September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning.

Slides:



Advertisements
Similar presentations
Houston Region Import Capacity Project Planning for Reliable Power.
Advertisements

RPG: September 24, Approach for ERCOT Independent Review of the 2013 Houston Import Project Jeff Billo, Manager, Transmission Planning September.
October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
March 6, 2008 Technical Advisory Committee Luminant Energy & Oncor Tyler Grande Autotransformer Addition and 138 kV Line Upgrade Project Jay Teixeira Manager,
Company LOGO Cleco Planning Process. Models Cleco uses SPP’s annual series of models to determine the NERC reliability violations. Cleco uses SPP or VST.
Regional Planning Group Project
ERCOT Planning Overview and Summer 2014 Assessments Update
Overview of ERCOT Outage Coordination Woody Rickerson Director Grid Coordination January 2015.
Houston Import Evaluation Cross Texas Transmission & Garland Power & Light ERCOT RPG Meeting August 27th, 2013.
KURTEN SWITCH PROJECT (BRYAN/ COLLEGE STATION AREA UPGRADES) Technical Advisory Committee December 1, 2005 Transmission Services.
Houston Region Import Capacity Project August 27, 2013 Regional Planning Group Meeting.
Nov 11, 2011 RPG Meeting Cross Valley Brownsville Loop Project – Status report.
Outage Coordination Overview D.W. Rickerson ERCOT Outage Supervisor 12/1/2008.
January 5, 2012 TAC Cross Valley 345 kV Project Jeff Billo Manager, Mid-Term Planning.
Valley Import Overview Jeff Billo Regional Planning Group Meeting July 22, 2014 Preliminary1.
RiversidePublicUtilities.com Arts & Innovation RiversidePublicUtilities.com Challenges and Solutions for Large-Scale PV Integration on RPU’s Distribution.
Jan 13, 2012 RPG Meeting El Campo – Vanderbilt 69 kV Project – Status report Ehsan Ur Rehman Planning Engineer ERCOT.
Houston Area Dynamic Reactive Project March 11,
Report on the NCTPC 2006 Collaborative Transmission Plan Mark Byrd, Manager – Transmission Planning Progress Energy Carolinas, Inc January 25, 2007.
JACKSBORO TO WEST DENTON 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
10/03/ Report on Existing and Potential Electric System Constraints and Needs Within the ERCOT Region October 3, 2002.
Lyndonville Electric Department Feasibility Analysis Review December 2,
Oct 14, 2011 RPG Meeting Cross Valley Brownsville Loop Project – Status report.
April 16, 2010 RPG Meeting ERCOT Five-Year Transmission Plan Update Jeff Billo.
Aug 17, 2012 RPG Meeting KEC & MEC – Load Addition Project – ERCOT Independent Review Ehsan Ur Rehman Planning Engineer ERCOT.
RPG Meeting Five Year Plan Extension Brad Schwarz.
Texas Wind Energy American Meteorological Society Summer Community Meeting – Norman Oklahoma Henry Durrwachter, P.E. August 12, 2009.
LAREDO PLANT RMR EXIT STRATEGY Presentation to Board of Directors March 16, 2004 Transmission Services Operations.
March 11, 2011 RPG Meeting Lower Rio Grande Valley (LRGV) Import.
June 19, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
Kurten Switch Project ERCOT Board of Directors Bill Bojorquez System Planning December 13, 2005.
October 16, 2009 RPG Meeting ERCOT 2009 Five-Year Transmission Plan Update Jeff Billo.
POWER SYSTEM PLANNING CHARTER AND PROCESSES UPDATES Presentation to TAC Sept 9, 2004 Transmission Services Ken Donohoo, Manager of System Planning
Jones Creek Project Submitted to RPG on July 7, 2014 July 22, 2014 Regional Planning Group Meeting.
Dale Osborn Midwest ISO October 13, 2008 EE 590 Transmission Planning with Significant Energy Resources.
WEST LEVEE TO NORWOOD 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
April 16, 2010 RPG Meeting Lamesa Area Upgrades ERCOT Independent Review Jeff Billo.
2008 Annual Five Year Plan Update 2 10/12/2007 Regional Planning: Jay Teixeira, Harry Liu, Brad Schwarz, Jeff Billo, Chris Ngai.
LAREDO RMR EXIT STRATEGY Presentation to Technical Advisory Committee March 4, 2004 Transmission Services Operations.
JACKSBORO TO WEST DENTON and WEST LEVEE TO NORWOOD 345-kV PROJECTS April 20, 2004 Transmission Services Operations.
Jeff Billo Manager, ERCOT Transmission Planning Kenedy to Nixon to Seguin Line Upgrade Project Regional Planning Group (RPG) Review; ERCOT Independent.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX.
TAC02/01/2007 DW 1 TAC Briefing on: - Report on Constraints and Needs: Five Year Plan Development - Long Term System Assessment (LTSA) - Entergy Integration.
AEPSC Live Oak County Transmission Project – ERCOT Independent Review TAC September 24, 2015.
ERCOT TAC11/2/ CREZ Study Update ERCOT TAC 11/2/2006.
February 13, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
ERCOT Independent Review
October 16, 2009 RPG Meeting ERCOT Independent Review of the Corpus Christi Improvements Project Jeff Billo.
LCRA TSC/ CPS Energy Transmission System Addition Regional Planning Group Project Jeff Billo Sr. Manager, Transmission Planning TAC ERCOT Public March.
RPG: September 24, Long-Term System Assessment Introduction Jeff Billo, Manager, Transmission Planning September 2013 Regional Planning Group.
Jeff Billo Manager, Transmission Planning
OPSTF – Issue 7 Long-term unavailability of autotransformers.
Update on the North Carolina Transmission Planning Collaborative January 30, 2007 For the North Carolina Utilities Commission and the North Carolina Public.
May14, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
Transmission Services Report: North and West RPG Projects Bill Bojorquez TAC July 7, 2005.
ERCOT PUBLIC 3/25/ RTP Inputs and Assumptions March 25, 2014.
June 11, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
Response to TAC Questions on PGRR031 TAC– January 28, 2014 Jeff Billo, ERCOT 1.
ERCOT Transmission Planning Overview
Houston Import Project – ERCOT Independent Review
Sep 16, 2011 RPG Meeting Cross Valley Brownsville Loop Project – Status report.
Reliability Must Run Workshop RMR Study Process May 24, 2016.
Houston Import Study Update
Freeport Area Master Plan Project -
Modeled Load Levels in the Valley
Nacogdoches to Lufkin SS 345 kV Line Project
Transmission Planning in ERCOT- Overview
Warren Lasher Manager, Long-Term Planning and Policy
Presentation transcript:

September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning

2 TACSeptember 1, 2011 LRGV Import Background The Lower Rio Grande Valley (LRGV) is currently served by: –(2) 345 kV lines, –(3) 138 kV lines, – approximately 1700 MW natural gas generation, and –150 MW DC tie to Mexico On February 3, 2011 the LRGV experienced load levels greatly exceeding the previous planning forecast for 2011, highlighting the need for additional transmission infrastructure to serve the area

3 TACSeptember 1, 2011 RPG Review AEPSC proposed initial project in March, following February event (project had been in planning discussions well before) ERCOT and AEPSC studies showed ERCOT planning criteria would be exceeded in 2016 without system upgrades RPG Comment Period was held during April (and a second comment period was held on the final options in August) RPG participants submitted alternative transmission solutions and ERCOT identified additional alternatives Several commenters discussed the potential for generation solutions; ERCOT does not have the authority to implement generation additions but does have planning criteria obligations AEPSC modified its proposal to enable the project to meet 2016 requirements Status reports on the ERCOT Independent Review were discussed at each monthly RPG meeting

4 TACSeptember 1, 2011 Independent Review Study Approach Evaluated 2016 summer peak SSWG case and 2020 summer peak case from the ERCOT/ DOE long-term study –Modified cases to use latest load forecasts from AEPSC –Removed 250 MW load addition in Brownsville (Brownsville needs are being analyzed in separate RPG review) –Set nearby wind output at 10% of capacity (based on 2010 historical data, 10 th percentile output of coastal wind plants) Performed AC contingency analysis and steady-state voltage stability analysis –With largest unit (combined cycle in LRGV) out of service per ERCOT planning criteria Focused analysis on 2016 reliability; also evaluated 2020 reliability and N-1-1 (maintenance outage) scenarios Nine distinct alternatives were evaluated and narrowed to three final alternatives

5 TACSeptember 1, 2011 Three Project Alternatives for Final Consideration Option 1R: $525 million Lobo-Rio Bravo-N. Edinburg 163 mile single circuit 345 kV line with 50% series compensation Energized reconductor of Lon Hill-N. Edinburg and Lon Hill-Rio Hondo 345 kV lines Reconfigure N. Edinburg and Rio Hondo series capacitors Reconductor Option 5D: $508 million Pawnee-N. Edinburg 200 mile double circuit 345 kV line with 50% series compensation on each circuit Option 6: $659 million Pawnee-Loma Alta 220 mile 1000 MW classic HVDC Loma Alta 345 kV bus with (2) 345/138 kV autotransformers Loma Alta-La Palma 14 mile 345 kV line

6 TACSeptember 1, LRGV Load Serving Capability Results (G-1 + N-1) MW

7 TACSeptember 1, LRGV N-1-1 Load Serving Capability Results MW

8 TACSeptember 1, LRGV Load Serving Capability Results (G-1 + N-1) MW

9 TACSeptember 1, 2011 ERCOT Independent Review Results Option 1ROption 5DOption 6 Project cost in 2016$ 525 million$ 508 million$ 659 million 2016 load serving capability (MW) N-1-1 (Maintenance outages) load serving capability Additional system upgrades needed in 2016 Raymondville-Harlingen Switch 69 kV (18.1 miles) Lon Hill-Smith-Edroy 69 kV (11.6 miles) and Raymondville-Harlingen Switch 69 kV (18.1 miles) Lon Hill-Smith-Edroy- Mathis 69 kV (25.4 miles) and Loma Alta-South Carbide 138 kV (1.1 miles) 2020 load serving capability (MW) Potential Project cost in 2020 (including infrastructure improvements for Laredo and Brownsville) $627 million$600 million$709 million Geographical diversity of the new lineExcellentGood Total new ROW required (2016/2020)~163/~202 miles~200/~244 miles~234/~264 miles Rehabilitation of existing Lon Hill-Rio Hondo and Lon Hill-North Edinburg 345 kV lines YesNo Infrastructure Improvement in the area of new generation interconnection projects GoodNoneFair Projected in-service date (estimation provider) 2016 (AEPSC)2017 (AEPSC)2016 (Sharyland)

10 TACSeptember 1, 2011 Conclusions ERCOT will request the ERCOT BOD endorse the following improvements associated with Option 1R: –Construct a new 163 mile, single circuit 345 kV line from Lobo to Rio Bravo to North Edinburg, utilizing ACSR conductor on double-circuit capable structures, and (2) approximately 24 ohm 3600 amp series capacitors on the Lobo 345 kV circuit (no additional substation equipment would be installed at Rio Bravo at this time but may be added in the future as needed to support the Laredo area needs) –Reconductor the existing Lon Hill-Nelson Sharpe-Ajo-Rio Hondo 345 kV line to 1988/2426 MVA normal/emergency rating to achieve increased rating before peak of 2016 –Reconductor the existing Lon Hill-North Edinburg 345 kV line to 1988/2426 MVA normal/emergency rating to achieve increased rating before peak of 2016 –Reconfiguration of the North Edinburg and Rio Hondo series capacitors such that the MVA rating is at least 2000 MVA and the compensation level is 25% of each respective circuit Estimated Capital Cost = $525M ERCOT will also ask that the BOD deem the project critical to reliability in accordance with PUCT Substantive Rule (b)(3)(D)

Questions? September 1, 2011TAC