G. Bolla For the CMS Pixel Group 2/25/20161 Status at P5 and infrastructures (mainly cooling) Status at P5 and infrastructures (mainly cooling)

Slides:



Advertisements
Similar presentations
Brio 2000 / Brio 2000-M E-Learning Service Manual Rev. 0.0.
Advertisements

Xenon Detector Status Liquid Xenon Group. 1 Outline Cryostat construction –Honeycomb panel test at Pisa –Assembly –Cryogenic test at SIMIC –Leak test.
EMCal DCS and related Issues with Shutdown/Installation B. S. Nilsen M. Cherney J. Fujita.
Procedures during Tracker Connection WPA meeting 3 rd December 2007, Michael Eppard, CERN Installation sequence Manpower needs for installation work.
MOM Summary 19/01/10 Water Now the ice has cleared I am able to get on the roof again. Could do with getting the conductivity readings fed back similarly.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 20, 2009.
CMS Pixel Technical Board Meeting – Dec. 16, Forward Pixel Cooling System Information Joe Howell.
SPD Cooling workshop: PLC item details. ups upgrade: 10-12' after trigger 24V - what to do in 10 minutes Present situation: In case of “normal power”
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
CMS FPIX Reinstallation/Commissioning Lorenzo Uplegger 4/20/091.
Chiho Wang ATLAS TRT Duke University CERN, Feb TRT Barrel assembly status & schedule Feb. 9, 2005.
LBT Q Engineering Review DYB. 26-Oct-2007LBT Q Engineering Review Highlights (Q3/2007) Currently in Commissioning Phase Currently in Commissioning.
1 Stony Brook Update Stretching your LEGS T.K. Hemmick for the tent crew.
Summary DCS Workshop - L.Jirdén1 Summary of DCS Workshop 28/29 May 01 u Aim of workshop u Program u Summary of presentations u Conclusion.
Endcap Integration Workshop: June 11-14, CSC Commissioning Andrey Korytov.
Status of NA62 straw electronics and services Peter LICHARD, Johan Morant, Vito PALLADINO.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
Evaporative Heater Design, qualification and planning M.Olcese PRR SCT off-detector cooling PRR SCT off-detector cooling March March 2005.
Faculty of Physics, University of Belgrade General meeting 19 th of August, ToF-LR HV Upgrade Jovan Puzović, Faculty of Physics, Belgrade.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Claudio Bortolin. 1 st June: PT100 electrical connection failure (Temp Chiller water In&Out) 1) it required an access to the cavern to be fixed 2) access.
Concept idea for the modular 2PACL system for the Atlas ITK 3 June 2015 Bart Verlaat 1.
19 May 09P. Tropea1 Fluorocarbon systems –SS1 hydraulics completed, now under commissioning –SS2 connections and sensors installation done –Pixels ready.
Active gas system status. S.Konovalov, K.Zhukov. Active gas system operation. S.Konovalov "Active gas system..."TRT Overview  Good design.
TOF Gas System Project Overview. Content Prototype for Aging tests done for RPC’s TOF Gas System: parameters and module layouts. Special Technology: channel.
European Organization for Nuclear Research - Organisation européenne pour la recherche nucléaire SSD/SDD Proposal Upgrade 30/08/2012
26 May 2010Hans Postema - CERN Status and plan for the development and construction of CO2 Cooling System for Pixel Upgrade 1.
Associated detection/extinction systems D. Swoboda.
Claudio Bortolin 03/09/2012. SPD (RP analyses required) 1) Pump 17b replacement and leak test 2)Pressure test on the old inlet lines (technicians coming.
IDE DCS development overview Ewa Stanecka, ID Week, CERN
TK Dry Gas System Operation  System overview  Dry Gas Consumption  Interlocks and thresholds  Documentation  Operational model  Final comments.
Lau and Niels, NA62 TD meeting, 17 March Complete the crane consolidation in TCC8 Reinstall front-end after alignment checks Consolidation of T10.
Status of and Installation Plan for DC Gas Control System and Target Work Scheduling Meeting 4 August 2006 PSI W. Molzon, Feng Xiao.
CMS Proposal for a Maintenance & Operation agreement with EN/CV/DC for fluorocarbon detector cooling circuits v.2 P. Tropea For the CMS experiment.
CLM Maintenance. Covers : 1 - Side cover, 2 - Back cover, 3 Top cover, 4 - Lamp door, 5 - Side cover input and communication side, 6 - HEPA dust filter,
Status and schedule for the H - source upgrade at HINS beam line HINS Meson meeting January 5 th, 2012 L. Prost (most inputs from Steve Hays & Alex Chen)
19 January 2006VELO installationEddy Jans 0 VELO-installation meeting CERN, January 17, 2006 preparation IP8-area SX8 moving SX8 -> IP8.
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
R. Boyd 1 February  Dr. M. Saleem  D. Jana  M. R. Meera Labbai  R. Boyd.
CO2 cooling in CMS General overview 30 July 20101Hans Postema - CERN.
1 Onsite Status Itaru Nakagawa RIKEN/RBRC. 2 Schedule.
October 18, Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.
CMS consolidation activities of detector cooling system Detector cooling project P. Tropea.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
R. Fantechi. Shutdown work Refurbishment of transceiver power supplies Work almost finished in Orsay Small crisis 20 days ago due to late delivery of.
Status of the ATLAS ID Evaporative cooling system JCOV 25 Nov P. Bonneau TS/CV/Detector Cooling CONTENTS Overall statusOverall status Cooling plant.
Installation of the T600 at Fermilab CSN2, September 22,
Claudio Bortolin. pump: replaced outlet filter: replaced demineralized cartridge: replaced mechanic filter on air control: replaced SSD chilled water.
ALBA RF System Paco Sanchez - 13th ESLS RF - DESY, 30 September Paco Sanchez, RF Group, CELLS (Consortium for the Exploitation of the Synchrotron.
Tracker cooling plant refurbishment Project status Revised plan Financial impact.
Tracker cooling status General status Production: Manifolds, Distribution lines Work at P5 Plan Conclusions 19/05/091E. Focardi.
TC meeting P2 planning wks 3&4 A.Tauro
Pixel Action Matrix C. Newsom July 15, Overview Critical Parameters Initial Discussion – Top 6 critical failures Discussion - Detailed Documentation.
The MINER A Operations Report All Experimenters Meeting Howard Budd, University of Rochester Feb 24, 2014.
LHCb CO 2 cooling meeting Burkhard Schmidt – May 20,
V Thermo-siphon Workshop Test protocol Jan Godlewski PH/DT-PO On behalf of thermo-siphon working group
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
Arnd Meyer (RWTH Aachen) Sep 8, 2003Page 1 Integrated Luminosity Total data sample on tape with complete detector > 200pb -1.
13 Januar 2011 Immanuel Gfall (HEPHY Vienna) Annekathrin Frankenberger (HEPHY Vienna) SVD Cooling Cooling Meeting Karlsuhe.
Pixel Cooling Upgrade (2013) 1 December 20081Hans Postema - CERN.
1 04 April 2007 L. Roy Detector Safety System for infrastructure - General fire detection (barracks, cavern) - Sniffer system (smoke detection above the.
7/8/20161 Pixel detector status and infrastructures Pixel detector status and infrastructures G. Bolla.
University of Colorado – Boulder
Completion of the MICE-US construction project
ELENA installation and commissioning status
Tracker cooling loop “check out” draft for discussion
IBBelle: Status Commissioning at MPP Transport to KEK
Presentation transcript:

G. Bolla For the CMS Pixel Group 2/25/20161 Status at P5 and infrastructures (mainly cooling) Status at P5 and infrastructures (mainly cooling)

The schedule for the removal/re-installation of FPIX March 05 extraction PLUS Z SIDE March 19 extraction MINUS Z SIDE March re-installation of PLUS Z SIDE April 09 re-installation of MINUS Z SIDE Passed the WPA with tech coord. Tech coord wants a single document that starts with the removal of the alignment ring and finishes with the pixel extracted (Salvatore is editing it). Procedures and manpower available at: Procedure : Manpower: Overall the situation seems to be under control. Removal/re-installation of the detector 2/25/20162Gino Bolla Tracker day

Mauro, Pasquale, Gino, Ricardo Danek etc… would like to have the transportation from P5 to TIF on Thursday (delivery on Friday) instead of Friday (delivery on Saturday). I already announced it last week at the tech coord meeting – Crane availability Seems to be OK but ES have some concerns If we want to go this way we would like to disconnect the PLUS Z side on Wednesday late afternoon (into the evening). This would add some safety to the transportation to TIF Trucks not allowed during the w-e – If not Friday night than Monday To be discussed tomorrow at tech coord. This week 2/25/20168Gino Bolla Tracker day

The work on the cooling plant is planned since the end of It can be split into two components Increase easiness of operation and safety: – Move the tank up a floor (rely on gravity and not on a pressurized GAS system) – Replace Manual bypass valve with a BPR Large enough o swallow the whole flow from the pump. – Replace the pressure regulating valve with a bigger one Large enough o swallow the whole flow from the pump. – Improve the degassing system (already rather good) Leak tightness – Change the distribution lines (as in the Strip cooling plant) Components of the distribution lines (TA valves and plastic hoses to calibrated orifices) are made with materials or technology Concerns were raised about leaks on the shutoff valves after disconnect/reconnect to the flanges – Overall checks of the status of the plant We always considered the first component mandatory and the second one optional being the pixel system never leaked much (~1/2 Kg/day). Cooling plant (0) 2/25/20169

Piping work inside the cooling plant finished on Feb 20 th New pressure regulating valve is installed since the middle of february The pump and BPR (back Pressure regulator) are being installed today (delays on delivery but irrelevant) Piping work from the cooling plant to the tank (up a floor) is finished (Wednesday Feb 25) Leak search of the cooling plant (alone) – Sometimes this week in parallel with the distribution lines work Cooling plant (1) 2/25/201610

Decision on what to do with the distribution lines. Large fruitful discussion Feb 25. If old cooling lines stays we start commissioning the cooling plant in stand alone mode. If not we need to modify the cabinet (enlargement) so that the new distribution lines fit. This is a two phase program: Phase 1. Implement the necessary modifications to host the new lines (URGENT): – Move and Modify the support brackets – Modify the roof of the cabinet Phase 2 get the new walls for the cabinet installed (NOT URGENT) – This is needed only for COLD operation that is not foreseen before the middle of April. Install and braise the new cooling lines (18+18). Starts next week the braising process requires inert gas flow and we want to avoid piping this gas into the detector The minus Z side (top lines at the plant) of the detector will be disconnected this week (Thursday or Friday) and bypass hoses installed The Plus Z side (bottom lines at the plant) of the detector will be disconnected next week (Tuesday or Wednesday) and bypass hoses installed On overall if we install the new lines than we need one more week than scheduled and we will be ready only on April 6th Cooling plant (2) to do 2/25/201611

Cooling plant stand alone. Find and fix any possible leak. Start the pump (all lines CLOSED) (bypass hoses anyway). Measure the setting point of the pressure switch (2.5 bar nominal). – Tuning if needed. Measure and tune the setting point of the back pressure regulator (BPR) Check and retune (if necessary) the time response of the feedback system to the pressure regulating valve (remember it is a new valve) Cooling plant with bypass hoses (This starts with a plant running stable at 2 bar). Open one loop at the time (shutoff) with the Swagelock closed Open the swagelock slowly to nominal position (flow established) – Repeat for all FPIX lines. During these operation we will need the cooperation of the TS-CV personal that handles the PLC code. Cooling plant (3) to do (commissioning) 2/25/201612

CAEN backboard modification – Finished PP1 splicing of two fibers – Given up on this under the advice of Jan Troska – These fibers are (at this point) spare fibers and they might be needed for the upgrade. Keep them in the to-do list for another shutdown New Humidity sensor to be installed in FPIX. – The sensors (HS2000) exist and Lalith will be here starting this w-e – It is decided to read them out through Andromachi Tracker Monitor PLC – The wires from the detector to the PIXEL PLC exist already – New wires have to be stringed from the PIXEL PLC to Machi’s PLC Documentation is final (connectors and pinout) Machi’s team will do the cabling – Machi will do the necessary work to enlarge the capability of the PLC (new modules) – Data will be available in PVSS FED daughter boards fixation – This week Manfred, Karl, Danek and Josh will tackle this minor modification Others (minor things if you like) 2/25/201613

Successfully negotiated an extra week with tech coord. Schedule (tentative) 2/25/201614

We have a very good plan for the next couple of months! We have very talented and experienced people that will do the job. We also have younger members that are new to these tasks. Always think about safety of the personnel and of the equipment while you perform your job. Many of us working at P5 on VME/CAEN and DCS do not have the proper electrical safety training. – Consider joining the training on March 19 Send to me and Christoph Schafer if you want to join We should take this as an example. – Comunication in CMS is not always optimal. Cooperation from each of us is welcome. (use hypernews to post training that you think might be useful to the member of the pixel community). General remarks 2/25/201615Gino Bolla Tracker day

In 3 weeks from now we need to be ready for checkout the re-connected detector In about 6 weeks (mid april) from now the re-commissioning phase will start as well. 4 weeks if no change in T 8 weeks if we go colder (??) This is a sizable effort for our community It is also the beginning of a continuous coverage of operation at P5 Your help will be needed for shift and expert coverage. It is time to setup again a tool to handle shifts. General remarks 2/25/201616Gino Bolla Tracker day