Technology Department 1 ELENA Fast Deflectors status Nicolas Voumard, Jan Schipper TE/ABT/EC TCM 17/11/2015 1/11.

Slides:



Advertisements
Similar presentations
A3016 and MAO test at CAEN Pigi, A. Boaino & CAEN.
Advertisements

HPS MPS OVERVIEW Dan Sexton & the Safety Systems Group JLAB 1.
N. Voumard, AB-BT-EC LBDS Audit, CERN LBDS Trigger Signal Distribution Trigger Synchronization Unit (TSU) Trigger Fan Out (TFO) Power Trigger Unit.
Jan. 15, Safety Board Review (Rev D) Safety Board PCB Review (Rev D) Eric Warmbier.
8/11/2006 FPIX TB meeting L. Perera 1 Pixel Power Supply Response Measurement Lalith Perera - Univ. of Iowa Carlos Florez, Simon Kwan, Charles Newsom,
1. Commissioning of cryogenic crates using Mobile Test Bench 1. The Mobile Test Bench 2. Cryogenics crates and equipment – types of transducers and actuators.
PH/DT MCP & MNO NEW MAGNET SAFETY SYSTEM HARDWARE Sylvain Ravat PH-DT Xavier Pons PH-DT.
Measuring Leakage Current on Singles and Ladders P. Riedler and S. Ceresa, August 2005 Sensor Chip Manipulator Needle for sensor back side contact Probe-card.
ZQNA Electrostatic Quadrupoles for ELENA Transfer Lines 1.Conceptual design 2.Performance 3.Engineering details 4.Interfaces 5.Production planning D. Barna,
TF Joint Voltage Drop Instrumentation Robert Marsala (609) Hans Schneider (609) Engineering Operations August 7, 2003 TF_JOINT_Final_Design_Review.ppt.
Low Voltage Power Requirement of TOF FEEs. Maximum tray. Low Noise:  Periodic and Random Distortion (PARD) < few mV RMS Floating.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
1 Copper Stabilizer Continuity Measurement Project CSCM Mini Review Powering Implementation H. Thiesen 30 November 2011.
Saverio Minutoli INFN Genova 1 1 T1 Electronic status Electronics Cards involved: Anode Front End Card Cathode Front End Card Read-Out Control card VFAT.
LKr Calorimeter Control and monitoring R. Fantechi 19/02/2010 R. Fantechi.
V. Bobillier1 Long distance cable installation status Calorimeter commissioning meeting.
CERN ISOLDE / HIE ISOLDE 1 Isolde Target Modulator Prototype development prepared by T. Gharsa TE-ABT-EC CERN.
The LST High Voltage System LST Readiness Review May 5, 2004 Klaus Honscheid Ohio State University.
Hall D Online Meeting 27 June 2008 Fast Electronics R. Chris Cuevas Jefferson Lab Experimental Nuclear Physics Division 12 GeV Trigger System Status Update.
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
TE/MPE/EE J. Mourao T/MPE/EE 1 November 2012 LHC Machine Local protection Redundant Power supply (DQLPUR) & interface Module (DQLIM) progress status.
TE-MPE-TM 25/10/2012, ELQA team TP4 System – the main tool for ELQA Mateusz Bednarek, CERN, Geneva Jaromir Ludwin, IFJ-PAN, Krakow.
Status and planning of the CMX Wojtek Fedorko for the MSU group TDAQ Week, CERN April , 2012.
HV-Splitter for RENO Project S. Stepanyan, 김우영 경북대학교 Y.Kim Sejong University May-2008.
MICE RF System Power Supplies, Control and Monitoring Status report February 2012 Chris White, STFC Daresbury Laboratory MICE Collaboration Meeting CM32,
STATUS OF NOKER PULSER FOR SHORT MAGNETS C. C. JENSEN DECEMBER 4, 2013.
1 4 PCB: LEFT TOP 115 channels, LEFT BOTTOM (115), RIGHT TOP (106), RIGHT BOTTOM (106). For LEFT TOP board 115 channels we have: 115 smd connectors (AMP.
Status of NA62 straw electronics Webs Covers Services Readout.
L0 Technical Readiness Review-Electronics Installation Linda Bagby L0 Electronics Installation  System Electronics Overview u Low Voltage s Filter.
Status of and Installation Plan for DC Gas Control System and Target Work Scheduling Meeting 4 August 2006 PSI W. Molzon, Feng Xiao.
BI.DIS10: Magnets & generators R. Rosol, L. Sermeus, T. Stadlbauer, TE-ABT LIU review, 20 November
Production Readiness Review at PNPI Chamber assembling: Main production and quality control steps 30 January 2004 – G.Alkhazov 1.Input components control.
LHC Beam Dumping System Experience from reliability run and Re-commissioning procedures MPP Nicolas Magnin – TE/ABT/EC.
Payload Safety Review Plan and Issues Leland D. Hill.
ELENA Fast Deflectors Generators N.Voumard, T. Gharsa.
P. Paolucci - I.N.F.N. of Napoli 1 RPC workshop, 2 march 07 RPC Power system P. Paolucci, G. Polese and D. Lomidze I.N.F.N. di Napoli.
8/31/05DR Lynch1 HBD Preparations in the IR Don Lynch.
Preparation of chamber training g. passaleva. Gaps to be trained We have O (100) gaps that have tripped at least once since June At a quick glance they.
B.Satyanarayana Department of High Energy Physics Tata Institute of Fundamental Research Homi Bhabha Road, Colaba, Mumbai,
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
V. Bobillier1 Cable installation status.
ELENA EXTRACTION LINES W. Bartmann, D. Barna, M. Fraser, J. Jentzsch, R. Ostojic ELENA Commissioning discussion, 23th November, 2015.
R. Fantechi. Shutdown work Refurbishment of transceiver power supplies Work almost finished in Orsay Small crisis 20 days ago due to late delivery of.
R. A. Barlow, LIU-PSB review, 20 Nov BI.DIS Pulse generators controls R.A.Barlow, LIU-PSB review, 20 Nov
Status of the PSD upgrade - Status of the PSD cooling and temperature stabilization system - MAPD gain monitoring system - PSD readout upgrade F.Guber,
Power Supply System Discussion Topics Steve Virostek / John Joseph LBNL Spectrometer Solenoid Workshop May 10, 2011.
Machine Protection Review, R. Denz, 11-APR Introduction to Magnet Powering and Protection R. Denz, AT-MEL-PM.
Technology Department BI.DIS general controls status R.A.Barlow EC section
Faculty of Physics, University of Belgrade General meeting, Wroclaw 28 th of January, ToF-L/R HV Upgrade, Status and Plans Jovan Puzović, Faculty.
André Augustinus 13 June 2005 User Requirements, interlocks, cabling, racks, etc. Some remarks.
Faculty of Physics, University of Belgrade Collaboration meeting, Budapest 15 th of May, ToF-L/R detector HV upgrade Jovan Puzović, Faculty of Physics,
Faculty of Physics, University of Belgrade Collaboration board meeting 31 th of January, ToF-L/R detector HV upgrade Jovan Puzović, Faculty of Physics,
RF Commissioning D. Jacquet and M. Gruwé. November 8 th 2007D. Jacquet and M. Gruwé2 RF systems in a few words (I) A transverse dampers system ACCELERATING.
February 4 th, Quality assurance plan: production, installation and commissioning N.Vauthier TE-CRG Technical Review on Beam Screen Heater Electronics.
Two half-day seminars on the remaining work packages to complete the MEDICIS Facility POWER CONVERTERS FOR MEDICIS Davide Aguglia & Julien Parra-Lopez.
Cost and schedule for ELENA Beam Transfer Systems W. Bartmann, J. Borburgh, E. Carlier, L. Ducimetiere, T. Fowler, M. Hourican, R. Ostojic, L. Sermeus.
ELENA installation progress F. Butin / ELENA collaboration.
TOF Low Voltage and High Voltage Systems Vahe Ghazikhanian UCLA Department of Physics and Astronomy V. Ghazikhanian July 21, 2005.
ProtoDUNE - SP SLOW CONTROLS MEETING 11/11/2016 CERN – EP/DT
MICE RF System Power Supplies, Control and Monitoring Status report
Test bench for active bases for SATLAS Photomultipliers
Dielectric Oil Installations
Injectors BLM system: PS Ring installation at EYETS
EC Activities Status for the LIU
T1 Electronic status Conclusions Electronics Cards:
Mini-drawers, FE-ASIC , Integrator
Some proposals on HV circuits realization for segmented straw detector
Vacuum Controls Stephen Schuh Tom Porter 25 October 2006
Rack and Interconnect Design in E-plan
KFA10 status 03/06/2019 Currently:
Presentation transcript:

Technology Department 1 ELENA Fast Deflectors status Nicolas Voumard, Jan Schipper TE/ABT/EC TCM 17/11/2015 1/11

Technology Department ELENA Fast Deflectors control overview 2/11

Technology Department -Control side on platform above ELENA ring on four consecutive racks -Two generators per crate (PCU and HVPS), 5 crates + 1 for potential future transfer lines… -Three PXI systems (1 system can control up to four generators) -One touch panel for local control for all generators -One rack for PDC -One front-end computer ELENA Fast Deflector control side 3/11

Technology Department -Fast deflector generator -1: 1.2 uF high voltage storage capacitors OK -2: 11kV Behlke switches push-pull OK (pos and 6.5kV) -3: CAEN bipolar 8kV HVPS TBT in remote with PXI -4: 12kV earthing switches OK -5: Generator controller Partially tested -6: Pickups New version TBD To be tested connected to the tank ASAP with actual pickups, And by mid december with new pickups version. ELENA Fast Deflector Generator HV circuit overview /11 5

Technology Department ELENA Fast Deflector control side, PXI Controller 5/11

Technology Department ELENA Fast Deflector : elements production and testing ELEMENTSTATUSDONETO BE DONEDUE Generator BoxOngoing Cabled, TBT by end november Base plate mounted with HV switches, capacitors, resistors and relays. HV Cables with SHV-20 New Pickups, Controller board mounted (TBT) End of November Mid December With new pickups PXI ControllerComponents to be ordered Software mainly done by JS Jan did already most of the control and LabView implementation Validation, testing… HVPS control to be tested Front-end computer architecture TBD February 2016 Cabling from platform to generators OngoingCables pulled by EN-EL and connectors on the control side mounted Connectors on generator side to be mounted. Mid February 2016 Generator Controller Ongoing- EIS interface done (TBT) - Analog Receiver done (TBT) - Caen HVPS tested - Power Control Unit -> finish schematic and routing, - Control crate cabling - Three crates to be assembled Mid January 2016 Power Distribution Controller Nothing done (AA)March 2016 PXI interfaceOngoingBased on existing design (HG)Cabling to be defined.February 2016 Comissioning with beam scheduled for July /11

Technology Department ELENA Fast Deflector : safety concerns and commisionning - EIS -Prepare safety documentation -Define tests to be done (lab and on-site) -Define clearly which and how much fast deflectors to be connected to EIS -Safety discharge switches tested (Ross relays) -Prepare interlocks test procedure -Correct reaction of the system to every interlock EIS Interface card Based on BE-PO design - Commisionning / Installation -Prepare commisionning plan and strategy -Installation should be ready by April-May 2016 for the two ELENA ring extractions -Beam comissioning expected for July Transfer lines fast deflectors planed for /11

Technology Department ELENA Fast Deflector : high voltage pickups There is still work to be done to get a precise high voltage pickup as requested for this application to avoid oscillations. (flattop and platbottom stability at 0.1%) A new pickup design has been already designed, on the base of the North Star high voltage probe, including a 50 Ohms series resistor to adapt to the cable impedance, reorganization of the components in «star topology», ground plane on low voltage side, removed adjustable capacitor. OLD DESIGN NEW DESIGN 8/11

Technology Department ELENA Fast Deflector : +6kV OLD DESIGN North Star PVM-12 Cable reflexion due to pickup position 9/11

Technology Department ELENA Fast Deflector : -6kV OLD DESIGN North Star PVM-12 Cable reflexion due to pickup position 10/11

Technology Department ELENA Fast Deflector QUESTIONS ? 11/11