1 CTF3 collaboration meeting Jan 2008 G.Geschonke Status of CTF3 G.Geschonke CERN.

Slides:



Advertisements
Similar presentations
Frank Tecker - BE/OP for the CTF3 Team IWLC 2010, Frank Tecker Critical Review of CTF3 performance Introduction Beam phase Improved operation.
Advertisements

JCS e + /e - Source Development and E166 J. C. Sheppard, SLAC June 15, 2005.
FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
R. Corsini, CLIC Project Meeting - 24 th May 2013 CTF3 1 CTF3: Highlights of the 1 st run R. Corsini for the CTF3 Team 1.
ATF2 Status and Plan K. Kubo ATF2, Final Focus Test for LC Achievement of 37 nm beam size (Goal 1) – Demonstration of a compact final focus.
Alessandro Cappelletti for CTF3 collaboration 5 th May 2010 RESULTS OF BEAM BASED RF POWER PRODUCTION IN CTF3.
CTF3 commissioning status R. Corsini - CTF3 committee 17 th September 2009 Update on CTF3 Operations and schedule This time I will try to give a more complete.
Drive Beam and CTF 3 International Workshop on Linear Colliders 2010 October 22, 2010 Erik Adli, Department of Physics, University of Oslo and CERN Bernard.
Conclusions from CLIC (IWLC 2010, Geneva) Ken Peach (JAI) Comments.
Summary of AWG4: Beam Dynamics A. Latina (CERN), N. Solyak (FNAL) LCWS13 – Nov 11-15, 2013 – The University of Tokyo, Japan.
R&D proposals for EuCard 2 EuCard2, April 21Steffen Döbert, BE-RF  SRF basic research (W. Weingarten)  CTF3 and CTF3+, possible infra - structure for.
Low Emittance RF Gun Developments for PAL-XFEL
TBL as a 12 GHz power source, overview and first results from commissioning IWLC 2010 workshopSteffen Döbert, BE-RF  Current status of TBL  Status of.
CesrTA Experimental Plan M. Palmer for the CesrTA Collaboration November 17, 2008.
R. Corsini, CLIC Project Meeting October 24, 2012 CTF3 Experimental program for end 2012 R. Corsini for the CTF3 Team 1.
1 CTF3 collaboration meeting 2007 G.Geschonke Status Status of CTF3 G.Geschonke CERN.
CLIC main activities and goals for 2018 Design and Implementation studies: CDR status: not optimized except at 3 TeV and not adjusted for Higgs discovery,
Activities and news Last meeting: 2015 CERN budget allocations as expected, now distributed on accounts Annual report done, and MTP (Medium Term Plan)
CTF3 Probe Beam G. A. Blair Royal Holloway Univ. London CTF3 Meeting, CERN 30 th November 2005 Introduction – UK Context Draft Proposal Future prospects.
Summary of progress towards CLIC goals and next steps for structure testing 6 th X-band collaboration workshop, April 18 th- 20 th 2012 Steffen Döbert,
The SPS as a Damping Ring Test Facility for CLIC March 6 th, 2013 Yannis PAPAPHILIPPOU CERN CLIC Collaboration Working meeting.
Contribution from Pakistan to CLIC & CTF-3 Project. NASIR ABBAS
CLIC work packages CTF3-003 (TBL+) CLIC0-001 (CLIC DB injector) CLIC0-002 (photo injector option for CLIC DB injector.
University of Oslo and CLIC Short overview for first “NorduCLIC” meeting Erik Adli and Steinar Stapnes, University of Oslo May 19, 2008.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
1 R. Corsini – CLIC Project Meeting CTF3 Update CTF3 Update R. Corsini for the CTF3 Team 1.
Electron Sources for ERLs – Requirements and First Ideas Andrew Burrill FLS 2012 “The workshop is intended to discuss technologies appropriate for a next.
TBTS Test Program & Schedule G. Riddone
P. Urschütz - CTF3 Collaboration Meeting 2007 CTF3 commissioning & operation in 2006 P. Urschütz for the CTF3 operations team  Commissioning of the Delay.
Injector Options for CLIC Drive Beam Linac Avni Aksoy Ankara University.
1 CTF3 CLEX day July 2006 CLEX day 2006 Introduction G.Geschonke CERN.
Summary of XFEL uses for CALIFES Erik Adli (University of Oslo, Norway)
1 CTF3 Collaboration Board Jan 2008 G.Geschonke Status of CTF3 G.Geschonke CERN.
Main and Drive Beam Dynamics Working Group Caterina Biscari, Daniel Schulte Attending people ~ 20 ± 5 Presentations ~ 18 (7 from CERN) CL IC 07.
TBL experimental program Status and Results  Introduction  Status  Experimental program for 2010 and beyond  Outlook ACE, Steffen Döbert.
1 CTF3 collaboration meeting 2007 G.Geschonke Status Status of CTF3 G.Geschonke CERN.
Status of the Spanish contribution to CTF3 L. García-Tabarés, F. ToralCERN, 17/9/2006.
Drive Beam Injector Drive Beam Accelerator X 2 Delay Loop X 5 Combiner Ring Two-beam Test Area 3.5 A  s 150 MeV 35 A ns 150 MeV 150 MV/m 30.
CLIC DB injector facility, photo-injector option studies LCWS, Granada, September 26 th -30 th,2011Steffen Döbert, BE-RF  CLIC DB injector  Thermionic.
High-efficiency L-band klystron development for the CLIC Drive Beam High-efficiency L-band klystron development for the CLIC Drive Beam CLIC workshop,
R. Corsini CLIC work-package planning meeting 2-3 November 2011 Introduction to the session.
Status of CTF3 G.Geschonke 1CTF3/CLIC Collaboration Board
TBL experimental program, evolution to RF power testing in TBL ACE 2011, February 2-3Steffen Döbert, BE-RF  Current status of TBL  Experimental program.
CALIFES A proposed electron beam test facility at CERN
CLIC work program and milestones
WP9-SuperB in TIARA M. Biagini, INFN-LNF.
First Year of Operation at the Two-beam Test Stand
CTF3 Collaboration Board May 2009 G.Geschonke
PHIL: A TEST BEAMLINE AT LAL Specifications of PHIL
CLEX Building Layout, Conventional Facilities, TL2, TL2’,
Steering algorithm experience at CTF3
Input to Strategy currently planned
CLEX* Status and Plans CTF3 complex CLEX
Status of the CLIC main beam injectors
Ideas for medium and long term facility upgrade Roberto Corsini for the CLIC Accelerator Collaboration.
TBL, Status, Plans, Experiments
Have a chance to operate your own beam at CERN
Oversea collaborators
Report from the 4th meeting of CLIC ACE
CTF3 Collaboration Technical Meeting January 2008
WP11: electron and proton beam testing
CLIC-ILC BDS & MDI work.
Instrumentation CALIFES ideal for tests and development that requires frequent access to test setup. CERN BI members already using CALIFES and want to.
Electron Source Configuration
Advanced Research Electron Accelerator Laboratory
CLIC damping rings working plan towards the CDR
ATF project meeting, Feb KEK, Junji Urakawa Contents :
Explanation of the Basic Principles and Goals
CLIC Feasibility Demonstration at CTF3
Two-beam Test-stand Design and Construction Status
Presentation transcript:

1 CTF3 collaboration meeting Jan 2008 G.Geschonke Status of CTF3 G.Geschonke CERN

2 CTF3 collaboration meeting Jan 2008 G.Geschonke Welcome / news Not all partners present their work: Turkey: change focus, because operation is now from CCC Pakistan: beam diagnostic equipment Russia IAP JINR : wiggler, fatigue tests PSI: stand-alone x-band power source, EPFL: PhD student UK: ITB removed from FP7, work on radiation effects Meeting programme: report ongoing work new:  Review of existing hardware  What do we need to demonstrate for CLIC technology by 2010?  Upgrade possibilities

3 CTF3 collaboration meeting Jan 2008 G.GeschonkeCTF3 collaboration meeting 2008 G.Geschonke Status 12 GHz stand-alone power source approved klystron being ordered Operating April 09 (at the earliest) Independent 24/7 testing with fast turn around Variable pulse length High repetition rate Easier to operate Derived from NLC 11.4 GHz klystron News 30 GHz programme continues in 2008

4 CTF3 collaboration meeting Jan 2008 G.Geschonke News news from CERN: “White Paper” has been approved by Council

5 CTF3 collaboration meeting Jan 2008 G.Geschonke Collaborating institutes * India and Pakistan have not signed the CTF3 MoU, but have an agreement with CERN Discussions with : UK (Cockcroft Institute), EPFL, INFN Milan, Ukraine, Oslo 18 members involving 24 Institutes Past collaboration with RAL within PHIN 3 new institutes

6 CTF3 collaboration meeting Jan 2008 G.Geschonke Collaboration issues In its last meeting on June 22. the CTF3 collaboration Board has approved to extend the CTF3 collaboration to the whole of CLIC. CLIC machine Advisory Committee has been installed (ACE) ACE reports to DG and Collaboration Board. T. Raubenheimer (SLAC, Chair), M. Huening (DESY), A.Mosnier (CEA), V. Shiltsev (FERMILAB), L. Evans (CERN), T. Shintake (RIKEN/Harima Inst), P.Raimondi/INFN, N.Toge/KEK. first meeting in June, 20 –

CLIC ACE June 22, 2007 Page 7 Tor Raubenheimer CTF3 – CLIC Test Facility CTF3 will demonstrate critical part the CLIC concept Very impressive facility! –Will be largest LC test facility constructed –Already demonstrated many critical issues Heavily loaded acceleration Delay loop and recombination Commissioning combiner ring –Need to ensure this is an operational facility not just a test demonstration Reliable routine operation with stable beams –Two significant differences: Average power and pulse length Need to consider how to deal with these Clearly need additional support to finish and operate facility from 1. CLIC ACE

CLIC ACE June 22, 2007 Page 8 Tor Raubenheimer Final Comments Very impressed with CLIC effort –Large amount of progress over the last decade –Has the potential to offer a real path to multi-TeV e+/e- LC CTF3 will demonstrate most of the critical issues –Potential to create an 800 MeV test linac using CTF3 TBL Clearly needed for TDR but likely possible well before Like to have the next meeting focused on the structure and PETS development program –Dates TBD but probably January Excellent presentations –Thanks to all participants (extra thanks to Sonia!)

9 CTF3 collaboration meeting Jan 2008 G.Geschonke More CLIC ACE comments on CTF3....The facility should also be used to demonstrate the drive beam stability which is necessary for reliable operation of a CLIC linear collider. On a longer timescale, the committee thought it important to develop plans for a significant two-beam accelerator demonstration; connecting the multiple PETS which are planned for the CTF-3 to accelerator structures could provide roughly 1 GeV of acceleration In particular, the low beam energy may make it impossible to reach the CLIC goal of converting 90% of the beam energy into rf power; the present goal for the CTF-3 is beam  rf 50% conversion. Simulations studies should be performed and operational considerations should be given to such implementation specific limitations The CLIC drive beam has a current of roughly 100 Amps, a pulse length of 300 ns, and an energy of roughly 2.5 GeV, while CTF-3 will operate with roughly 35 Amps, 140 ns, and an energy of 100 MeV. Since CTF-3 will likely be the only two-beam accelerator demonstration on the CLIC CDR timescale, it is important to understand how to interpret the results.....Finally, the committee felt that the CTF-3 should be designed with sufficient overhead to test rf components well beyond the nominal design parameters.

10 CTF3 collaboration meeting Jan 2008 G.Geschonke DL CLEX building in Conclusion of Jan 2007 meeting 2006 Thermionic gun CR TL GHz production (PETS line) and test stand Photo injector / laser tests from Linac Beam up to here 2007

11 CTF3 collaboration meeting Jan 2008 G.Geschonke Plan for 2007 start with beam 2. half March, Commission Combiner Ring operation Install vacuum system for Combiner Ring operate for 30 GHz production like in 2006: nights and weekends, supervised by CCC full-time during installation of TL2 Install equipment in CLEX from May 2007 Install TL2: Finish optics, detailed layout ü produce all vacuum elements - ongoing produce magnets, power converters -ongoing Very ambitious, spill over into 2008 ? ü ü ü ü ü

12 CTF3 collaboration meeting Jan 2008 G.Geschonke DL CLEX building in 2006/ Present CTF3 status 2006/7 Thermionic gun CR TL / 8 30 GHz production (PETS line) and test stand Photo injector / laser tests from 2008 On schedule so far Linac TL2 / TL2’ installation ongoing, commissioning start in April 2008 Beam up to here, exit Combiner Ring Laser at CERN, not finished RF gun under construction

13 CTF3 collaboration meeting Jan 2008 G.Geschonke Combiner Ring

14 CTF3 collaboration meeting Jan 2008 G.Geschonke Operation 2007 commissioning of CR: a bumpy start with many problems, optics studies, finally good result. challenging new instability discovered, possible explanation: see D. Alesini Delay Loop not used Operation for 30 GHz: at nights and weekends, finally share with commissioning in bigger blocks

15 CTF3 collaboration meeting Jan 2008 G.Geschonke Operation 2007 ● vacuum leak in dog-leg,  chamber to be replaced in shut-down ● two vacuum leaks after injector in vacuum bellows cause: dark current from gun? ● two cathodes had to be exchanged problems with gun electronics, unstable operation  consolidate gun ● RF power sources: three klystrons needed replacement several charging power supplies failed  new supplies lower beam energy ● teething problems with modifications to the controls system (improved during the year)

16 CTF3 collaboration meeting Jan 2008 G.Geschonke Ongoing work: Combiner Ring new extraction kicker for Combiner Ring (lower impedance): Stripline kicker made by Ciemat, pulser from CERN will be installed during this shut-down Large campaign to align Beam Position Monitors during this shut-down

17 CTF3 collaboration meeting Jan 2008 G.Geschonke Work for the next phase Optics for TL2 (RRCAT) Optics for TL2’ (CERN) detailed layout TL2 and TL2’ finished, all components ordered magnets : RRCAT, TSL, CERN vacuum components: AL chambers: RRCAT Special components: LNF, CERN Stainless steel chambers: CERN Beam diagnostics: CERN, LNF, LAPP

18 CTF3 collaboration meeting Jan 2008 G.Geschonke Work for next phase Tail Clipper change length of bunch train going into CLEX with fast transverse kickers – collimator/dump Strip-line kickers from CIEMAT, pulser: collaboration CIEMAT-CERN Collimator / dump (CERN): serves also as safety element to inhibit beam into CLEX

19 CTF3 collaboration meeting Jan 2008 G.Geschonke Operation in 2008 Operation all year, one stop foreseen: Installation of tail clipper and collimator / dump in September 30 GHz production will continue in 2008

20 CTF3 collaboration meeting Jan 2008 G.Geschonke Ongoing work in CLEX (2008 and later) Instrumentation Test Beam Line not presently funded (FP7 GADGET proposal) CEA Dapnia Saclay overall responsibility CERN CEA laser beam line, laser beam conditioning LAL RF gun for photo injector Uppsala University Two Beam Test Stand CERN PETS and Accelerating structure CIEMAT magnet movers, PETS prototype,(+ series ????), PETS tank (series ???) UPC & IFIC : BPM development + electronics (series ???) CERN overall responsibility, optics, RF equipment, diagnostics, infrastructure, quadrupoles ??? Pakistan: stainless steel vacuum components Iran: RF + Beam dynamics simulations

21 CTF3 collaboration meeting Jan 2008 G.Geschonke CLEX building June Jan 2008 Construction on schedule Equipment installation from May 2007, Beam foreseen from April/May 2008 Sept 2006

22 CTF3 collaboration meeting Jan 2008 G.Geschonke Photo Injector Phase 1: off-line testing from 2008 test stand being built in CTF2 Phase 2: Gun in CTF3: ????? base-line optics has been prepared smaller emittance, faster phase coding, no “satellite bunches” Cs 2 Te photo cathode 3% QE 40 hours life time pulse train: 1.5  s, charge per bunch: 2.33 nC bunch spacing 0.67 ns number of bunches: 2332 diode pumped Nd:YLF laser 10  J IR / bunch 0.37  J UV on cathode /bunch LAL CERN RAL Present status: RF gun under construction, Laser at CERN, needs to be finished strong involvement from CERN, INFN Frascati and Milan Laser is needed also for CALIFES injector !

23 CTF3 collaboration meeting Jan 2008 G.Geschonke Conclusion Programme basically on schedule: Commissioning of Combiner Ring has started TL2 and TL2’ will be completed in spring 2008 CLEX : Califes and Two-Beam Test Stand will become operational in spring 2008 The first cell of TBL will be available in first half of 2008 The other 15 cells of TBL are still missing

24 CTF3 collaboration meeting Jan 2008 G.Geschonke Conclusions Highly motivated team, excellent collaboration between all partners Very good perspectives to meet our goals in 2010 Exciting year ahead for operation: Commission Combiner Ring, Full bunch combination with phase-coding, Delay Loop and Combiner Ring Commission TL2, TL2’ Commission Two-Beam Test Stand incl. PETS tests Commission Califes Qualify TBL PETS **** Consolidate some critical equipment ****