FRCC System Restoration 2016 FRCC System Operator Seminar.

Slides:



Advertisements
Similar presentations
“Power Factor” In Transmission System
Advertisements

Summary of Second Draft of the NERC Standard PRC Disturbance Monitoring and Reporting JSIS Meeting August 10, 2010 Salt Lake City, UT.
Beckett Energy Systems
1. Four LLs were published in February Transmission Relaying – Undesired Blocking 2.Lack of Separation for Critical Control Power Supply Leads.
New Energy Horizons Opportunities and Challenges Fault Current Contributions from Wind Plants Dean Miller PacifiCorp July 25,
Submitted by: Name:Rajendra Kumar Choudhury Branch:Electrical Engg.
Distributed Intelligence Provides Self-Healing for the Grid
Lesson 38 Shipboard Power
Goshen Area Bus Reconfiguration
NERC Lessons Learned Summary December NERC lessons learned published in December 2014 Three NERC lessons learned (LL) were published in December.
DOD Microgrids The Missing Link: Microgrid Applications Michael Dempsey P.E. Burns & McDonnell June 12, 2013 © 2013 Burns & McDonnell. All Rights Reserved.
GENERATOR PROTECTION.
Bulk Electric System Power Outages and Restoration Considerations Peter Heiman Western Area Power Administration (Desert Southwest Region) 1.
FREQUENCY CONTROL DURING BLACK START OPERATIONS
1 DISTRIBUTION SERVICE PROVIDER BLACK START TRAINING 2015.
1. 11/26/2012: NERC Board of Trustees adopted CIP v5 CIP thru CIP CIP and CIP Version 5 Filing FERC requested filing by 3/31/2013.
ANCILLARY SERVICES THE NEXT STEP IN MARKET GRANULARISATION.
1 Voltage Collapse Animation (AC) Created by Peter W. Sauer Department of Electrical and Computer Engineering University of Illinois at Urbana-Champaign.
Chapter 8 Inverters AC Power • Inverters • Power Conditioning Units • Inverter Features and Specifications.
Three-Phase ac Voltage Generation
Disconnect Switches There are many purposes for disconnect switches in substations and power lines. They are used to isolate or deenergize equipment for.
System Operator Conference Simulator Drill Orientation 2014 System Operator Conferences Charlotte NC & Franklin TN SERC/SOS Facilitator Team.
PowerPoint ® Presentation Chapter 12 Utility Interconnection Distributed Generation Generators Inverters Interconnection Codes and Standards Interconnection.
Substations. Substations Chapter 4 Substations Major types of equipment found in most transmission and distribution substations with their purpose,
PRESENTATION ON SUBSTATION DESIGN
Chemical, Biological and Environmental Engineering Generating Electricity.
Chapter 7 SYSTEM PROTECTION
Lunch & Learn Project Presents to you: “The Electric Power Grid” By: Dexter Hypolite Electrical Engineer VIWAPA.
Interconnect Protection of Dispersed Generators
THE ELECTRIC SUB STATION
THE TRES AMIGAS SUPERSTATION Southwest Renewable Energy Conference Santa Fe, NMSeptember 16 th 2010 UNITING THE NATION’S ELECTRIC POWER GRID.
Applying the Distribution System in Grid Restoration/NERC CIP-014 Risk Assessment Srijib Mukherjee, Ph.D., P.E. UC Synergetic.
Electrical Installation 2
1 Cheng-Ting Hsu Chao-Shun Chen Islanding Operations for the Distribution Systems with Dispersed Generation Systems Department of Electrical Engineering.
Neptune BU Switching Circuit diagram and operations.
Need for protection Power system must be kept in operation continuously without major breakdowns This can be achieved in two ways: 1.Implement a system.
SIMPLE TRANSMISSION OUTAGE. Nodal Protocol Definition 2.26 Simple Transmission Outage A Planned Outage or Maintenance Outage of any Transmission Element.
Generation assets important to the reliable operation of the Bulk Electric System What does this mean?
Queensland University of Technology CRICOS No J Protection of distributed generation connected networks with coordination of overcurrent relays.
Utility Engineers, PC.  Generation  Transmission  Distribution.
NERC Project S ystem Protection Coordination - PRC-027​ Presentation to the NSRS Conference Call April 20, 2015 Sam Francis Oncor Electric Delivery.
Steady State Analysis Of A Microgrid Connected To A Power System
NERC Lessons Learned Summary LLs Published in September 2015.
A PRESENTATION OF PRACTICAL TRAINING ON “400KV GSS “ \
Submitted to: Submitted by:
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
C-12 ELECTRICAL CW3 RIESE 18 APRIL DC SYSTEM -24V, 34 AMP HOUR NICKEL CAD BATTERY A 30V DC STARTER/GENERATORS -AN EXTERNAL DC POWER SYSTEM.
Restoration Concepts PEAK RC Training Classification: Confidential Version No.: 1.5 Date of Document: Document Owner/Author: B Pederson Classification:
Protection of Power Systems
©2003 PJM 1 Presentation to: Maryland Public Service Commission May 16, 2003.
Impact of Hurricane Ike on CenterPoint Energy’s Transmission System Paul Rocha Director, Transmission Planning Presented at October 2, 2008 ERCOT TAC Meeting.
SYNERGY INSTITUTE OF ENGINEERING AND TECHNOLOGY
Microgrid Load Management and Operation Erich Keller G&W Electric Co. Frank Patton Jr., PE N. J. Shaum & Son, Inc.
SEMINAR PRESENATATION ON WIDEAREA BLACKOUT (AN ELECTRICAL DISASTER) BY:Madhusmita Mohanty Electrical Engineering 7TH Semester Regd No
Equipment 1.Circuit Breaker. 3.Fuses. 4.Protecti- ve relay.2.Bus bar. TYPES OF SWITCH GEAR EQUIPMENT:-
1 NPCC – A-2 Dr. Mayer Sasson Transmission Planning Consolidated Edison of New York June 1, 2006 Presented to the NYSRC-RRS.
(c) IRD 2002 Power System Restoration (Black Start) Black Start Panel Session IEEE PES Summer Meeting Chicago, Illinois July 23, 2002 M. M. Adibi IRD Corp.,
Protection of Power Systems
Sub Station.
“FRCC RESTORATION PLAN (BLACKOUT & BLACK START)” - TRAINING -
IG BASED WINDFARMS USING STATCOM
Economic Operation of Power Systems
Combined operation of different power plants PREPARED BY : Priyanka Grover Btech (EE) SBSSTC,FZR.
Introduction To Reactive Power
POWER SYSTEM ANALYSIS INTRODUCTION.
Chapter 7 System Protection
Protective Relaying Conference
Interconnection of AES With The Grid
Presentation transcript:

FRCC System Restoration 2016 FRCC System Operator Seminar

FRCC System Restoration 2 Training Objectives System Assessment Restoration Strategies Restoration Considerations

Assessment of Elements System status Generation resources Transmission facilities

System Assessment – Generation Resources Identify Surviving Generators Stabilize Surviving Units Determine status of other generators Get start up power to off line units Initiate unit start ups Determine start up sequence

Identify Surviving Generators Current loading level Location Connected load Boundaries of island Plant capabilities Unit stability region

Stabilize Surviving Units Add additional load to stabilize Station load Distribution load Determine areas of separation May be difficult Location and size of islands may effect restoration strategy

Status of Generation Lost During Event Damage incurred Type of unit and characteristics

Determine Start Up Sequence Start-up sequencing is dependent on operation prior to event Surviving generation Outaged generation Offline generation Need to understand the Size Types State of operation going forward

Determine Start Up Sequence Blackstart Capability and location Off-line Generation Status prior to event Type of unit Power requirements Start up times Nuclear plants Company obligations

Determine Start Up Sequence Start Up Times (estimates) Hydro – usually quickest Combustion Turbines Smaller CTs – quick-start (10 minutes) Large CTs – may take longer (up to 1 hour) Steam - Drum-type 1-20 hours away Steam - Super Critical 4-20 hours away

System Assessment –Transmission Facilities EMS/SCADA Operational? Identify Energized Facilities Identify Faulted Equipment Restoration Identify Facilities Energized

EMS/SCADA Operational? 12 Are consoles up? Check data quality (watchdog, heartbeat, etc.) Are ICCP links valid?

Determine Faulted Equipment Digital Fault Recorders (DFRs) Inspections by field personnel Relay targets in substations Smart Relays

Identify Facilities Energized Breaker indications Open Permanent faults Out-of-Step conditions Temporary faults Closed De-energized line with no problem Faulted equipment that never cleared Equipment damaged after event

Identify Facilities Energized Station Batteries Capabilities Hour until depletion Open-close-open operation Relay Reliability Adequate fault current available Most questionable relays Re-closing relays Station hot bus-dead line re-closing

Identify Facilities Energized Underfrequency relays Status of what activated Sequence of restoration Facility status with regards to plan May not have what you thought you would May impact restoration plan

Restoration Two general restoration strategies: “All Open” All circuit breakers at affected substations are opened “Controlled Open” Only circuit breakers necessary to allow restoration to proceed are opened

All Open Strategy Can be accomplished by: Station Operators EMS/SCADA systems Advantages Simpler and safer configuration to restore Only breakers in restorations process will be closed Unlikely to experience inadvertent load pick-up Disadvantages Longer time to accomplish More breaker operations

Controlled Open Strategy Advantages Less energy requirements Breakers not involved in sectionalizing and restoration remain closed Postpone operation of some breaker to later in process May be quicker Disadvantages Higher emphasis on isolation between restored and de-energized systems

Restoration Methods Inside-Out / Blackstart Starts with formation of islands Utilizing blackstart generation Serve as basis for restoration plan Different methodologies Multiple Island Core Island Backbone Island

Restoration Methods Outside-In / Outside Assistance Utilizes outside source of power to begin restoration Only option without blackstart Combination Utilizes both approaches Inside-Out - Blackstart Outside-In – Neighbor Assistance

Restoration Methods Restores transmission from outside source while building internal islands Islands can be connected to either other internal islands or outside interconnection points

Priority vs. Critical Loads Priority Loads Highest priority Station service for nuclear facilities Service to facilities needed to restore the system Critical Loads Generating plant fuel supply depots Military facilities Law enforcement organizations Facilities affecting public health Public communication facilities

Restoration Considerations Cold Weather Switching SF6 Breakers Temperature and pressure dependent Compressors and heaters supplied by AC power Breaker operability could be reduced to as short as 30 minutes Low pressure will block operation

Restoration Considerations System Sectionalizing (Load disconnect) Regardless of strategy – sectionalizing should occur Disconnect load and capacitors from transmission system Load should be restored in small blocks Open station and controlled distribution capacitors Help prevent high voltages

Restoration Considerations Voltage Control Bulk Electric System maintained +/- 10% Maintaining voltages at minimum levels will reduce charging current Local load must be restored as transmission lines are energized to reduce voltages Station light and power Customer load

Restoration Considerations Interconnecting Generating plants or stations with synchro scopes Phase angle should be 10 o or less Transmission Stability Only facilities expected to carry significant load should be energized

Restoration Considerations Load/Frequency Control Small increments of generation and load Minimize frequency impacts Load pick-ups ≤ 5% total synchronized generating capability Example: You have 1000 MW of synchronized capacity – maximum load pick-up is 50 MW Frequency maintained between – Hz Regulate toward Hz

Restoration Considerations Surge Impedance Loading – The Surge Impedance Loading is the MW loading required to cancel the capacitance effect on the line. (VARS IN = VARS OUT) A line loaded below its SIL (MW) generates VARS A line loaded above its SIL (MW) absorbs VARS

Restoration Considerations AGC Control Set AGC control to CFC (Constant Frequency Control) when islanded Set AGC control to TLBC (Tie Line Bias Control) when tied with the Interconnection When tied to the Interconnection, all actions go through the Reliability Coordinator (RC). RC might direct one system to remain on CFC and the other to go on TLBC

Restoration Considerations Conditions to synchronize Voltage matched as close as possible Frequency close to identical Voltage phase angle within tolerance The goal in synchronizing two systems is to match frequency and phase angle so that there will be little or no transfer of energy between the two systems when the breaker is closed.

Restoration Considerations Synchronizing Phase Angle must be within 40° Raise generation on the side with the smaller voltage angle. Lower generation on the side with the larger voltage angle. Remember, it is easier to adjust the smaller system than the larger system

Restoration Considerations Voltage Magnitude when Synchronizing The greater the difference translates into a greater reactive power that will flow when the breaker is closed Angular difference between Running and Incoming Buses Incoming Bus Voltage 90°180°270°360° δ Running Bus Voltage

Restoration Considerations Matching Frequency when synchronizing The greater the difference translates into a greater real power that will flow when the breaker is closed Running Bus Frequency 60Hz Incoming Bus Frequency Hz

SOS Discussion There is more I can add onto this such as: Island Identification Synchronous Control Isochronous control ETC…. Currently at 29 slides, with questions this could be 45minutes to an Hour. Bob is working on a IncSys Tutorial PowerPoint to be taught as well. Let me know of suggested changes.

Questions? 36