MKI failure event 17-April-11 Recall from logbook: MKI D (1st one seen by the beam) had a real flashover between the two sets of 36b during the 3rd 72b.

Slides:



Advertisements
Similar presentations
LHC Beam Operation CommitteeJune, 14 th UFOs in the LHC Tobias Baer LBOC June, 14 th 2011 Acknowledgements: N. Garrel, B. Goddard, E.B. Holzer, S.
Advertisements

Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
LHC progress Saturday 2 nd May 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Shielding studies at TDIs Results from Rob Appleby – Studies made for P8 (LHCb) – Aimed to look at what shielding can improve Local LHC BLMs LHCb RICH.
UFO Study Working GroupAugust 12 th Update on UFO Studies Tobias Baer August, 12 th 2011 Acknowledgements: G. Arduini, W. Bartmann, M. Barnes, C.
● Morning: – Squeeze and collide. – Smooth, orbit rather well under control (max. excursion ~ 0.2 mm at TCT, roughly sigma). Orbit evolution at the.
Injection and Extraction Losses W. Bartmann with many inputs from: R. Appleby, R. Assmann, P. Baudrenghien, V. Boccone, C. Bracco, B. Dehning, E. Gianfelice,
Sunday :00 injection 336 bunches, ramp, squeeze luminosity. 03:19 Stable beams #1718. Duration: 9h08.  Peak lumi ATLAS/CMS: 3.8/3.6e32.  Int.
LHC 30 th and 31 st July :10 Finish scrubbing fill 25 ns trains by operator dump. –No XPOC data … 08:40 Inject for another scrubbing fill 09:09.
New ALICE Beam Pipe: Injection Protection C. Bracco on Behalf of ABT/BTP Acknowledgment: M. Giovannozzi.
LER Workshop, CERN, October 11-12, 2006Detector Safety with LER - Henryk Piekarz1 LHC Accelerator Research Program bnl-fnal-lbnl-slac Accelerator & Detector.
:00: Prepared new fill B1: Q X =0.293, Q Y =0.269; lifetime = 25h ✔ B2: Q X =0.297, Q Y =0.267; lifetime = 5h ✗ Strong 50Hz and 100hz lines.
LHC 8:30 meetingEBH 1  Cryogenics recovery in point 8  Meanwhile a couple of accesses:  MKI investigation on noise in IP2  Insulation Vacuum.
Managed by UT-Battelle for the Department of Energy Analysis of 2008 Beam Instability Data S. Cousineau, V. Danilov, M. Plum HB2008.
Simulation of Beam-Beam Background at CLIC André Sailer (CERN-PH-LCD, HU Berlin) LCWS2010: BDS+MDI Joint Session 29 March, 2010, Beijing 1.
Tuesday 17 th April 04:00 Prepare second fill for v/d Meer scans. 06:22 Stable beams, v/d Meer scans for Alice and LHCb. 13:20 End v/d Meer scans.Dump.
BPMs period General BPM Tasks/Projects New single bunch BPM electronics on ALICE AR1 + ST2 They had been tested already last year by Alex and Ian.
Simulations of TCT beam impacts for different scenarios R. Bruce, E. Quaranta, S. RedaelliAcknowledgement: L. Lari, C. Bracco, B. Goddard.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
00:15: Stable beams fill 1883, 1.1E33 cm-2s-1.  Seems the 144 bunches beam 1 doe not fit properly on the injection kicker waveform. Systematically the.
Monday h34: beam (1020b) lost after 10 Hz RF trim. Fill h56: XPOC to be reset by expert. 08h18: Masked QPS_STATE SIS interlocks for RB.A12.
LHC Progress Thursday 29 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
BLM update procedure: - Updated the RT software - Updated the BLETC firmware (ver _A) - Changed the firware version in the MASTER tables and generated.
Goal of the week: Stable beams with trains of 200 & 248 bunches 1 OP summary of week 40 R. Bailey, J. Uythoven & J. Wenninger.
Tuesday 24 th July - morning 10:15 Operator dump of fill 2873  Initial luminosity: 5.83e33 cm-2s-1  12 hours stable beams  151 pb-1 delivered  Initial.
Injection and protection W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, A.Nord, J.Uythoven, J.Wenninger, OP, BI, CO, ABP, collimation,
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
Injection status W. Bartmann, C. Bracco, B. Goddard, V. Kain, A. Macpherson, M. Meddahi, S. Redaelli, J. Uythoven, J. Wenninger LIBD Meeting, 20 th Sept.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Production running 1 pb-1Lost to Mon h2062e32EOF studies Tue h17.152e32UFO Q8.L5 Tue h e32OP request Thu h e32OP.
04h36: Cryo problem in arc 81. Access. 09h14: Injection.  TI8 injection collimator setup.  Testing new sequence.  New version of vacuum application.
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
MTE commissioning status S. Gilardoni, BE/ABP With C. Hernalsteens and M. Giovannozzi.
MPP Workshop: Injection System C. Bracco on behalf of ABT Acknowledgments: STI, ABP, BI,LHC and SPS OP.
Aperture measurements during LHC commissioning 2017
Wednesday
1st LHC MD Period Started
Cryo Problem MD Planning Tue (1.11.) C B Day Time MD MP Tue 01:00
SPS extraction, transfer lines, injection
-9:00: Test IP transverse adjustment (CMS) and optics verification.
MD2036: UFO dynamics studies and UFO fast detection
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Monday :00 Stable beams 9_6_6_6 13:40 Access.
Tuesday Nov 16th Fill 1492 into physics around 07.30
Monday fill with 1092 bunches (6 h stable beams)
Thursday morning – optics correction
Summary of Week 11: 14 – 21 March
LHC Status Su Morning 17-April R. Assmann, B. Holzer et al
Monday – recovery from MKI flashover
Tuesday Fill 1494 dumped by operations at (~ 0.25 ub-1 in ~6.5 h): LSS6 BPM interlock test 13:00 Fill 1495 dumped by RF dump (cavity quench) 14:00-17:30.
LHC commissioning Week 38
LHC Injection and Dump Protection
Summary of Week 16 G. Arduini, J. Wenninger
Friday Morning 3:44 – 15:04 stable beams Fill (dumped by operator)
Tuesday 20 March 2012.
Saturday – Morning 7:36 beams dumped
Saturday 7th May Sat – Sun night
Monday 24 October hours of 25ns MD
Scrubbing progress - 08/12/2012
Monday 8th December Morning used for RF work (IP z, injection), damper noise checks. Stable beams period with LHCb spectrometer OFF – lost beam after.
Monday Fill 1803 into stable beams at 9:30. Dump at 19:45.
Thursday - setup 10:00 Starting pre-cycle. 11:30 Injection.
Friday h55 Stable beams. Fill #1841. Lumi ~1.2e33.
Tuesday 24/5 Fill # :00 Stable beam fill # bunches
Wednesday 26 October 2011.
Wednesday 6.10 Morning: Quench test at 450 GeV
Tuesday
Thursday 10:00 Fill 1986 in stable beams.
Presentation transcript:

MKI failure event 17-April-11 Recall from logbook: MKI D (1st one seen by the beam) had a real flashover between the two sets of 36b during the 3rd 72b injection 2 nd 36 b of the 72b train hitting the TDI with between 75 and maybe 90% of the nominal MKI deflection Dumped ~ 88% of expected beam – nearly all p+ of these 36 b impacted TDI/TCLIB Big injection oscillations of 5 mm for 2 nd 36 b Degraded kicker vacuum already before problem. 20/05/2011W. Bartmann, MKI failure event 17-April-111

20/05/2011W. Bartmann, MKI failure event 17-April-112 Loss pattern compared to optics B2 injection Losses in [Gy/s] Optics functions [m]

Loss pattern compared to optics 20/05/ W. Bartmann, MKI failure event 17-April-11 B2 injection Loss peaks in arc Losses in [Gy/s] Optics functions [m]

TDI grazing tests 8-March-11, B2: MKI scan 7 sig oscillation LHCb triggered even with sunglasses /05/2011W. Bartmann, MKI failure event 17-April-114 Loss peaks in arc ~ 5 mm vertical oscillation

MKI failure vs. TDI grazing test losses 20/05/2011W. Bartmann, MKI failure event 17-April-115 Losses in [Gy/s] Scaled by Intensity (36b nominal/1b probe)

MKI failure with 288 bunches? 20/05/2011W. Bartmann, MKI failure event 17-April-116 To be expected: All ‘peak’ BLMs far in saturation Far-ranging and extensive quenches Damage???

Summary Loss pattern agrees with positions of high horizontal dispersion – Probably by scattering from V-osci into H-osci – If momentum lost should be even enhanced Comparing failure losses with TDI grazing tests – Loss pattern exactly the same – Scaling factor 800 (36 nominal over 1 pilot) shows high agreement also for the loss levels These tests can very likely be used to predict – loss levels for higher intensities (288 b grazing) and – Worst case in terms of grazing angle Scaling for MKI failure with 288 bunches – ‘Peak’ BLMs in arc by far saturated – Extensive quenches to be expected – Damage?? To be checked 20/05/2011W. Bartmann, MKI failure event 17-April-117