kV disturbance.
Tuesday 9th November 10:02 Fill beams dumped
Yesterday morning Held 1647 for a while – SPS kicker problem
Summary Thursday h21: Stable beams fill #1303.
Summary of week 19 Machine Coordinators: G. Arduini, M. Lamont Main aim: Luminosity production.
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
Saturday Nov Stop proton operation. Switch back to ions
Wednesday 13th 9:30 Stable Beams… with 1 pilot and 2 nominals
Saturday :42 stable beams fill 3541
Monday :15 fill 3523 dumped by BPMs IP6
Wednesday 23/2 Thanks CRYO!!!.
Fri :52 Stable beams fill #2536
Another Immortal Fill….
Wednesday morning Waiting for PS – problem on RF cavity.
Thursday 2.12 Cryo recovery…. Access… RF cavity check (noise) Cav4B1.
Daniel, Gianluca and Belen (for the Collimator team)
HI2011 Commissioning Status
Saturday 29th October Friday during IP2 1 m squeeze test
Presentation transcript:

Pevatron status Sunday 29 th November 2015 Coordination: John Jowett, Mike Lamont, Jan Uythoven Access Loss maps Physics

Recall DateFillSBNbPeak e27 ub-1 ATLAS Dump Thu 26th4660Ramp250Losses TCTPH.4L2B1 changing crossing angles (ADT) Thu 26th46612h OP dump Thu 26th46644h OP dump Fri 27th GeVAccess point 6 Fri 27th46665h OP dump Fri 27th4668Flat-top426Instability B1V Fri 27th46696h OP dump Sat 28th4670Flat top426Losses in 7 – BPM/OFB Sat 28th46719h OP dump Sun 29th46726h OP dump Sun 29th In prep

Saturday 28 th November 07:00 Ramp # :22 Dump at flat top on losses B1 near TCP – BPM/OFB… 09:45 Injecting 12:15 Stable beams #4671 – 426 bunches – Had to hold onto this one for a long time – SPS RF problem (200 MHz cavity controller ) 21:15 #4671 – OP dump

Sunday 29 th November 00:55 Stable beams # :50 #4672 – OP dump Will now try 518 bunches with 150 ns spacing in SPS – 100_150ns_518Pb_516Pb_492_444_24_22inj

4670 – dump to losses on FT BPMWC.6L7.B1 developed a negative offset of ~-1 mm and the OFB tried to steer it back – (the date in the image header is the time when it happened, data difference with respect to 1st orbit at FT). – In the end of BPM even flipped into the other direction toward +1mm (last image) just before the dump happened. Note that the counter bump that was put it was still quite modest, only ~ mm (max). We seem to be incredible sensitive with the ions. I have disabled that BPM for the moment. Jorg Wenninger

Wire scanner 450 GeV

Lies, lawyers, and luminosity Nc = 400 for ATLAS and CMS Nc = 362 for ALICE ? ?

150 ns After the tests this morning we are confident that the 150 ns MKP rise time is now robust in the SPS, thanks to the great efforts of Francesco, Etienne and Gerd. The attachment shows the bunch emittances measured with 150 ns gap, which look basically similar to those for 225 ns (it would be good to check in LHC). The damper is working well on all bunches. Brennan Goddard

ALICE backgrounds

Something’s wobbling around

Longitudinal profiles from BSRA Thanks to Marcus Palm who made available the application from CCM. Nice beams: 0.58% (0.42%) of satellites for B1 (B2) (bunches around +/- 5 RF buckets of the main bunch) 2.63% (1.75%) of ghost charges (bunches elsewhere besides the main bunch and the satellites definition)

The Ion Plan Anticipating next week: – Monday: Physics – Tuesday: Ion source refill – Wednesday: Crystal collimation MD – Thursday: V/d Meer – Friday: ALICE polarity change Plus TCT set-up and loss maps 1328/11/2015LHC Morning meeting – JU, ML & JJ