May14, 2010 RPG Meeting Houston Import Study Update Jeff Billo.

Slides:



Advertisements
Similar presentations
RPG: September 24, Approach for ERCOT Independent Review of the 2013 Houston Import Project Jeff Billo, Manager, Transmission Planning September.
Advertisements

October 16, 2009 RPG Meeting ERCOT RPG Project Review Update Jeff Billo.
Regional Planning Group Project
NTTG Economic Study and Biennial Study Update NTTG Economic Study and Biennial Study Update NTTG Study Cycle.
Houston Import Evaluation Cross Texas Transmission & Garland Power & Light ERCOT RPG Meeting August 27th, 2013.
KURTEN SWITCH PROJECT (BRYAN/ COLLEGE STATION AREA UPGRADES) Technical Advisory Committee December 1, 2005 Transmission Services.
Houston Region Import Capacity Project August 27, 2013 Regional Planning Group Meeting.
Navarro to Houston Presentation to ERCOT RPG August 27, 2013.
January 5, 2012 TAC Cross Valley 345 kV Project Jeff Billo Manager, Mid-Term Planning.
BRAZOS ELECTRIC COOPERATIVE Dobbin 345 Project David Albers, P.E. Manager – System Planning.
Valley Import Overview Jeff Billo Regional Planning Group Meeting July 22, 2014 Preliminary1.
ERCOT PUBLIC 8/19/ LTSA Scenario Results Updates August, 2014.
ERCOT PUBLIC 4/22/2014 Updates for 2014 LTSA Scenario and Data Assumptions 4/22/2014.
Jan 13, 2012 RPG Meeting El Campo – Vanderbilt 69 kV Project – Status report Ehsan Ur Rehman Planning Engineer ERCOT.
Long Term Study Task Force Update to ETWG ERCOT Long-Term Study: Scenarios, New Software, and Emerging Technology Assumptions January 27, 2012.
Valuing Economic Benefits from Transmission Planning ERCOT System Planning March 22, 2006.
Houston Area Dynamic Reactive Project March 11,
JACKSBORO TO WEST DENTON 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
Warren Lasher Director, System Planning October 4, 2014 Our Energy Future.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
NRG Comments/Concerns with HIP Assumptions January 21, 2014 RPG Meeting NRG Comments/Concerns with HIP Assumptions - January 21, 2014.
April 16, 2010 RPG Meeting ERCOT Five-Year Transmission Plan Update Jeff Billo.
RPG Meeting Five Year Plan Extension Brad Schwarz.
1 WMS Report To TAC September In Brief Four Working Group Reports Four Working Group Reports One Task Force Report One Task Force Report Three.
John Dumas Director of Wholesale Market Operations Jeff Billo Manager of Mid Term Planning Dan Jones Director with Potomac Economics, the ERCOT IMM Board.
June 19, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
October 16, 2009 RPG Meeting ERCOT 2009 Five-Year Transmission Plan Update Jeff Billo.
Proposed North – South Congestion Mitigation Plan Luminant Energy July 2008.
Economic Planning Criteria Question 2 1/7/2011 Joint CMWG/PLWG Meeting March 4, 2011.
March 13, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
December 7, 2012 Transmission Needs Analysis Scenario 5/7 Update.
Jones Creek Project Submitted to RPG on July 7, 2014 July 22, 2014 Regional Planning Group Meeting.
Ramping and Demand Shifting: A Case Study Tim Mount Dyson School of Applied Economics and Management Cornell University Demand Response.
Dale Osborn Midwest ISO October 13, 2008 EE 590 Transmission Planning with Significant Energy Resources.
WEST LEVEE TO NORWOOD 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
April 16, 2010 RPG Meeting Lamesa Area Upgrades ERCOT Independent Review Jeff Billo.
2008 Annual Five Year Plan Update 2 10/12/2007 Regional Planning: Jay Teixeira, Harry Liu, Brad Schwarz, Jeff Billo, Chris Ngai.
OFFSHORE WIND CONNECTION & COSTS Mary Doswell Alternative Energy Solutions December 7 th, 2010.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX.
TAC02/01/2007 DW 1 TAC Briefing on: - Report on Constraints and Needs: Five Year Plan Development - Long Term System Assessment (LTSA) - Entergy Integration.
SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.
Jesus A. Guerra, P.E. Distribution System Reliability CenterPoint Energy SWEDE 2011.
ERCOT TAC11/2/ CREZ Study Update ERCOT TAC 11/2/2006.
February 13, 2009 RPG Meeting ERCOT System Development Update Jeff Billo.
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
ERCOT Independent Review
October 16, 2009 RPG Meeting ERCOT Independent Review of the Corpus Christi Improvements Project Jeff Billo.
RPG: September 24, Long-Term System Assessment Introduction Jeff Billo, Manager, Transmission Planning September 2013 Regional Planning Group.
3/28/2008 RPG CREZ Meeting CREZ Transmission Optimization (CTO) Study And The Oscar Goes To… Warren Lasher Manager, System Assessment.
September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning.
OPSTF – Issue 7 Long-term unavailability of autotransformers.
Panhandle Renewable Energy Zone (PREZ) Study
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
Transmission Services Report: North and West RPG Projects Bill Bojorquez TAC July 7, 2005.
December 14, 2007 RPG - CREZ Meeting CREZ Transmission Optimization Study: Update Warren Lasher ERCOT System Assessment.
2006 Reliability Study James Manning Bryan Guy May 12, 2006.
June 11, 2010 RPG Meeting Houston Import Study Update Jeff Billo.
Response to TAC Questions on PGRR031 TAC– January 28, 2014 Jeff Billo, ERCOT 1.
03/06/2008 TAC CREZ Transmission Optimization (CTO) Study Update Dan Woodfin Director, System Planning.
2016 LTSA Update Doug Murray 6/21/2016. Agenda Introduction Scenario Retirement Process Scenario Summary Results Appendix.
2008 Annual Five Year Plan Update 4 For RPG-CREZ Meeting 12/14/2007 Department of Regional Planning Harry Liu.
Houston Import Project – ERCOT Independent Review
ERCOT – LP&L Study Status Update For Regional Planning Group Ben Richardson March 22, 2016.
Northern Tier Transmission Group Report to Columbia Grid Planning Committee February 9, 2012 “To ensure efficient, effective, coordinated use & expansion.
Houston Import Study Update
Freeport Area Master Plan Project -
Transmission Planning in ERCOT- Overview
Barrilla Junction Area Transmission Improvements Project
ERCOT 2009 Five-Year Transmission Plan Update
Warren Lasher Manager, Long-Term Planning and Policy
Presentation transcript:

May14, 2010 RPG Meeting Houston Import Study Update Jeff Billo

2 RPG Meeting May 14, 2010 Houston Import Study Assumptions Study Assumptions –Base case = YTP 2014 Economic Case Includes YTP projects identified for 2014 Includes all CREZ transmission facilities Does not include additional CREZ generation –Analysis will focus on economic benefit of additional import capacity into Houston area per ERCOT RPG Charter and Procedures Section 3.3 UPLAN Assumed load can be served reliably without additional import capability, but additional import project may allow reliability criteria to be met at a lower overall cost –$2.5 M/ mile 345-kV double circuit cost

3 RPG Meeting May 14, 2010 Approach Base Case BC + CREZ Generation BC + STP 3 & 4 BC + STP 3 & 4 BC + New Gas Gen North of Houston BC + New Gas Gen In Houston BC + Load Variation Bulk of analysis will focus on the base case. Options may be eliminated at this stage. Alternate scenarios will be used to quantify relative merit of options that pass first stage. Final recommendation will be selected. Sensitivity scenarios will be run for recommended option and results added to report. BC & $3.34M/ mile 345-kV cost BC + $4 gas/ $10 gas BC + New SGIAs

4 RPG Meeting May 14, 2010 Houston Import Study Options 1Lufkin-Canal 345-kV double circuit 2Salem-Zenith 345-kV double circuit 3Fayetteville-Zenith 345-kV double circuit 3AFayetteville-Zenith 345-kV double circuit w/ 30% series comp 4Gibbons Creek-Zenith 345-kV double circuit 6Fayetteville-Obrien 345-kV double circuit 6AFayetteville-Obrien 345-kV double circuit w/ 30% series comp 9Gibbons Creek-Salem-Zenith 345-kV double circuit 12Gibbons Creek-Salem/ Fayetteville-Zenith 345-kV double circuit 19Add series comp to existing Hillje-WAP and Hillje-Holman 345-kV 22Fayetteville-Zenith 345-kV double circuit w/ 50% series comp 24Option 19 + Option 22 J1Sandow-Zenith 345-kV double circuit J1ASandow-Zenith 345-kV double circuit w/ 30% series comp J2Marion-Holman-Obrien 345-kV double circuit J3Hillje-Obrien 345-kV double circuit DCBrown-Zenith 3000 MW HVDC line DC2Scurry-Zenith 2000 MW HVDC line E1Twin Oaks-Salem-Zenith 345-kV double circuit

5 RPG Meeting May 14, 2010 Houston Import Study Options To Brown Option 1 Option 2 Option 3/ 3A/ 22 Option 4 Option 6/ 6A Option 9 Option 12 Option 19 Option J1/ J1A Option J2 Option J3 Option DC Option DC2 Option E1 To Scurry

6 RPG Meeting May 14, 2010 Houston Import Study Alternate Scenarios Narrowed to Options 3, 9, and J1 after base case analysis –Options 1, E1, and DC2 did not pass base case analysis but were further evaluated in alternate scenarios Alternate Scenarios –CREZ-level wind generation: to study effect of eventual CREZ generation build-out –STP 3&4: to study potential impact of additional generation south of Houston –Load variation (studied +/- 10% forecasted 2014 Coast wz load): low load scenario run to study extreme effect of energy efficiency, wide- scale PV installation, longer than expected economic recovery, etc.; high load scenario run to study extreme effect of quicker than expected economic recovery, long-term load growth, etc. –Gas price variation (studied +/- $3 from roughly $7 base price): to study impact of gas price on viability of various options

7 RPG Meeting May 14, 2010 Alternate Scenario Savings Results Option139J1E1DC2 Total Cost ($M)$333$175$278$253$379$923 Needed for Justification$55.5$29.2$46.3$42.2$63.2$153.8 Base Case Annual Savings ($M)$18.9$50.7$13.3$45.4$11.8$52.3$12.0$51.3$19.1$56.5$17.7$37.7 CREZ Annual Savings ($M)$12.8$148$17.1$87.5$11.2$98.7$24.9$91.9$31.6$115$77.0$171 STP 3/4 Annual Savings ($M)$6.1$19.1$5.0$4.0-$2.7$39.9$4.1$11.6-$0.3$18.5n/a Low Coastal Load Annual Savings ($M)$14.5$5.4$6.0$55.0$6.3$17.2$5.8$20.1$8.4$27.5n/a High Coastal Load Annual Savings ($M)$23.1$123$14.6$114$12.7$111$12.4$91.8$15.2$123n/a $4 Gas Annual Savings ($M)$18.3$39.5$7.3$31.6$7.5$24.8$10.8$13.3$11.8$33.7n/a $10 Gas Annual Savings ($M)$24.9$82.5$12.7$42.3$9.1$90.1$12.1$89.3$19.1$80.0n/a PC = Production Cost; ER = Energy Revenue PCERPCERPCERPCERPCERPCER

8 RPG Meeting May 14, 2010 Houston Import Alternate Scenario Results Observations –None of the projects would be economically justified in the STP 3&4 scenario –Option 3 was the only one that would be economically justified (based on energy revenue savings) in the other five alternate scenarios Conclusion –Option 3 appears to be the most viable project

9 RPG Meeting May 14, 2010 CREZ discussion Option DC2 showed significant savings in CREZ scenario Further investigation into difference between Options 3 and DC2 in CREZ scenario –Option DC2 relieved North-Houston congestion and West export congestion Several small projects may be implemented in north and near Kendall with Option 3 to get similar level of savings for much lower overall cost Hicks project from YTP not originally in base case was added –Reduced congestion in benchmark case which reduced Energy Revenue Savings for Option DC2 by $13M –Option DC2 modeling was optimistic HVDC was originally modeled as lossless –Updated model results pending Scurry Switch does not have adequate fault current for conventional HVDC –Morgan Creek may be nearest bus with adequate fault current

10 RPG Meeting May 14, 2010 Sensitivity Analysis for Option 3 Additional gas generation in Harris County –Currently 2116 MW of natural gas generation in FIS in Harris County based on ERCOT System Planning March ROS report –Analysis will model 1058 MW (50%) in Harris County at sites under study –Results: Annual PC Savings = $10.8M Annual Energy Revenue Savings = $55.4M (still enough to justify project) Additional gas generation north of Houston –Currently 2099 MW of natural gas generation in FIS in Madison, Navarro, and Freestone Counties based on ERCOT System Planning March ROS report –Analysis will model 1050 MW (50%) at sites under study –Results: Pending

11 RPG Meeting May 14, 2010 Sensitivity Analysis for Option 3 Higher transmission line cost –Used CenterPoint Energy’s original cost estimate of $3.34M/ mile –Base case results: Annual Energy Revenue Savings = $45.4M Capital Cost ($2.5M/mile) = $175M Capital Cost/Annual Savings Ratio = 3.85 (passes economic criteria) –Sensitivity results: Annual Energy Revenue Savings = $45.4M Capital Cost ($3.34M/mile) = $226M Capital Cost/Annual Savings Ratio = 4.98 (passes economic criteria) Additional SGIA –Las Brisas: 1300 MW pet coke in Nueces County –Coleto Creek 2: 660 MW coal in Goliad County –Panda Temple: ~1300 MW combined cycle in Bell County –Results: Pending

12 RPG Meeting May 14, 2010 Reliability Considerations for Option 3 Too many lines into Zenith station? –Option 3 would result in eight 345-kV lines (four importing power) in Zenith station –Preliminary analysis revealed that Zenith substation contingency (Category D) would be less severe contingency than other substation contingencies in area and less severe than what is considered to be most limiting Category C contingency Option 3 improves the import capability for these more limiting constraints –Conclusion: Option 3 does not degrade reliability for Zenith substation contingency outage Voltage Stability –Will additional import capacity cause less local generation to run and negatively impact voltage stability? –Study underway

13 RPG Meeting May 14, 2010 Houston Import Study Next Steps –Complete sensitivity scenario analysis for Option 3 –Complete voltage stability analysis for Option 3 –Finalize report in June pending above analysis results

14 RPG Meeting May 14, 2010 Questions?