Dynamo use cases on the New Rennes Subway Line
London General Contractor & Construction company 1400 employees 380 M€ Turnover Engineering Office: INGENOVA
Rennes Subway line B
Project location LEGENDRE SCOPE OF WORK
Stations & Maintenance hall
Classic use of Navisworks to get clashes Question: How to send clashes to contractors, knowing they only have Revit skill? Coordination Phase
Answer: Push clashes into Revit with Dynamo using Dynaworks package (Author: Adam Sheather) Coordination Phase
Next step: Openings Validation Coordination Phase
Openings Validation Create 3D Cropped Views for selected elements Setup Views accordingly Coordination Phase
Openings Validation Coordination Phase
Geometry Operation: Attach and Cut Host from Validated Openings Coordination Phase
Tagging…. Quality check Coordination Phase
Dynamo used as a Swiss Army knife Small tasks automation Filling Revit gaps Documentation Phase
One Dynamo definition Rule: Run before any documentation issue Wall thickness Floor thickness Top Bottom Elevation Tags Documentation Phase
PreConstruction Phase Specific Revit use Structural model as link Construction Site documentation Features involved: –Parts –Assemblies –IFC
PreConstruction Phase Families aware of their environment
PreConstruction Phase Families aware of their environment
PreConstruction Phase Assemblies for Equipment Documentation
PreConstruction Phase Assemblies for Equipment Documentation
Dealing with Parts coming from IFCs PreConstruction Phase
Dealing with Parts coming from IFCs PreConstruction Phase
Dealing with Parts coming from IFCs PreConstruction Phase