SJR PRIME CORPORATION PVT. LTD. Takes pleasure in bringing you all an update on the progress for HAMILTON HOMES As on 5 th February 2016
Block – A – Norfolk – 2 nd floor bar bending is in progress.
Block – B – Cornwall – 3 rd floor bar bending work is in progress.
Block – C – Albany – Footing work is in progress.
CLUB HOUSE – Footing work completed.
Block – D – Suffolk – ground floor bar bending is in progress.
Block – E – Durham – Footing work is in progress.
Block – F – Surrey – Structure completed & 5 th floor block work in progress.
Block – G – York – Structure completed & 5 th floor block work is in progress.
Block – H – Kent – Structure completed & block work is in progress.
Block – I – Lancaster – Structure completed & 5 th floor block work is in progress.
Block – J – Nottingham – Structure completed & 5 th floor block work is in progress.
Block – K – Avon – Structure & block work completed.
Block – L – Cheshire – Structure & block work completed.
Block – M – Dorset – Structure & block work completed.
Block – N – Devon – Structure 7 block work completed.
Block – O – Somerset – Structure & block work completed.
STP work is in progress.