Machine Status Proton Source Commissioning and Studies 8/13-8/14: Linac & Booster Maintenance Period Main Injector MI30 vacuum ○ Work continues to resolve the high gas load at MI308 MI back-fed from Master Sub-Station ○ KRS T85 work complete, but still using Feeder 45 for MI conventional Need to schedule a 20 minute MI conventional power outage to remove the back-feed from Master Sub-Station after tunnel work. SY120 Neutrino Muon ○ G2 NM1 berm pipe progressing Mtest ○ MC6 magnet replacement
MI 307 to 309
Section 3 Stable Holding vacuum No further work
Section 2 Contamination Bellows Pirani Gauge Samples sent for testing Section 2 removed Cleaning elements and building a new section in parallel Leak check and reinstall
Section 1 RGA Scan completed Friday Did not reveal anything conclusive Additional baseline scans this morning Downstream end put under vacuum (not including collimator) Heated bellows for 30 seconds Ion pump tripped off. Section 1 contaminated Collimator beam pipe will be cleaned in place Remainder of section replaced.
Neutrino Muon M. Geelhoed 8/16/2013 G2 NM1 Berm Pipe Progress Status – Welding third set of pipes in enclosure
August 2013 DRAFT
Shutdown 2012 Schedules and Links: Schedule can be accessed from the Operations Home Page - Schedules -> Operations ScheduleOperations Schedule Direct link to schedule -