CHAMONIX XV QRL installation and first experiences of operation G. Riddone on behalf of the QRL team AT/ACR-cd Acknowledgements to AT/ACR-op and AT/ACR-in.

Slides:



Advertisements
Similar presentations
1 AFSWG Mtg 15 Aug 2003 Elwyn Baynham RAL Safety Overview Work done by RAL Group Contributors Elwyn Baynham Tom Bradshaw Iouri Ivaniouchenkov.
Advertisements

M. Jimenez AT/VAC Room Temperature (LSS) Vacuum Systems M. Jimenez.
LHC HARDWARE COMMISSIONING REVIEW May 2005 CRYOGENIC VACUUM SYSTEM Paul Cruikshank for AT/VAC.
A. Perin, CERN, TE-CRG, 26 May Review of the cryogenic by-pass for the LHC DS collimators 26 May 2011 Modifications to the DFBs, DSLC and cryogenic.
Spectrometer Solenoid Update Steve Virostek - LBNL MICE Video Conference #129 February 25, 2010.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM24 at RAL June 1, 2009.
Felix Wamers, Technical Coordination Meeting, 12 th -13 th of May CERN-GSI Technical Coordination Meeting Felix Wamers, Yu Xiang,
QRL Leak Tests the story so far………. Paul Cruikshank on behalf of TE-VSC colleagues & AL4030 Consortium (S133) 1 Paul Cruikshank TE/VSC - QRL Leak Tests.
1 Presented at ColUSM by D. Ramos on behalf of the Cold Collimator Feasibility Study Working Group Longitudinal.
Laurent Tavian Thanks to contribution and helpful discussions with M. Jimenez, V. Parma, F. Bertinelli, J.Ph. Tock, R. van weelderen, S. Claudet, A. Perin,
NED and post-NED WUT involvement NED S.C. meeting Maciej Chorowski.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
LTC Extended days, 03 March’08 J.M. Jimenez, AT Vacuum Group LHC Vacuum commissioning J.M. Jimenez On behalf of AT-VAC.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
CRYOGENICS AND POWERING
23 Jan 2007 LASA Cryogenics Global Group 1 ILC Cryomodule piping L. Tavian for the cryogenics global group.
R&D Status and Plan on The Cryostat N. Ohuchi, K. Tsuchiya, A. Terashima, H. Hisamatsu, M. Masuzawa, T. Okamura, H. Hayano 1.STF-Cryostat Design 2.Construction.
ESS Cryogenic Distribution System for the Elliptical Linac CM - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden J. Polinski.
MQXF Cold-mass Assembly and Cryostating H. Prin, D. Duarte Ramos, P. Ferracin, P. Fessia 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014.
ESS Cryogenic Distribution System for the Elliptical Linac MBL/HBL - CDS requirements Preliminary Design Review Meeting, 20 May 2015, ESS, Lund, Sweden.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
SCU Segmented Cryostat Concept M. Leitner, S. Prestemon, D. Arbelaez, S. Myers September 2 nd, 2014.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
HC review - 12 May 2005Luigi SERIO - AT/ACR/OP1 SECTOR COOL DOWN AND CRYOGENIC COMMISSIONING L. Serio.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
Introduction to LHC cryogenic system (layout, architecture) Preparation before cool-down (Purge, flushing) Transient operations to reach nominal operating.
Arnaud Vande Craen (TE-MSC) 27/02/20131 EUCARD : ESAC Review – CEA Saclay.
Cryogenic update before Fermilab meeting (and after the helium tank review) Coordination meeting 6 th May 2015 K. Brodzinski HiLumi-LHC-CC-Cryo-PPT-18_v1.
M. Karppinen TE-MSC-ML on behalf of S. Atieh, P. Cruikshank, M. Duret, J-C. Perez, V. Parma, T. Renaglia, S107, S108, Dubna teams Pressure relief valve.
05 Novembre 2003Chamonix XIV Workshop, January How to deal with leaks in the QRL and magnet insulation vacuum Paul Cruikshank for AT/VAC Germana.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
Session 6 - LHC Installation Chamonix XV January 2006 T.Pettersson EDMS: Installation – some issues.
OLAV III Experience with the LHC Insulation Vacuum System S. Blanchard, P. Cruikshank, B. Jenninger, N. Kos, W. Maan, L. Mourier, N. Provot, J. Wallner.
HC review, A. Perin, 12-MAY DFB Project LHC hardware commissioning review May 2005 Hardware commissioning of the DFBs and DSLs and connection.
L. Serio COPING WITH TRANSIENTS L. SERIO CERN, Geneva (Switzerland)
C. Garion Presentation Outline  Overview of the inner triplet interconnections  Q1/Q2, Q2/Q3 interconnections  General view  Working conditions  Compensation.
9/17/07IRENG071 Cryogenic System for the ILC IR Magnets QD0 and QF1 K. C. Wu - BNL.
Interconnection work for the the QRL cryogenic extensions Ivo Slits - AT/CRI
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel.
Cryogenics for crab cavities – SPS/LHC 2 nd HiLumi LHC meeting – Frascati (Italy) 15 November 2012 K. Brodzinski and L. Tavian on behalf of cryogenic team.
Interconnections Cryogenic Extensions and DSL Ivo Slits - AT/MCS
Special interventions Status of production and QC Nicolas Bourcey TE-MSC-MDT Fourth LHC Splice Review November 2013.
4 December 2007Sylvain Weisz - LEMIC1 Status of LHC installation.
Installation of the T600 at Fermilab CSN2, September 22,
MAGNET#1MAGNET#2MAGNET#3 SATELLITE VB#1 SATELLITE VB#2 SATELLITE VB#3 PRECOOLER#1PRECOOLER#2 DISTRIBUTION VALVE BOX DVB CP#1CP#3CP#2 BUFFER DEWAR LHe 5m.
Can we change a magnet without warming-up a full arc ? Serge Claudet, With help from P. Cruikshank & J-P. Tock (Chamonix Jan’10)
Quality Assurance Overview Ranko Ostojic 12 Nov 2012.
Cryogenic Summary - K. C. Wu Testing D2L102 in MAGCOOLJune, 02 Difference between D2L102 and D2L101 Operating Summary Cooldown to 100 K and 6 K Test Condition.
Cryogenic scheme, pipes and valves dimensions U.Wagner CERN TE-CRG.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
ILC Cryogenic System Shallow versus Deep Tunnel Tom Peterson Dubna Meeting 5 June 2008.
8/29/07K. C. Wu - Brookhaven National Lab1 Major Components in ILC IR Hall Interchangeable Detectors.
LHC Machine Advisory Committee Meeting no.19 QRL status 16 June 2006 G. Riddone, AT-ACR On behalf of the QRL team.
CW Cryomodules for Project X Yuriy Orlov, Tom Nicol, and Tom Peterson Cryomodules for Project X, 14 June 2013Page 1.
Overview of the ESS Linac Cryogenic Distribution System
Bruno Vullierme Sept LHC-CC09 - 3rd LHC Crab Cavity Workshop Slide 1 CRAB CAVITY INTEGRATION CRYOGENICS INSTALLATION.
Workshop on cryogenic & vacuum sectorisation of the SPL Vacuum Sectorisation Paul Cruikshank, CERN Technology Department (TE) Vacuum Surfaces & Coatings.
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
ILC : Type IV Cryomodule Design Meeting Main cryogenic issues, L. Tavian, AT-ACR C ryostat issues, V.Parma, AT-CRI CERN, January 2006.
FCC Infrastructure & Operation Update on the cryogenics study Laurent Tavian CERN, TE-CRG 28 October 2015.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
ESS Cryomodule Status Meeting – Introduction | | Christine Darve Introduction to Cryomodules for the ESS 2013 January, 9 th Christine Darve.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
NIKHEF Annual Meeting, December 18, The LHC Project Status report to the NIKHEF annual meeting Jos Engelen Based on last week’s reports to CERN.
TDR Cryogenics Parameters Tom Peterson 28 September 2011.
IT-4189 Supply and installation of a cryogenic distribution system
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
SPS cryogenic proximity equipment and SM18 validation
The LHC - Status Is COLD Is almost fully commissioned
Presentation transcript:

CHAMONIX XV QRL installation and first experiences of operation G. Riddone on behalf of the QRL team AT/ACR-cd Acknowledgements to AT/ACR-op and AT/ACR-in sections, AT/VAC, AB/CO, TS/IC, TS/SU groups for their support and collaboration

GR, AT/ACR-cd 2 Contents QRL layout Installation »Main features »Present status »Schedule Operation  Reception tests »Schedule »Main results Conclusions

GR, AT/ACR-cd 3 QRL layout Tested part is marked in blue A G F E D C B H I A - Vacuum sub-sector “A” QRL is a continuous cryostat of ~3.2 km length no header (4 or 5) sectorisation  9 vacuum sub-sectors (A…I)  vacuum insulation separate from machine QRL elements in one sector ~ 38 service modules ~ 40 fixed point/vacuum barrier elements ~ 235 straight pipe elements ~ 10 steps/elbows ~ 1-2 cryogenic extensions

GR, AT/ACR-cd 4 QRL layout Sector 3-4 Sector 5-6 Pipe element Service module

GR, AT/ACR-cd 5 QRL sector installation Installation of ~ 700 external supports Positioning of ~ 325 elements Welding and testing of ~ 325 interconnections  > 2000 welds »~ 180 “O” type interconnections (1 butt-weld per header) »~ 75 “C” type interconnections (2 butt-welds per header) »~ 70 “A” type Interconnections (3 welds per header)

GR, AT/ACR-cd 6 QRL sector installation Overall installation: 6 teams Installation by sub-sectors Automatic welding for the inner headers »Nominal rate: 20 int./week »Achieved rate: 30 int./week Manual welding of the external sleeves »Nominal rate: 20 int./week »Achieved rate: 35 int./week NDT tests »Internal (video camera) and external visual control: 100% »Radiography tests: from 100 % to 10 % as a function of weld quality »Leak tightness tests: 100 % (each weld, each sub-sector, each sector) Head of the machine Tool for He leak test

GR, AT/ACR-cd 7 Status of the installation

GR, AT/ACR-cd 8 Schedule

GR, AT/ACR-cd 9 Reception tests QRL tests: »Sector 7-8, sub-sectors A and B: about 700 m »Sector 8-1, full sector: about 3200 m Tests »Pressure tests »Flushing of the circuits »Cooldown »Instrumentation commissioning »Heat inleak measurements »Warmup

GR, AT/ACR-cd 10 Reception test schedule

GR, AT/ACR-cd 11 Pressure test Sector 8-1

GR, AT/ACR-cd 12 Configuration for flushing and cool-down

GR, AT/ACR-cd 13 High-flow rate flushing with He Original colour ! New filter (8-1) Old filter (7-8, A-B)

GR, AT/ACR-cd 14 QRL layout for reception test

GR, AT/ACR-cd 15 Tests for the sector 8-1

GR, AT/ACR-cd 16 Cool-down Valve blockage by a “plastic film” coming from header B

GR, AT/ACR-cd 17 Thermometer validation Header C, SSA: 8 TT fully in accordance

GR, AT/ACR-cd 18 Heat inleak measurement Q B,C,D = (mD·hD+mB·hB) - mC·hC (indirect calculation of the mass-flow by using the heaters EH) Q EF = mF·(hFout-hFin) + mE ·(hEout-hEin) B, C and D E and F

GR, AT/ACR-cd 19 Results for headers E and F Boundary conditions »Insulation vacuum in the main envelope: mbar (8-1) mbar (7-8) »Headers E and F: K »Headers C, D and B: 8-15 K [W]Sector 7-8Sector 8-1 Calculated Measured2250 +/ /- 400

GR, AT/ACR-cd 20 Results for headers C, B, D (sector 7-8, A and B) - without JR and without JC ~ 0.25 W/m - JC ~ 50 W  4.2 W/JC - JR ~ 70 W  1 W/m Measurement cross-checked with independent refrigerator input JC = jumper connection JR = junction region

GR, AT/ACR-cd 21 Results for headers C, B, D (sector 8-1) Boundary conditions »Insulation vacuum in the main envelope: mbar »Headers E and F: K »Headers C, D and B: 8-15 K [W] B+C+DBCD Calculated Measured [+/- 30] Measurement cross-checked with independent refrigerator input Mass-flow cross-checked by using the valve opening QRL with JR and without JC

GR, AT/ACR-cd 22 Results for headers C, B, D (sector 8-1) - without JR and without JC ~ 0.16 W/m - JC ~ 90 W  2.4 W/JC - JR ~ 35 W  0.4 W/m

GR, AT/ACR-cd 23 Temperatures of the vacuum jacket

GR, AT/ACR-cd 24 Conclusions 1/2 Installation progresses well: »External support installation at 75 % »Element installation at 50 % Installation in the sectors 3-4 and 5-6 (JR excluded) meets the target rates At present the main concerns for the installation are: »delay for leak detection and repair »availability of singularities for the sector 1-2 (2 JR  18 elbows/steps) »installation of the QRL in UJ22 and UJ24 and possible interference with magnet transport: tooling for QRL installation shall allow the magnet transport Pressure tests successfully performed for sectors 7-8 (A+B), 8-1 and 4-5 (without the JR) Flushing of headers required and sufficient time shall be allocated

GR, AT/ACR-cd 25 Conclusions 2/2 Cold reception tests performed for sectors 7-8 (A and B) and 8-1 Successful thermo-mechanical validation of the QRL design Thermometer accuracy of about +/- 50 mK, much better than specification (+/- 1 K for T> 6K) Heat inleaks to K (headers E and F) circuit within specification For sector 7-8 (sub-sectors A and B) heat inleaks to 4-20 K (headers B, C and D) above specification. Possible causes identified: »Higher thermal shield temperature than expected »Higher insulation vacuum than nominal »Not nominal insulation vacuum in the jumpers: impact on the heat flux through MLI For sector 8-1 heat inleaks to 4-20 K circuit are within specification »Important: Header B heat inleaks within the specification (QRL heat inleaks represents more than 95 % of the corresponding total budget) Other QRL sectors cold tested with the cryo-magnets: still possibility to measure the heat inleaks to the headers only (at present no allocated time for this test)