CERN, CT Workshop, ID Week, July 2 nd, 2007 Connectivity Workshop Conclusions: Lessons learned C12 Test Next future Claudia Gemme, CERN - INFN Genova Connectivity.

Slides:



Advertisements
Similar presentations
The ATLAS Pixel Detector - Introduction -
Advertisements

June 19, 2002 A Software Skeleton for the Full Front-End Crate Test at BNL Goal: to provide a working data acquisition (DAQ) system for the coming full.
1 WP 10- High Voltage ’06 March 23 rd HV Trip studies  See previous meetings for the foreseen tests on LBC44  Started late by Clermont people when Clermont.
The LAr ROD Project and Online Activities Arno Straessner and Alain, Daniel, Annie, Manuel, Imma, Eric, Jean-Pierre,... Journée de réflexion du DPNC Centre.
Atlas SemiConductor Tracker Andrée Robichaud-Véronneau.
1.ATLAS and ID 2.SCT 3.Commissioning 4.Integration 5.Latest Runs 6.Conclusions Commissioning the ATLAS Silicon Microstrip Tracker IPRD08 - Siena Jose E.
Walls crates cables gas chambers electronics CERN adb.
CFT Calibration Calibration Workshop Calibration Requirements Calibration Scheme Online Calibration databases.
ECAL status Outline: Signal cable connectors quality check results: –ADC side –PM side ECAL PM/C-W channels commissioning status Access activities Further.
Leo Greiner IPHC testing Sensor and infrastructure testing at LBL. Capabilities and Plan.
Towards a Detector Control System for the ATLAS Pixeldetector Susanne Kersten, University of Wuppertal Pixel2002, Carmel September 2002 Overview of the.
The MINER A Operations Report All Experimenters Meeting Howard Budd, University of Rochester July 8, 2013.
ATLAS Upgrade ID Barrel: Services around ‘outer cylinder’ TJF updated According to the drawing ‘Preparation outer cylinder volume reservation’
Ron Madaras, LBL U.S. Pixel Meeting, SCIPP, July 9-10, 2003 Patch Panel 1 (PP1) Brief Review Cost and Effort Estimate.
Activities Status and Plan for the week D. Giugni / INFN Milano D. Giugni Monday Meeting
LV and HV status of the RPC system RPC detector and trigger group.
Status of NA62 straw electronics and services Peter LICHARD, Johan Morant, Vito PALLADINO.
SCT Week -CERN- September 23, Defective ASIC’s A. Ciocio - LBNL.
Optoboards dependence on Temperature C. Gemme, T.Flick detector meeting, April 2 nd 2009 Motivations Test in SR1 thanks to K. Lantzsch, L.Masetti, J.Moss,
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
Commissioning of the ECAL A-side Irina Machikhiliyan, Reference data samples: #45498 PM HV nominal, LED LV = nominal, 5K of 5 TAE events, LED.
Mobile DAQ Testbench ‘Mobi DAQ’ Paulo Vitor da Silva, Gerolf Schlager.
18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page
Commissioning and Operation of the CMS Tracker analogue optical link system at TIF with CMSSW: R.Bainbridge, A.Dos Santos Assis Jesus, K.A.Gill, V. Radicci.
Ideas about Tests and Sequencing C.N.P.Gee Rutherford Appleton Laboratory 3rd March 2001.
Status of the Remote HV System 10 June 2015 TileCal week, upgrade session Roméo Bonnefoy, Romain Madar and François Vazeille ● Summary of performances.
4 th Workshop on ALICE Installation and Commissioning January 16 th & 17 th, CERN Muon Tracking (MUON_TRK, MCH, MTRK) Conclusion of the first ALICE COSMIC.
ATLAS Pixel Detector September 2003 Services E. Anderssen LBNL Service Connectivity from Module to PP1b Eric Anderssen LBNL Pixel Services Meeting, CERN.
On behalf of joint ITEP / IHEP team: A. Arefiev, N. Filimonov, T. Kvaratskheliya, I. Machikhiliyan, P. Shatalov, T. Zakoryuchkina, A. Zhokhov, S. Zvyagintsev.
LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,...
L0 DAQ S.Brisbane. ECS DAQ Basics The ECS is the top level under which sits the DCS and DAQ DCS must be in READY state before trying to use the DAQ system.
IDE DCS development overview Ewa Stanecka, ID Week, CERN
Part I – Shifter Duties Part II – ACR environment Part III – Run Control & DAQ Part IV – Beam Part V – DCS Part VI – Data Quality Monitoring Part VII.
Overview and Status of the ATLAS Pixel Detector Claudia Gemme, CERN/INFN-Genova on behalf of the ATLAS Pixel Community 10th ICATPP Conference, Como, Oct.
ROBOX with Multi Anode PMT’s Status and plans A.Mestvirishvili, I. Schmidt, S. Sen, F. Ozok University of Iowa.
S.MonteilCOMMISSIONING1 PS/SPD ELECTRONICS OUTLINE 1)STATUS OF PS/SPD FE BOARDS PRODUCTION 2)PHASES OF PS/SPD COMMISSIONING 1)LEDs AND DETECTORS 2)TUBES.
CERN, CT Workshop, ID Week, July 2 nd, 2007 Problems and solutions during the integration. Unconformities in the detector Claudia Gemme, CERN - INFN Genova.
MINERvA Status Report Deborah Harris, Gabe Perdue, Kevin McFarland, Jorge Morfin October 15, 2009.
1/5 ECAL/HCAL Front-end status Calorimeter Meeting Frédéric Machefert Wednesday February 9 th, 2011.
TB Peter Glässel, Heidelberg1 TPC Status Report Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel, Heidelberg.
PS VFE & PS/SPD FE Electronics Status and Plans 16 January 2008 LPC Clermont.
1 Calorimeters LED control LHCb CALO meeting Anatoli Konoplyannikov /ITEP/ Status of the calorimeters LV power supply and ECS control Status of.
9/17/2008TWEPP 2008, R. Stringer - UC Riverside 1 CMS Tracker Services: present status and potential for upgrade Robert Stringer University of California,
Status of Muon Activities W.Baldini, N. Bondar, O.Maev, B. Schmidt LS1 Meeting Dec. 20-rd 2013.
H. MatisSTAR Inner Silicon Tracking Detector Review – July 8, SSD software and hardware maintainability Howard Matis.
STAR Pixel Detector readout prototyping status. LBNL-IPHC-06/ LG22 Talk Outline Quick review of requirements and system design Status at last meeting.
HBD Report Craig Woody BNL DC Meeting January 7, 2009.
SPD VFE installation and commissioning (status and plans) I.Summary of VFE installation II.Stand alone VFE test: noise & offset III.Stand alone test: LED.
Status of the PSD upgrade - Status of the PSD cooling and temperature stabilization system - MAPD gain monitoring system - PSD readout upgrade F.Guber,
Calorimeter global commissioning: progress and plans Patrick Robbe, LAL Orsay & CERN, 25 jun 2008.
Opto temperature experience in the Pixel detector C. Gemme IBL meeting, 17 March 2009.
1 ECS CALO LED Control System CALO Piquet Training Session Anatoli Konoplyannikov /ITEP/ Outline  Introduction  Calorimeter ECS LED monitoring.
 94 LVPS Packages mounted 4’-25’ from the front-end electronics.  4 modules per package. u +5V& -5V “Digital”, +5V & -5V “Analog” 18 A 1A 18A 18Amps.
Piquet report Pascal, Yuri, Valentin, Tengiz, Miriam Calorimeter meeting 16 March 2011.
Cables Ian Crotty 8 May 2012 Cables for the RE4 Upscope in CMS News. The HV cables are in the Integration DB (INB/904) The Hv order is confirmed. Need.
SiW ECAL: the status before Fermilab Marcel Reinhard LLR – Ecole Polytechnique CALICE caollaboration meeting 18/03/08, Argonne.
1 4 July 2006 Alan Barr - SCT DAQ Experience and plans from running the (SCT) DAQ at SR1 HEP Cosmics setup Running modes Problems Future.
Plans for the 2015 Run Michal Koval, Peter Lichard and Vito Palladino TDAQ Working Group 25/3/2015.
E.Gushchin,S.Filippov(INR,Moscow) 16 April 2008Calo commissioning meeting CERN PS/SPD LED monitoring system status General status LED signal is used for.
RF Commissioning D. Jacquet and M. Gruwé. November 8 th 2007D. Jacquet and M. Gruwé2 RF systems in a few words (I) A transverse dampers system ACCELERATING.
Calorimeter Cosmics Patrick Robbe, LAL Orsay & CERN, 20 Feb 2008 Olivier, Stephane, Regis, Herve, Anatoly, Stephane, Valentin, Eric, Patrick.
2 March 2012Mauro Citterio - SVT Phone meeting1 Peripheral Electronics Some updates Mauro Citterio INFN Milano.
Straw Working group Ferrara 4/9/2014. Outline Status and Plans Installation of Chambers 1-3 Chamber 4 Vacuum test SRB Readout, monitoring and software.
PIXEL 2000 P.Netchaeva INFN Genova 0 Results on 0.7% X0 thick Pixel Modules for the ATLAS Detector. INFN Genova: R.Beccherle, G.Darbo, G.Gagliardi, C.Gemme,
LKr status R. Fantechi.
- STT LAYOUT - SECTOR F SECTOR A SECTOR B SECTOR E SECTOR D SECTOR C
Services – First Considerations Sigi Wenig / Nicolas Massol ATLAS Tracker Upgrade Workshop Valencia December 2007 Existing services (in cryostat.
Monitoring system commissioning
US Module Testing Progress Report
Presentation transcript:

CERN, CT Workshop, ID Week, July 2 nd, 2007 Connectivity Workshop Conclusions: Lessons learned C12 Test Next future Claudia Gemme, CERN - INFN Genova Connectivity Workshop Conclusions: Lessons learned C12 Test Next future Claudia Gemme, CERN - INFN Genova

2 2 First SQP (C34) was shipped to SR1 from Bat 154 on 22 Feb. The Connectivity Test was an effort that a large part of the Pixel community supported for more than 3 months, involving many people from DAQ, DCS, mechanics, optolinks experts other than the CT crew itself (11 shifters). Operation required 7 days week and long working hours to fit the schedule; DAQ and DCS permanently on call -> and quite unusually we finished perfectly in time! Other than testing and qualification of the Pixel Package, an important and not secondary outcome is that many people were involved in the actual running of the detector and now know how to basically control DAQ, DCS and the detector itself.

3 3 Test on the first SQP C34Inner started indeed 28 Feb! Up to 21 Mar we work to test and improve our tools: Sequence of tests and integration Test optoheaters Test sense lines SIT mapping Optolink fiber mapping Database issues… -21!! Test of A34 started on 22 March with much better tools. With red arrows the most problematic SQPs. On A34 we had to give up and we tested it again at the end of the integration.

4 4 Lessons learned: Hardware Mapping MT16/MT8 mapping from PP0 to PP1: it was not completely traced in 154 and not included in any database that routed directly from PP0 to BOC plugin. Based on the measured connectivity we did, we are now starting the fiber allocation in the pit crates. Detector final mapping has few unconformities with respect to the original mapping. This is the starting point for the detector services. Failures in the type 0 cables were not where we expected to find them -> fine for the future. Higher sense lines resistance in L2 cables have been fixed but it could be a on-going process. Experience in debugging problems has greatly increased during testing time as the system knowledge was increasing. For instance: to fix the ROD problem (no DCI in one channel) it took three SQPs! debug of no PIN current in the optoboard has now a more clear debug procedure.

5 5 Optoboards operation Optoboards have been tuned relatively easily: the boards selection in 154 has improved since the system test and they were running rather hot (25-35C). Gained significant tuning experience at 40Mbit/s, 80Mbit/s, and 160 MBit/s and developed software to deal it. Extensive comparison of clocked opto-link (Fast) versus short pseudo-random sequence (Slow): some indication of “slot turn- on” effects seen and correlated with 154 measurement -> see Beate’s talk. But no problem in operation. No full optoboard failure but unexplained death of one PIN channel (never observed before) and VCSEL (one failure in 154) No hints of CommonSeriesResistance aging process.

6 6 Some additional problems observed occasionally in module digital scans are not yet fully understood, (see Andreas’s talk) but appear un-related to opto-link parameters. We succefully operated 20 RODs in 2 crates. Full parallelization was not possible only because the detector had no cooling but it has been proved to be possible.

7 7 Lessons learned: software We have done big improvements in DAQ during the Connectivity Test (see DAQ session): DAQ-DCS-Communication was extensively used CoralDb/Oracle connectivity database Module configuration in RootDB Machinery to create the xml files for the SIT mapping CT code However online analysis was poor and we needed to check summary results by eye. Output file format has been fixed only at the 5 th SQP as code and procedure kept having major updates since then. The main problem was that we had to manage two opposite needs: testing the detector in time for the installation (need a stable code and a stable procedure) and develop the code to more stable/efficient releases. The result was often confusing.

8 8 C12 test in SR1 This was a realistic test of connections (electrical, optical and cooling) of PP1 region using C12 quadrant. Setup of “dummy PP1 region” at C-side of DST, near System Test services Mock up approximate geometry of nose region, and bundle SR1 System Test cables as done on the flange in the pit. Full report of the 5 working days by Maurice on the detector e-log Test done at any stage: Type 1 cable in panels While connecting Type 2 cables After fiber connection

9 9 Unfolding electrical services First step is unfolding of electrical services to form PP1b using corrugated panels. This was more complicated than expected and took 2 days to find an optimal solution. 1. Cut back of outer panel to allow routing cables to the back of the nose 2. Shifted all connectors on rows 1 and 5 towards cable source in order to have the empty slot (these rows always have an empty) in the longest cable position. 3. Left-right swapped outer panel connector pairs whenever is possible to match what was erroneously done in the pit with the PP2 cables (already dressed). Only 3 pairs need to be handled by crossing PP2 cables. This solution seems fine for the pit even if any quadrant may be slightly different. Estimate in UX15 is roughly one day per octant.

10 Whenever all the type 1 cables were allocated in the corrugated panel, a test was performed to verify the connections. The most fragile parts are the solderings on the penetration cards that should be better fixed while cabling. LV Type1 cables were tested with the Keithley sense setups (it is a complete check). NTC were tested by using Type2 cable of the bistave setup as it was available. This will not be possible in the pit. HV Type1: No test.

11 Connection of Type 2 cables Type 2 cables were bundled and routed as on flange as it is in the pit. Same “dummy” heaters were used to define a safe envelope around where real heaters will go. Some preliminary electrical tests have been done during the connection. It is important to know at this stage if the match is right and the connection is working. NTC: check NTC are all connected. Switch on Viset and Vpin (we will try to inject light at PP1 to measure some PIN current). OptoRST not measurable. We did it by eye with the FSM panels but we will do it as a Phase1 test. HV: switch on high voltage and measure currents (we could ramp to 600V) LV: run a phase1-no opto.

12 We have just realized that connecting by row (NTC first, the HV, last LV) is not easy and we will connect by position. LV can be tested only if ‘their’ NTC is already plugged in.

13 Connectivity Test Bucket was removed and fibers plugged in (but not routed in the proper place). Fibers run at smaller radius than Type 2 cables. Both cables and fiber will be trapped by pipe connections.

14 Connectivity Test For the full qualification of the cable connection, fibers are needed. The proposed test is: Phase1 i.e. measure voltages, currents and temperatures of modules and optoboards. It checks also that the TTC fibers are fine as measures the PIN current and the presence of clock in the modules. Phase2: link test or power measurement to check that the DATA fibers are fine. FastTuning in the pit. Phase3 Threshold scan to measure noise for few pixels in each module to be sure that the HV is provided to each sensor. BOC setting obtained during the CT were used. It took less then 6 hours to run the CT on C2 (18 boards)

15 Next future Unfolding services will start next week and wiil take four weeks. Maps have to be prepared to plug type 1 cables in the corrugated panels following the experience of C12 mockup. Due to the big delay between the unfolding and the connection of type 2 cables (October?), we will certainly be interested to know something more on the status of the detector. So we expect to run, other than the sense test to check the LV cables, some more test on the NTC and on the HV. Then we will have time to prepare the connectivity test with the final services, optolinks, DAQ and DCS better support to operate the detector for the first time.