Entry Capacity transfers in the constrained period Transmission Workstream 5 th October 2006.

Slides:



Advertisements
Similar presentations
UK Gas Entry Regime – Review of existing Interruptible Arrangements & Potential Reforms for this Winter.
Advertisements

Information Transparency Proposal Transmission Workstream 2 nd November 2006 Presentation by Abid Sheikh, energywatch and Angela Love, Poyry Energy.
Trades and Transfers Activity to Date. 2 Introduction  Trade and Transfer functionality added to RMSEC auction (renamed RMTTSEC) from July, applying.
Entry Capacity Buy Backs Feeder 7 Shutdown July 2006 National Grid NTS Dave Adlam 3 August 2006.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Long Term Entry Capacity & User Commitment Transmission Workstream 7 th August 2008.
Discretionary Release Interruptible Entry Capacity 1st November 2007.
Moving the QSEC and AMSEC Auctions National Grid NTS, Transmission Workstream.
Capacity trade and transfer mechanism and the next AMSEC auction Nienke Hendriks Head of Gas Transmission Policy, Enforcement and Compliance 9 May 2007.
European Transparency Requirements – Draft Mod Transmission Workstream 4 th September 2008.
Transfer & Trades Special Transmission Workstream
Further consultation on NTS entry baselines Nienke Hendriks Head of Gas Transmission Policy, Compliance and Enforcement 14 August 2007.
RMTTSEC – Rolling Monthly Trade and Transfer System Entry Capacity Auction Transmission Workstream, 2 April 2009.
The Entry Capacity Transfer & Trade Methodology Statement Transmission Workstream
Entry Capacity Substitution Workshop 8 – 7 th April 2009.
Transfers and Trades Transmission Workstream
Discretionary Release of Non Obligated NTS System Entry Capacity Transmission Workstream 1st May 2008.
Classification: Statoil Internal Status: Draft Mod 156/156a Questions regarding the proposals…
Medium-term TEC Trading ARODG Seminars Glasgow & London February 2007.
Third Workstream meeting re Baseline Re-consultation and Substitution 12 September 2007.
1 Allocation of Baseline Reduction in the Substitution Methodology Draft Presentation aimed for 11 th June Substitution Workstream John Baldwin Gas Strategies.
Update on Entry Capacity Substitution Transmission Workstream 6 th March 2008 Summary of consultation responses.
A GAS FLOW MODEL FOR THE NTS NETWORK MELVIN BROWN CLAUDIA CENTAZZO JOGT Meeting, London, 5 June 2008.
Entry Capacity Substitution Workshop 2 7 th May 2008 Substitution Example.
Force Majeure - Capacity Transmission Workstream 2 July 2009.
Mod 166 Review Group Incremental Exit Capacity at New and Existing Exit Points.
Review Group 221: Option 3 – security provided after allocation.
Open letter on Development of the regime ahead of winter 2007/8 Nienke Hendriks Head of Gas Transmission Policy, Enforcement and Compliance 28 June 2007.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Initial Thoughts on the Release of Non Obligated NTS System Entry Capacity Transmission Workstream 3 rd April 2008.
Capacity Methodology Statements Transmission Workstream 5 th July 2007.
Optimisation of Entry Capacity Strawman Transmission Workstream 4 th May 2006.
Entry Capacity Substitution Workshop 3 11 th June 2008 Substitution Example.
15 February 2006 TPCR second consultation: gas offtake Offtake Arrangements Workstream 15 February 2006.
Entry Capacity Trading Transmission Work Stream, 5 April 2007.
Fundamental review of entry charging principles UNC Transmission Workstream - 6 th August 2009.
Transmission workstream 6 April Overview of TPCR Third Consultation UNC transmission workstream – 6 April Mark Feather.
Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight.
Supply Assumptions for Investment Planning Transmission Planning Code Workshop 1 3rd April 2008.
Entry Capacity Substitution Workshop 4 9 th July 2008 Entry Capacity Substitution Methodology Statement: Discussion Paper.
“Amendment of Network Entry Provisions at the European Interconnector NTS sub- terminal at Bacton" Transmission Workstream 1 st December 2005.
Proposal to adjust investment lead times Transmission Workstream 4 th May 2006.
Review Group -140 Thoughts on additional information requirements.
DRSEC Update Transmission Workstream 06 November 2008.
Trades and Transfers Workshop, 6 th November 2007.
Mod Entry Capacity Transfers Transmission Work Stream, 5 April 2007.
Transfers and Trades Special Transmission Workstream
Force Majeure Existing FM situation: Up to 200GWh/d capacity shortfall due to the rejection of NG’s planning application for a PRI in Corse / Tirley area.
Entry Capacity Overrun price calculation
Transmission Workstream, 01 October 2009
Non-approved draft Transmission Workstream, 6th December 2007
Transmission Workstream, 2nd March 06
DRSEC Update August 4th 2009.
Capacity Methodology Statements: Impact of Mod 452
Action from Workshop 3 – SUB010
Capacity Methodology Statements
Background to National Grid’s Baseline analysis
Development of Entry Capacity Substitution
Long Term Non Firm Capacity Update
Review of Trade and Transfer Winter 09/10
Entry Capacity Transfer and Trade
Baseline Re-consultation
Modification Proposal 0133 – “Introduction of AMTSEC auction”
Optimisation of Entry Capacity Modification Proposal
Information Provision for Transitional Exit Capacity
CAM: Next Steps UNC Transmission Workgroup Lisa Martin 9 January 2014.
Transmission Workstream 1st February 2007
MOD 501 Update.
Entry Capacity Transfers - Constrained Period
Transmission Workstream 05 November 2009
Presentation transcript:

Entry Capacity transfers in the constrained period Transmission Workstream 5 th October 2006

Entry Capacity transfers in the constrained period  Based on allowing transfer of capacity between interacting ASEPs  Transfers take place within zones on a 1:1 basis  Capacity transfer allows ASEP capability to transfer  Monthly Capacity made available through a new auction  AMTSEC  Subject to a Nodal maxima  Industry concerns  Doesn’t go far enough  Sterilisation of Entry Capacity  Agreed to further explore the possibility of transfers across zones

Transfers between zones  How can this be achieved  Earlier workstream presentations suggested this could be done through;  Commercial exchange rates  Buyer covers the incremental cost of transferring capacity  Physical exchange rates  Exchange rate factors in likelihood of constraints  Is it possible to allow transfers between Zones that are adjacent and have ‘some’ physical interaction  ASEPs with no physical interaction  ASEPs with limited/variable physical interaction  ASEPs with a strong physical interaction

Physical exchange rates  Transfers between ASEPs with no physical interaction  Does not allow transfer of physical capability  Any transfer would be using existing headroom (if any) near recipient ASEP or creates incremental risk at recipient ASEP.  Therefore no exchange rate available

Physical exchange rates  Transfers between ASEPs with limited/varying physical interaction  Physical interaction only comes into play when capacity transfer reduces flows at the Donor ASEP  Physical interaction limited by configuration of Network  Multi junction  Compressors  Therefore possible for ASEPs in close proximity to have no / minimal transfer of capability as a result of a request to transfer capacity.

Capacity Exchange rate

Physical exchange rates  Certain ASEPs have a 1:1 exchange rate  Share common areas of pipeline and/or junctions  Highly interactive  If 1 unit of flow decreases at one ASEP then 1 unit of additional flow would be allowed at interacting ASEP  Basis of grouping ASEPs into zones

Zonal definition  Zonal Definition  ASEPS placed within the same zone if;  Share common areas of pipeline and multi junctions  Highly interactive  If 1 unit of flow decreases at one ASEP then 1 unit of additional flow would be allowed at interacting ASEP

Teesside Hatton Barrow Theddlethorpe Easington Carnforth Bishop Auckland Bacton Burton Point Alrewas Asselby Wisbech Peterborough Warrington Garton NTS Schematic – Easington Area Scunthorpe Hornsea

Multiple Transfer requests  Provision of certainty to Users of applicable exchange rates  Prior to participation in an auction to enable transfer of unsold capacity;  Uncertainty around demand for capacity in forthcoming auction  Uncertainty around whether Users would secure the capacity to enable the transfer to take place.  Exchange rate may change after the auction.

Multiple requests Baseline Capability Transfer request 10 Units Capacity Exchange rate 2:1

Multiple requests Baseline Capability Transfer request 10 Units Capacity Exchange rate 4:1

Multiple requests Baseline Capability Transfer request 10 Units Capacity Exchange rate 0

Alternative proposals  Unsold Capacity  Provide wide range of exchange rates  ‘Lock in’ Users to transfer request  Sold Capacity  First come first served

Way forward  Modification Proposal to go to October Mod Panel?  Does Proposal meet the relevant objectives?  Is the Proposal sufficiently developed?  Is it worthwhile proceeding with Proposal?