Transfer Line Test preparation meeting 19.11.2014V. Kain, R. Alemany.

Slides:



Advertisements
Similar presentations
Jan Uythoven, AB/BTLHCCWG, 3 May 2006 Page GeV Commissioning Machine Protection Needs to be commissioned to: Prevent damage with the used, higher.
Advertisements

1 Commissioning ABT Equipment in the LHC Jan Uythoven ABT TCM 13/01/2015.
8:16 SB 25ns dumped by RF; integrated lumi 0.6 nb-1. 9:14 BIC problem in TI8 and CMS recovering their tracker 10:09 Abort gap cleaning commissioning. 16:29.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
R.Giachino / M.Albert Be/op 5 April 2015 LHC Machine check out 1v1.
SECTOR TEST PREPARATION W. Bartmann, C. Bracco, J. Uythoven LIBD Meeting, 10-Feb-2015.
Injection test? Mike Lamont For initial discussion.
LHC 30 th and 31 st July :10 Finish scrubbing fill 25 ns trains by operator dump. –No XPOC data … 08:40 Inject for another scrubbing fill 09:09.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
Injection test1 Injection test in 2006 The installation schedule version 1.7 recently approved includes a ‘possible injection test’ - foreseen in April.
V. Kain, G.H. Hemelsoet AB/OP1Nov 08, 2007 LHC Injection System V.Kain, G.H. Hemelsoet, AB/OP Input from: E. Carlier, B. Goddard, J. Wenninger What do.
Feedback from MEF  Only possible, if COMMON COORDINATION MEETINGS  Main possible conflict: SAFETY –No “work permits” in the injectors. MEF working on.
● 08:30 Loaded by mistake squeeze function to 2 m  Dumped beams ● 10:30-13:00 Test of new algorithm for long. Emittance blow-up to minimize oscillations.
V. Kain AB/OP1Sep 12, 2007 Summary of Discussion on Injection Protection Issues Injection Protection Issues – meeting 22 nd of June V. Kain, A. McPherson,
Friday March 4 th LHC morning report the short story: from a global point of view we had basically only one access !!!
Monday h00: End of fill #1640: 3.7 pb h14: RB S12 and S23 tripped before loading rampdown table, active filter. MPE piquet. Fip_Com_Lost.
Tuesday 17 th April 04:00 Prepare second fill for v/d Meer scans. 06:22 Stable beams, v/d Meer scans for Alice and LHCb. 13:20 End v/d Meer scans.Dump.
Status of ABT beam tests preparation 9-Oct-14. Preparation of sector test without beam I MKI: – Open valves, conditioning to 55 kV, softstart – Check.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
00:15: Stable beams fill 1883, 1.1E33 cm-2s-1.  Seems the 144 bunches beam 1 doe not fit properly on the injection kicker waveform. Systematically the.
Scrubbing Run: TDI, MKI and MKE interlocks Chiara Bracco, Jan Uythoven ABT/BTP Acknowledgments: T. Baer, M. Barnes, E. Carlier.
Schedule IT General Schedule 9 th, September 09 Today.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
Overview Extraction tests: TT40 and TT60, week 21 –controls and data, interlocking, extraction, MKE6 transfer function and energy tracking, high intensity,
1 Sector Test – Preparation Layout in LSS7 Jan Uythoven (AB/BT) Thanks to Mike Lamont and the other ‘sector testers’
Last night Lhc closed 15:00 Beam on Ti 8 /Ti2 Prepulse check synchronisation ok with LHCb /RF 17:00 Open Point 4 PC’s and RF 19:00 LBDS energy tracking.
Monday 12 th November 04:50 Beam dump, trip of RF line 4B, integrated L ~120 pb-1. Access for RF. 07:00 Injecting. FBCT phasing. Line steering. 09:59 Beam.
LHC sector test - summary 1 14/03/2008 Possible injection into part of the machine Options etc.Mike Lamont Stopping the beamStefano Redaelli Proposed Tests.
LHC progress Tuesday 28 th April 2015 Coordination: Mike Lamont, Wolfgang Hofle.
Injection and protection W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, A.Nord, J.Uythoven, J.Wenninger, OP, BI, CO, ABP, collimation,
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
Discussion and preliminary conclusions LIU-SPS dump review.
Injection status W. Bartmann, C. Bracco, B. Goddard, V. Kain, A. Macpherson, M. Meddahi, S. Redaelli, J. Uythoven, J. Wenninger LIBD Meeting, 20 th Sept.
1 TI 8 LHC SPS LSS6 IR2 TT41 LSS4 IR8 TI 2 TT60 TT40TT20 LSS2 LSS1 TT10 Mobile dump block (TED) Targets T2, T4, T6 Target T40.
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
Thursday 27 th October 00:57 fill 2257 dumped during squeeze (RQTF.A67B1) 03:52 stable beams fill #2258 4:33 Dumped, problem of LBDS dilution kicker power.
07:00 Dump fil #2219, 123 pb -1 delivered. Trim TDI parking position to +/- 55 mm in the collimator BP trimmed the temperature kicker limit to 62 degrees.
Monday 19 th March 07:33 Lost (another) beam in the squeeze, beyond 2 m, B2 hits 1/3 resonance. 08:30 Start (another) ramp  Try to correct coupling and.
AWAKE p+ beam line HWC C. Bracco, J. Schmidt Acknowledgment: MCS, EPC, MPE, SPS-OP, BI, ABP (survey),STI, EA, ACE, RP.
HiRadMat Summary of Phase-I and plans for Phase-II commissioning J. Blanco, N. Conan, V. Kain, K. Cornelis, B. Goddard, C. Hessler, M. Meddahi, C. Theis,
HiRadMat Primary Beam Overview C. Hessler, B. Goddard, M. Meddahi On behalf of the HiRadMat Primary beam line working group HiRadMat Project Review
Aperture measurements during LHC commissioning 2017
LHC Beam Commissioning Meeting V. Kain & R. Alemany
DRY RUNS 2015 Status and program of the Dry Runs in 2015
Wednesday 8.9 External crossing angles:
SPS extraction, transfer lines, injection
Saturday :12 Stable beams fill 3351 Initial luminosity
Jan Uythoven For discussion
Monday h00: Ramp 10 A/s (chromaticity, crossing angle non-closure, beta-beating): At 7m and 3.5m, put in one by one crossing angles, calculated.
Safe Injection into the LHC V.Kain AB/CO
Safe Injection into the LHC V.Kain AB/CO
Tue :25 Beams dumped due to RF vacuum interlock
Thursday morning – optics correction
LHC Injection and Dump Protection
Dry Run 0 Week 13: BI test of...everything circulating beam: all fixed displays and BI applications OP directories for 2009, concentrators running Need.
Lost at 12:05 to power converter (RTQX2.R1) problem
Saturday 2/4/ :00-09:00 Problems with SPS:
Week 35 – Technical Stop and Restart
Wire almost entirely through beam before BLM triggers dump
Yesterday morning Held 1647 for a while – SPS kicker problem
Summary Thursday h21: Stable beams fill #1303.
Aims for the week Recover from technical stop and precycle at 10A/s
Wednesday 10:00 test of the un-squeeze to 90 m at 4 TeV.
Thursday 04/11 - Morning Access until ~13:00 Pre-cycle Proton checks:
IP8 aperture measurements (07:30-10:30)
Wednesday 23/2 Thanks CRYO!!!.
Thursday Aperture studies (foreseen until ~ midday, nothing done) Problems with single bunch B2 from SPS (extraction kicker not enabled) Setting.
Wednesday 26 October 2011.
HI2011 Commissioning Status
Presentation transcript:

Transfer Line Test preparation meeting V. Kain, R. Alemany

Detailed test plan B V. Kain, R. Alemany

B1 B V. Kain, R. Alemany

B2 B1 B1B2 B V. Kain, R. Alemany ALICE SHOTS ON TED = 20 hours (TDI closed to avoid forward detectors trips) LHCb SHOTS ON TED = 18 hours Note: If 100% efficiency is assumed BLM to COLLIMATOR MAPPING  If possible will be done during aperture measurements

Total beam intensity and RP Assuming 100% efficiency and two extractions per minute of p+ (or p+ for trajectory stability) Total intensity per activity Total intensity per TED and for the whole weekend: TOT INT B1 = p+ TOT INT B2 = p+ 4.8E E+13 V. Kain, R. Alemany

In October 2004 we performed a similar test as it is planned this year for the TI2 and TI8*. With similar total beam intensities on TED. Prompt radiation: Point 2 and 8 and neighboring tunnel areas have to be closed during test. Relevant RAMSES radiation monitoring will be operational during the test. Residual radiation after test: TI tunnels: Area around TEDs will show dose rate levels being clearly above current “Supervised Radiation Area” classification. LHC tunnel: Areas in R22 and R88 located parallel to TED positions in the TI tunnels will show elevated dose rate levels. However, most probably there will be no need to change locally the current classification (Supervised Radiation Area). Prior access radiation survey will be conducted.  no access restrictions are expected after test in the LHC tunnel. *Dedicated RP report available: H. Vincke, D. Forkel-Wirth, N. Conan: Investigation of the Radiation Protection Issues of the TI8 Injection and TT40 Material Tests, EDMS: Radiological consequences arising from this test H. Wincke V. Kain, R. Alemany

Status of the systems SystemStatusComments TED TT40/TT60 movement checked TO BE DONE TED TI2/TI8 locked in beam OK MSI (TI8) and MBH (TI2) (after TEDs) condemned OK Beam Permit to TI2&TI8 TED ON GOING2 signatures missing LHCb shielding close Will be close for the weekend ALICE shielding close OK V. Kain, R. Alemany

SystemStatusComments SPS MKEOKTested during extraction test TL Power converters: magnet polarity heat run logging OK TCDION GOING: collimator movement will be checked for TI2&TI8 Application fully operational with trim. Collimator temperatures in SIS if possible LSS4/LSS6 extraction with beam OK TL BI: FBCT, BLM, BPM, BTV OKLogging, application and acquisition Which settings are foreseen?  Parking position, i.e. fully open. Only the first TCDI up stream TI2 will be moved for commissioning the automatic application V. Kain, R. Alemany

SystemStatusComments LHC MKI B1OKTested LHC MKI B2Pending LHC BIC connected only to LBDS OKBIC arming sequence: OK LHC INJECTION BICOKTested Extraction BICsOK ALICE & LHCb injection permit OKTested with handshake protocol TI2_SETUP and TI8_SETUP SPS SMPOKSBF OK LHC SMPOKOnly energy needed TDITo be doneInitial position in IP2 & IP8: In beam and tilted. The experiments could ask to open the jaws during the week end V. Kain, R. Alemany

SystemStat us Comments LHC LBDS B1OK LHC LBDS B2OK Inject and dumpOKTested fully with B1 (dump kickers and MKI pulsing) BETSimOKLock at 450 GeV SystemStatusComments SPS-LHC Rephasing and synchronization OK LHC Timing systemOK LHC Timing editorOK Dynamic destinationOK LHC Injection sequencerOK TI2&TI8 SETUP handshakeOK V. Kain, R. Alemany

SystemStatusComments IQCOn going SPS BQMOK XPOCON GOINGIt might not be ready for the TL test (not crucial) PMOK V. Kain, R. Alemany

Other topics When changing the beam intensity from PILOT to NOMINAL bunches and vice versa, we have to close the TIx_SETUP handshake and start it again. Put the new intensity in page 1 and call the experiment control room. If a patrol drops in ALICE or LHCb: 1 st call the experiment control room and the run coordinator. To broadcast the ON LINE development of the plan we will use the LHC Coordination page: webtools/vistar/vistars.php?usr=LHCCOORD V. Kain, R. Alemany