David M. Lee 12-06-2005 Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs.

Slides:



Advertisements
Similar presentations
FVTX Transition to Operations PHENIX FVTX Close Out April 23, 2012 BNL 1 FVTX Close Out Review Ed OBrien April 23, 2012.
Advertisements

David M. Lee Los Alamos National Laboratory Heavy Ion Program 1. Dave Lee – Heavy Ion Program – 15 min 2.Mike Leitch – pp, dAu – 30 min 3.Pat.
A “BTeV” Hybrid Pixel Telescope for MTest David Christian May 4, 2007.
Muon Tracking FEE R.E. Mischke Los Alamos 10 September, 1999 presentation to the PHENIX Muon Arm Technical Advisory Committee.
L. Greiner 1HFT PXL LBNL F2F – March 14, 2012 STAR HFT The STAR-PXL sensor and electronics Progress report for F2F.
3 Oct Cost and Schedule Update Craig Ogilvie, Iowa State University Analysis of system risks Update schedule  Critical path.
PALM-3000 Management Update A. Bouchez Team Meeting #9 10/22/2008.
PHENIX Vertex Tracker Atsushi Taketani for PHENIX collaboration RIKEN Nishina Center RIKEN Brookhaven Research Center 1.Over view of Vertex detector 2.Physics.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
E.Kistenev, Forward Upgrade Meeting 08/18/04 Forward (Nose Cone) Calorimeter: Update 2.5 mm.
David L. Winter for the PHENIX Collaboration PHENIX Silicon Detector Upgrades RHIC & AGS Annual Users' Meeting Workshop 3 RHIC Future: New Physics Through.
March 20, 2001M. Garcia-Sciveres - US ATLAS DOE/NSF Review1 M. Garcia-Sciveres LBNL & Module Assembly & Module Assembly WBS Hybrids Hybrids WBS.
Electrical Integration WBS Eric J. Mannel Columbia University Electronics Project Engineer VTX and FVTX.
Takeyasu Ito University of Tennessee EDM Collaboration meeting December, 2004 Cost and Schedule Estimate WBS 2.5- Neutron beam polarizer/splitter for SNS.
Jon S Kapustinsky 11/17/2010 Jon S Kapustinsky FVTX Commissioning Plan 1.71 Jon S Kapustinsky 1.
NEDM Construction Project Cost & Schedule Philosophy Vince Cianciolo, ORNL Physics Division Internal Cost & Schedule Review 02/11/2005.
HvH, DNP Oct The FVTX detector in PHENIX Hubert van Hecke, Los Alamos National Laboratory for the PHENIX collaboration Vtx (Mannel) Fvtx (HvH) RPC.
David M. Lee Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs.
U N C L A S S I F I E D FVTX Detector Readout Concept S. Butsyk For LANL P-25 group.
Gerd J. Kunde - LANL1 The FVTX Technology  Outline Overall Picture Silicon Detector –Geometry, Layout, Process Readout Chip –FNAL Chips, New Chip PHX.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
DOE/NSF Review of the U.S. ATLAS Construction Project June 3-4, 2002 WBS 1.1 Silicon Subsystem Abe Seiden UC Santa Cruz.
Slide 1 6-Nov-98PHOBOS Review: Cost & Schedule Cost & Schedule S. Steadman, MIT PHOBOS Cost & Schedule Review Technical Advisory Committee BNL November.
Pixel hybrid status & issues Outline Pixel hybrid overview ALICE1 readout chip Readout options at PHENIX Other issues Plans and activities K. Tanida (RIKEN)
Robert Pak 1 DOE VTX Review June 2, 2009 Mechanical Integration & Safety Personnel: Walt Sondheim: Mechanical Project Engineer Don Lynch: PHENIX Chief.
U N C L A S S I F I E D 7 Feb 2005 Los Alamos RHIC Program David M. Lee Heavy Ion and Medium Energy 7 February 2005.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese U.S. ATLAS Review Revised Version November 29, 2000.
Muon trigger upgrades, missing since not aimed towards DOE funding PHENIX upgrades: view presented to DOE R&D $3.5M Construction $16.6M Au-Au p-p 200 Si-Si.
M. Brooks, LANL 1 02/19/07 Review Schedule The FVTX upgrade project Melynda Brooks Silicon Sensor, Chip, ReadoutJon Kapustinsky Mechanics Walt Sondheim.
MTest Pixel Telescope – Status Update David Christian September 11, 2007.
03/12/07 Jon S Kapustinsky LANL Jon S Kapustinsky, LANL Forward Vertex Detector Collaboration Meeting UNM, March 12, 2007 Outline: FVTX Overall Description.
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese Revised Version December 18, 2000.
2 Silicon pixel part Done and to be written Written! Under way To be done Introduction 1.Hybrid Pixel Assembly Concept 2.Silicon sensor 1.First thinned.
ATLAS PIXEL SYSTEM OVERVIEW M. Gilchriese Lawrence Berkeley National Laboratory March 11, 1999.
David Lee, FVTX Review Nov Cost and Schedule WBS 1.0 David M. Lee Los Alamos National Lab Deputy Project Leader.
The PHENIX Forward Silicon Vertex Tracker Eric J. Mannel IEEE NSS/MIC October 29, 2013.
M. Gilchriese U.S. Pixel Mechanics Overview M. G. D. Gilchriese Lawrence Berkeley National Laboratory April 2000.
Axel Drees, Stony Brook University BNL review of RHIC detector upgrades, March 14 th 2006 Overview of PHENIX upgrades Goals of PHENIX upgrades program.
FVTX Wedge Assembly WBS , , , , , David Winter Columbia University FVTX Wedge Manager.
Aug 2003 Craig Ogilvie 1 Landscape/Goals for R&D  Goal: Barrel+structure ready Summer/Fall 06 (run07)  Goal: Endcaps ready Summer/Fall 07 (run08)  RIKEN.
Robert Pak, FVTX Annual Review Nov Mechanical Integration WBS Robert Pak Brookhaven National Laboratory.
1 FVTX Detector Assembly Stephen Pate New Mexico State University (FVTX Assembly Management WBS 1.7) Stephen Pate, NMSU – FVTX Review – 16-Nov-2009.
Muon Tracker Responsibilities This Year South arm commissioning through this year’s run Analysis Software oversight and development North Arm station 2.
Brenna Flaugher Sept. 24 th Lehman Review1 Run IIB Silicon Upgrade: Cost and Schedule Lehman Review Sept. 24, 2002 Brenna Flaugher Run IIB Silicon Project.
D. M. Lee, LANL 1 07/10/07 Forward Vertex Detector Cost and Schedule.
Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs Cost Schedule.
1 FVTX Monthly/Quarterly Report January 2009 Cost Summary Schedule Summary Current technical status of each WBS item.
D. M. Lee, LANL 1 07/10/07 Forward Vertex Detector Overview Technical Design Overview Design status.
PHENIX Timetable FY 2002 FY 2003 Prepare S  S  with Au-Au beams May 2001 March 2002 Jan 2001 June 2002 Sept st  physics (J/  suppression &
PHENIX Vertex Detector with Conventional Strip Sensors Abhay Deshpande Stony Brook University.
Walter Sondheim 6/9/20081 DOE – Review of VTX upgrade detector for PHENIX Mechanics: Walter Sondheim - LANL.
M. Brooks, 16-Dec-00 Muon Collaboration Meeting North FEE Schedule Assume installation in 2002 shutdown, June-October(?), gives 1.5 years to complete pre-installation.
Columbia University IN THE CITY OF NEW YORK FVTX Electronics Oversight and Integration Eric J. Mannel Columbia University.
Robert Pak VTX Meeting June 3, Robert Pak 1 VTX Meeting June 3, 2005 General Progress Started general integration meetings for detector upgrades.
March 25, FVTX Monthly/Quarterly Report June, 2009 Technical Status, Cost & Schedule Melynda Brooks, LANL.
D0 PMG 2/3/00 PMG Agenda Feb 3, 2000  Overview u Project Manager’s Report – Tuts u Fallback options – Weerts  Silicon Support Cylinder Modifications.
D. M. Lee, LANL 1 07/10/07 Forward Vertex Detector Status: R&D: Scientific and Technical Resources Technical Design Overview Design status R&D Cost and.
Silicon strip detector R&D issues –readout chip decision –interface with PHENIX –ladder Technical options –SVX4 or MVD-TGV+AMU/ADC recut –other sensors.
B => J/     Gerd J. Kunde PHENIX Silicon Endcap  Mini-strips (50um*2mm – 50um*11mm)  Will not use ALICE chip  Instead custom design based on.
David M. Lee Los Alamos National Laboratory DOE Review of the Heavy Ion Program Agenda Introduction – Joel Moss 1. David M. Lee – KB02 program.
1 FVTX Quarterly/Monthly Report July 2008 Melynda Brooks, Dave Lee.
Melynda Brooks, FVTX Annual Review, November FVTX Project Overview Cost & Schedule Melynda Brooks Los Alamos National Laboratory FVTX Project Manager.
Summary of IAPP scientific activities into 4 years P. Giannetti INFN of Pisa.
WBS 1.05 Commissioning Detector Scope, Cost & Schedule Sven Vahsen University of Hawaii.
Evidence for Strongly Interacting Opaque Plasma
Silicon Pixel Detector for the PHENIX experiment at the BNL RHIC
ECAL project in the future 2-3 years
Work packages status in Torino and perspectives
RF System (HLRF, LLRF, Controls) EDR Plan Overview
Calice Tile-HCal and Tail-catcher/Muon Tracker
Presentation transcript:

David M. Lee Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs Cost Schedule

David M. Lee Los Alamos National Laboratory LANL coordinate work to procure the silicon sensors, work with FNAL on the development of the PHX chip, with Columbia on development of the interface to PHENIX DAQ, and on the simulation effort with NMSU. Los Alamos is currently leading the mechanical engineering and the integration effort for the barrel detector, VTX, and will continue those efforts for the FVTX. Columbia University Columbia University is an acknowledged expert on the PHENIX DAQ system They will work on the interface between the PHX chip and the PHENIX DAQ. Iowa State University Iowa State University is currently working on management details with the barrel detector and working on an (funded) SBIR effort for the level one trigger capabilities of the FVTX. Charles University, Czech Technical University, Institute of Physics, Academy of Sciences, Prague The Czech groups have been active in the development, testing, assembly, and commissioning of the ATLAS pixel sensors. They will do the same for the FVTX effort and additionally participate in software development. New Mexico State University NMSU will work on comprehensive simulations for the FVTX effort and work on the sensor testing. University of New Mexico UNM has experience in testing, Q/A and a laboratory for characterization of sensors. They are currently working on the barrel strip sensors and will do the same for the FVTX effort. They may also work on the flex cables. Ecole Polytechnique, Saclay Ecole Polytech has contributed to the electronics and software for the muon system has expressed interest in doing the same for the FVTX. Saclay will work on software. Participating and Interested Institutions

David M. Lee Yonsei University, Seoul, Korea The Yonsei group has worked on electronics and software for the muon system and will do the same for the FVTX. Argonne National Laboratory Argonne National Laboratory is not a member of PHENIX but is considering joining to work on the spin physics program and the FVTX. We will want them to manage and coordinate all activities at FNAL. Participating and Interested Institutions

David M. Lee Subsystem Manager D.Lee Deputy Subsystem Manager M. Brooks Mechanical Engineer Walt Sondheim Electronics Engineer Sensors Charles University, LANL PHX LANL, FNAL Interface Columbia, LANL Flex Cables UNM,LANL Integration and Ancillary Systems BNL,LANL Simulation NMSU, LANL Design J. Kapustinsky Prototyping Prague,NMSU SensorTesting Prague, UNM Production Prague Design FNAL, G. J. Kunde Prototyping G. J. Kunde Prod + Testing G. J. Kunde Bump Bonding ANL Prototyping M. Brooks FPGA S. Butsyk Board design BNL, Columbia, LANL Racks, LV, HV UNM, BNL, Sensor cable D. Fields ? Bus D. Fields ? Ladder D. Lee Support Structure D. Lee Ladder Assembly FNAL, ANL Detector Assembly ANL, BNL, LANL Installation BNL Ancillary Systems BNL Track finding NMSU, LANL, SACLAY Organizational Chart

David M. Lee Cost Basis - Major Items Mechanical structures – HYTEC estimate based on prior experience Sensors – Quotes from ON Semiconductor and CIS, Nov 2005 PHX – FNAL estimate based on prior experience Electronics Interface – estimate based on prior experience with Muon system Bump Bonding – BTev experience with pixel chip DCM,slow controls, etc – Muon system experience

David M. Lee R&D Costs LANL LDRD-DR - $310k $1.2M/year for 3 years (FTE’s and M&S) Interface Module - $200k Mechanics - $50k HDI and flex cables $60k LANL Heavy Ion Program - $50k Sensor design - $50k BNLR&D funds - $495k PHX design and Prototype - $440k Mechanics - $55k

David M. Lee Contingency – Risk Analysis Risk FactorTechnicalCostScheduleDesign 0Not used Detail design > 50% done 1Existing design and off-the-shelf H/W Off-the-shelf or catalog itemNot used 2Minor modifications to an existing design Vendor quote from established drawings No schedule impact on any other item Not used 3Extensive modifications to an existing design Vendor quote with some design sketches Not used 4New design; nothing exotic In-house estimate based on previous similar experience Delays completion of non-critical subsystem item Preliminary design >50% done; some analysis done 6New design; different from established designs or existing technology In-house estimate for item with minimal experience but related to existing capabilities Not used 8New design; requires some R&D but does not advance the state-of-the-art In-house estimate for item with minimal experience and minimal in-house capability Delays completion of critical path subsystem item Conceptual design phase; some drawings; many sketches 10New design of new technology; advances state- of-the-art Top-down estimate from analogous programs Not used 15New design; well beyond current state-of-the-art Engineering judgmentNot usedConcept only

David M. Lee FVTX Cost Estimate

David M. Lee HYTEC Cost Estimate – VTX and FVTX FVTX

David M. Lee FVTX Types 1 & 2 Silicon Wafer Layout Sensor Needs: Type ea Type 2 96 ea Wafer needs: 96 x 1.2/.6 = 192 Cost: $240k

David M. Lee FVTX Type 3 Silicon Wafer Layout Sensor Needs: Type 3384 ea Wafer Needs: 77 wafers x 1.2/.6 = 154 Cost:$192.5k

David M. Lee FVTX Schedule Assumptions Construction start – October 1, 2007 ( FY08) LANL R&D start - January 2006 BNL R&D start – January 2006

David M. Lee FVTX Schedule

David M. Lee FVTX Schedule

David M. Lee Summary No exotic or state-of-the-art R&D necessary LANL LDRD funds very important with BNL R&D funds Will design bus and flex cables with conventional, widely available line width Bump bonding within existing industry standards Management Plan is taking shape Cost Basis is maturing Construction Schedule points to FY 2011 as data run