Update of Booster Alignment & Magnet Moves February 20, 2013 Bill Marsh, Kiyomi Seiya, Dean Still, Kent Triplet Alex Waller.

Slides:



Advertisements
Similar presentations
PIP and the Booster Notch Bob Zwaska October 12, 2011 PIP Meeting.
Advertisements

C and S band BPM system update A. Aryshev, S. T. Boogert, S. Molloy, C. Swinson 5/25/20151ATF2 Software meeting.
University of Dortmund Marc Grewe, IWBS 2004, Grindelwald, CH 1/21 Orbit Correction Within Constrained Solution Spaces.
Beam Based Survey and Alignment of Ring Magnets David Rubin Cornell Laboratory for Accelerator-Based Sciences and Education.
RF de-bunching problem  The Beam Phase module measures the phase of each individual bunch and makes an average that is passed to the Low Level for updating.
Booster Cogging Teststand Progress Update Kiyomi Seiya, Alex Waller, Craig Drennan August 22, 2012.
PIP Update July Agenda Summary Update – Budget/RLS – Current Activities – Upcoming Activities/ Changes Update Slides High-Power Ferrite TestingDennis.
Searching for Quantum LOVE at the Australian Synchrotron Light Source Eugene Tan On behalf of Rohan Dowd 120/10/2010Eugene Tan – IWLC 2010, Genega ASLS.
PIP Update June 25 th Agenda Summary Update – Current Activities/Updates – Ryan Crawford: Anode Supply Update – Peter Prieto: BPM Update – CY Tan:
1 BROOKHAVEN SCIENCE ASSOCIATES Commissioning Plans F. Willeke 9 th ASAC Meeting for NSLS-II Project February 1-2, 2012.
PIP Update Aug 6 th Agenda Summary Update – Current Activities/Updates – New Tuner Test Result: Reid & Slabaugh – Anode Supplies: Crawford.
Booster Cogging Upgrades Craig Drennan, Kiyomi Seiya, Alex Waller.
March 7, 2007 LET Issues (Cai/Kubo/Zisman) Global Design Effort 1 Low-Emittance Tuning Issues and Plans Yunhai Cai, Kiyoshi Kubo and Michael S. Zisman.
PIP Update Feb 20 th Agenda Summary Update – Current Activities/Updates – Startup Schedule Highlights – Upcoming Talks, Reports, Meetings Updates/Talks:
Y. Ohnishi / KEK KEKB LER for ILC Damping Ring Study Lattice simulation of lattice errors and optics corrections. November 1, 2007 Y. Ohnishi / KEK.
F Antiproton Source Apertures Steve Werkema DOE Tevatron Operations Review March 22, 2006.
FLS2006 Workshop, HamburgEduard Prat, DESY DISPERSION MEASUREMENT AND CORRECTION IN THE VUV-FEL (FLASH) Winni Decking, Torsten Limberg, Eduard Prat 37th.
G 0 Coordinator Update & “To-Do List” Joe Grames William & Mary, June 5-6, 2006  Hall C Beam Line Tasks  Accelerator Preparation Tasks  Beam Halo 
Energy Spectrometer for the ILC Alexey Lyapin University College London.
ATF DR Overview Introduction Low emittance history Present status S.Kuroda ( KEK ) GDE Review 3rd Apr.2013.
EMMA Horizontal and Vertical Corrector Study David Kelliher ASTEC/CCLRC/RAL 14th April, 2007.
SPS re-commissioning with beam K. Cornelis PS-SPS days.
‘BBA’ Goals Understand BPM performance –validate use for precision optics tests –justify & specify hardware/software upgrades Beam – Based ‘Alignment’
Booster Beam Notching Installation Update PIP Talk Salah Chaurize February 20, 2013.
Booster Acceptance, Apertures, and Alignment Kiyomi Seiya Proton Source WorkshopDecember 07, 2010.
Booster Alignment & Magnet Moves Kiyomi Seiya. Aperture scan B75 : Aperture scan program with new corrector Kent Triplet, Alex Waller BPM data from B40.
Managed by UT-Battelle for the Department of Energy Using Online Single Particle Model for SNS Accelerator Tuning Andrei Shishlo, Alexander Aleksandrov.
PIP Update July 30 th Agenda Summary Update – Current Activities/Updates – Project Controls Update: K. Domann – Linac Lattice – Valeriy Kapin.
Low emittance tuning in ATF Damping Ring - Experience and plan Sendai GDE Meeting Kiyoshi Kubo.
Plan in summer shutdown Magnet -SF1FF -Swap of QEA magnet - Multipole field of Final Doublet IP-BSM improvement.
Vertical Emittance Tuning at the Australian Synchrotron Light Source Rohan Dowd Presented by Eugene Tan.
Proton Plan PMG 9/27/07 E Prebys 1 Proton Plan Status Eric Prebys.
Proton Improvement Plan Bill Pellico April 19, 2013 NOvA collaboration Meeting Bill Pellico NOvA.
1 Alternative Bunch Compressor 30 th Sep KNU Eun-San Kim.
Recent Work Towards Increasing the AP2 & Debuncher Aperture – Keith Gollwitzer – May 9, Recent Work Towards Increasing the AP2 & Debuncher Aperture.
Preparation Status of pp Run11 Haixin Huang Time Meeting 12/21/
Booster Losses Keith Gollwitzer PIP and MI 700 kW review January 2015.
Antiproton Acceptance Keith Gollwitzer Dept. of Energy Review March 30, 2005.
PIP Update June 18 th Agenda Summary Update – Current Activities/Updates – Reid, Slabaugh.
Craig Drennan Linac and Booster Beam Diagnostics Proton Source Workshop December 7 and 8, 2010.
SLAC ESA T-474 ILC BPM energy spectrometer prototype Bino Maiheu University College London on behalf of T-474 Vancouver Linear Collider.
DMS steering with BPM scale error - Trial of a New Optics - Kiyoshi Kubo
Booster corrector measurement QA Phil Schlabach 1 May 2007 Proton Source Magnet Meeting.
Orbit related issues of the spin tune control at RHIC V.Ptitsyn, M.Bai, W.MacKay, T.Roser.
Craig Drennan Linac and 400 MeV BPMs January 7, 2011.
RHIC CNI Polarimeter status RHIC CNI Group February 26, 2008.
1 1 Orbit Response Update 30September 2010 Jeff Rzepiela Update 9/30/10 J. Rzepiela Orbit Response Measurements.
Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before.
PIP Update Jan. 16 th Agenda Summary Update – Current Activities/Updates – Shutdown ScheduleHighlights – Upcoming Talks, Reports, Meetings Updates/Talks:
Brief review of past studies on Wakefield ATF2 Proj. Mtg K.Kubo.
PIP Update March 6 th Agenda Summary Update – Current Activities/Updates – Startup Schedule Highlights – Upcoming Talks, Reports, Meetings Updates/Talks:
RHIC Status April 8, 2011 RSC Meeting Haixin Huang.
Workshop on Accelerator R&D for Ultimate Storage Rings – Oct Nov.1 – Huairou, Beijing, China A compact low emittance lattice with superbends for.
09/21/07Shutdown’07 Week 7 F.G. Garcia1 MTA beam line installation Weekly Report September 21, 2007 Period covered: September 14 th September 21 th (Week.
Wakefield effect in ATF2 Kiyoshi Kubo
Antiproton Acceptance Steve Werkema DOE Review February 24, 2004.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
8 th February 2006 Freddy Poirier ILC-LET workshop 1 Freddy Poirier DESY ILC-LET Workshop Dispersion Free Steering in the ILC using MERLIN.
LHC Collimation Working Group Monday, 21 March 2016 Analysis of collimator BPMs in the 2015 run A.Valloni, G. Valentino with input from R. Bruce, A. Mereghetti,
Ultra-low Emittance Coupling, method and results from the Australian Synchrotron Light Source Rohan Dowd Accelerator Physicist Australian Synchrotron.
ILC Main Linac Beam Dynamics Review K. Kubo.
ATF2 Status N.Terunuma, KEK
Intensity dependence of Beam size at IP and Wakefield in ATF2
For Discussion Possible Beam Dynamics Issues in ILC downstream of Damping Ring LCWS2015 K. Kubo.
Saturday 21st April 00:33 Interlock during ramp on BLM HV
Beam-based alignment measurements
Startup program, 1 Machine setup (i.e. R:\Controls\matlab\acceleratorcontrol\docs\SRSetupUsingMatlab_ALS.doc) Bergoz BPM/orbit checks: monbpms, correct.
ورود اطلاعات بصورت غيربرخط
Temperature distribution Vertical displacement
Main Linac Beam Optics and Tolerances
Presentation transcript:

Update of Booster Alignment & Magnet Moves February 20, 2013 Bill Marsh, Kiyomi Seiya, Dean Still, Kent Triplet Alex Waller

Long 7Aligned beam pipe Long 10Aligned beam pipe Long 11Aligned beam pipe Long 12kickerRotated V  HAlignment Short 12Corr. & BPMNew BPMAlignment Long 13Absorbernew Long 14BRF#1,#2Missing BRF#1 Long 15BRF#3,#4Missing BRF#3 Long 16BRF#5,#615Hz Op. cavitiesAlignment Long 17BRF#7,#815Hz Op. cavitiesAlignment Long 18BRF#19 Long 19BRF#17,#18PA SS upgrade Long 20RWM Long 21BRF#9,#10PA SS upgrade Long 22BRF#11,#12PA SS upgrade on #11 Long 23BRF#13,#14PA SS upgrade Long 24BRF#15,#16PA SS upgrade Moved components during Shutdown

VL04Replaced RF module HL10Replaced RF module HL11Found jumpers and no connection to BPMs VL11Found jumpers and no connection to BPMs HL12Replaced RF module HS12New BPM, Replaced RF module, Changed gain and offset on frontend VS12New BPM, Replaced RF module, Changed gain and offset on frontend HS23It still has issue. BPMs which didn’t work after shutdown

Aperture scan analysis: offline to online *Comparison has to be done with two software.

Aperture (90%) before and after shutdown Long Short * Assuming beam size was same. *Central position from the data after shutdown was normalized to the data before.

Aperture: Upper - Lower

#1 D F F D #2 #3 D F F D #4 #5 D F F D #6 #7 D F F D #8 #9 D F F D #10 #11 D F F D #12 #13 D F F D #14 #15 D F F D #16 #17 D F F D #18 #19 D F F D #20 #21 D F F D #22 #23 D F F D #24 +5mm -5mm 0 +5mm -5mm 0 RF Corrector FD FD Period #22 Period #23Period # mm Move1 Magnet move 2 Two magnets were realigned in Feb. 18, 2013 period 22: F-up magnet (upstream of the magnet by +1.3mm) period 24: F-up magnet (upstream of the magnet by +1.3mm)

Magnet Move Program MAD Orbit difference with the vertical alignment error. 10mm -10mm

Orbit difference before and after the magnet move

V apertires before and after the magnet move V_Long V_Short

After move2 before move2 VS22 before and after the magnet move

Plan Redo scans at 20 – 23. Measure beam size with MW. Fix BPM HS23. Move magnet