NCSX 21 March 2003 Reiersen - 1 PDR Preparations Wayne Reiersen NCSX Engineering Meeting 21 March 2003.

Slides:



Advertisements
Similar presentations
Project Management Process. Project Complexity means that: a team of people are needed to supply expertise the work needs to be broken into manageable.
Advertisements

NCSX Vacuum Vessel Overview Paul Goranson WBS 12 Manager Vacuum Vessel Manufacturing Study Kickoff meeting April 29, 2003.
NGAO Team Meeting Management Peter Wizinowich May 26, 2009.
Dominion Radio Astrophysical Observatory DVA-1 Reflector Development Timeline Gary Hovey NRC-HIA Dominion Radio Astrophysical Observaotry.
LSU 01/18/2005Project Life Cycle1 The Project Life Cycle Project Management Unit, Lecture 2.
LSU 07/07/2004Communication1 Communication & Documentation Project Management Unit – Lecture 8.
ITER In-Vessel Coils (IVC) Interim Design Review PDR Checklist Items C Neumeyer July 28, 2010 July 26-28, 20101ITER_D_3MAZCX.
1 Stage 3 Peer Review October 26, 2006 T. Brown. 2 Field Period Assembly (FPA) 1.Make sure the requirements for the tooling is well defined (including.
ITER In-Vessel Coils (IVC) Interim Design Review Introduction C Neumeyer July 26, 2010 July 26-28, 20101ITER_D_3F7XHR.
1 NCSX Modular coil winding pack To shim or not to shim? NCSX WBS 1 Engineering Meeting July 7, 2004 What is requirement? What is baseline winding pack.
GLAST LAT ProjectCDR/CD3 Review May 12-16, 2003 Document: LAT-PR-01967Section XX 1 GLAST Large Area Telescope: LAT System Engineering WBS Dick Horn.
1 WBS 1 Design Analysis Status NCSX Analysis Meeting Dec 3, 2003.
Defining the Vacuum Vessel Geometry NCSX Project Meeting November 27, 2002 Art Brooks.
11 T Dipole Status at FNAL Fred Nobrega January 21, 2014.
NCSX NCSX Design Review Guide May 27, 2005 Wayne Reiersen NCSX.
J.H. ChrzanowskiMod Coil R&D Update1 Modular Coil R&D Update April 9, 2003 James H. Chrzanowski.
Hall 180 Cryogenic test facility: Project management: Project Change Request, EVM and Interface Sheet L. Serio.
NMI End-to-End Diagnostic Advisory Group BoF Fall 2003 Internet2 Member Meeting.
SC Project Review of NCSX, April 8-10, 2008 NCSX Coil Services P.L. Goranson Work Package 161.
NCSX VACUUM VESSEL PL Goranson Thermal Insulation Final Design Review July 31, 2006 WBS12 NCSX.
THE PROJECT LIFE CYCLE PROJECT MANAGEMENT LIFE CYCLE LSU 01/18/2005 PROJECT LIFE CYCLE 1.
Metrology Milestones Metrology Task Force –Vacuum vessel manufacture - P. Goranson –Mod. Coil Form manufacture - D. Williamson –Mod. Coil winding- S. Raftopoulos.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62)
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
Conceptual Design Requirements for FIRE John A. Schmidt FIRE PVR March 31, 2004.
NCSX Systems Engineering Management Plan Peer Review Bob Simmons May 15, 2003.
ITER- TBM Planning and Costing Activity DCLL TBM Mechanical Design ( ) & TBM-Port Interface ( ) Presented by Mo Dagher December
SC Project Review of NCSX, April 8-10, 2008 Job 1260 Neutral Beam Transition Duct (NBTD) P. L. Goranson.
1 -TBWG next meeting 8 - Presentation of Parties, in particular on action 17 and action 19 (TBWG-15), including: Progress of work Impact on TBMs of frame.
TOF Preliminary Design and Safety Review Project Management Controls R. L. Brown.
11/2/2005Mike Viola1 November Lehman Review November 2, 2005 NCSX VVSA NCSX Vacuum Vessel Fabrication Major Tool and Machine – S F 3 120° segments.
F. Dahlgren -SC Project Review of NCSX, April 8-10, 2008 PF, TF, & Trim Coil Supports (WBS-15) Core Base Support Structure (WBS-17) F. Dahlgren NCSX Coil.
Solar Probe Plus A NASA Mission to Touch the Sun March 2015 Instrument Suite Name Presenter's Name.
NCSX B. Nelson for the NCSX Engineering Team NCSX modular coil cooling workshop June 10-11, 2004 PPPL NCSX Modular Coil Cooling Requirements and Initial.
Reproduction interdite © ALMA EUROPEAN CONSORTIUM Reproduction forbidden Design, Manufacture, Transport and Integration in Chile of ALMA Antennas Page.
NCSX NCSX Project Meeting Wayne Reiersen 15 December 2004.
J.H. ChrzanowskiMod Coil R&D Update1 Modular Coil R&D Update April 2, 2003 James H. Chrzanowski.
SC Project Review of NCSX, April 8-10, 2008 NCSX Cryogenics Systems WBS-62 Steve Raftopoulos NCSX Cryogenic Systems WBS(62) Manager.
1 Daya Bay Project Design Review Status Ralph L. Brown US Chief Engineer January 9, 2008.
LAr Week Feb 2000 M. Lefebvre Milestones and Schedule General Production Readiness Review  Passed in Jan 99 Leak Test Station and Electric Test.
How the NCSX Project Does Business
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
1 Stellarator Core Metrology issues NCSX WBS-1 Meeting April 2, 2003 What are we measuring? When? How do we take the measurements? How do we correlate.
1 Assembly Tooling PU Workshop on NCSX Cost & Schedule Princeton Plasma Physics Laboratory Princeton, NJ Mar 1-4, 2007 T. Brown Princeton Plasma Physics.
September 10, FY 2003 Plans Bob Simmons. September 10, Introduction Overview of Project and Engineering Plans Project Plans Engineering Plans.
NCSX VACUUM VESSEL PL Goranson Final Design Review November 17, 2005 Man Access Port /Lateral Supports NCSX.
UCLA - March 8, 2006 US TBM Cost Estimate Status March 8, 2006 Tom Mann.
Field Period Assembly Wayne Reiersen SC Project Review PPPL May 2006.
12/2/04Module 2C1 The NCSX Engineering Web – An Overview Part III Design Data, Fabrication, Assembly, and Installation Plans.
GLAST LAT ProjectCAL Peer Design Review, Mar 17-18, 2003 P. Dizon Naval Research Lab Washington DC GLAST Large Area Telescope Calorimeter Subsystem Gamma-ray.
I. Preliminary Design Review 1. Product specification 2. Project scope 3. Technical approach/solution to the Design Problem 4. Working Schedule (Gantt.
Preparations for working on Station 1 November 22, 2005.
NCSX Strykowsky 1Cost and Schedule Rebaseline April 25, 2005 NCSX Project Re-baseline Review April 25, 2005 Cost and Schedule Ron Strykowsky.
NCSX VVSA / MCWF FDR A Systems Engineering Perspective Wayne Reiersen Bob Simmons NCSX VVSA / MCWF FDR May 19-20, 2004 PPPL.
1 WBS 1 Preparation for FDRs NCSX WBS 1 Engineering Meeting March 17, 2003 What establishes the plan? What are near term deliverables? How will we status.
PPPL Stellarator Program Overview Hutch Neilson NCSX Project Manager NCSX Program Advisory Committee Meeting #6 Princeton, NJ December 9, 2002.
Collaborating for Quality Quality Assurance (QA) & Quality Control (QC) in the Accelerator Project (ACCSYS) Matthew Conlon ACCSYS QA/QC
1 CD-2 ECP Preparations What is Needed. 2 Background As part of the CD-2 process, we need to establish a fully supported and documented cost and schedule.
1 VV Support Fixture FPA Stage 1 PDR Review August 10, 2005 T. Brown.
1 NCSX radial build NCSX Project Meeting December 18, Modular coil build assumptions 2.Vessel build assumptions 3.FW/internal build assumptions.
NCSX Strykowsky 1Independent Project Review (IPR) June 8-9, 2004 NCSX Project Review June 8-9, 2004 Cost, Schedule, and Project Controls Ron Strykowsky.
First-Year Engineering Program Preliminary Design Review (PDR) Definition PDR Objectives PDR Material Project Management Review.
Review of Modular Coil Winding Pack Configuration David Williamson March 19, 2004.
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
Introductory Remarks and Meeting Goals
SCHEDULE Nov 1st - Assembly Table Complete
2K CB FDR Overview:  Agenda, Charge, Review Process

Experimental equipment Edgar L. Black February 17, 2019
US TBM Cost Activity Tom Mann December 12 – 14, 2005.
Presentation transcript:

NCSX 21 March 2003 Reiersen - 1 PDR Preparations Wayne Reiersen NCSX Engineering Meeting 21 March 2003

NCSX 21 March 2003 Reiersen - 2 Definition of a PDR PDR (pe’de-ar) n. 1. A project-level DOE review to determine if the maturity of the project’s design and cost and schedule estimates is adequate to establish the performance baseline. 2. A subsystem-level internal review to determine if all the deliverables for Preliminary Design have been satisfactorily completed. The June PDR will be both a project-level DOE review and a subsystem-level internal review of the Vacuum Vessel (WBS 12) and the Modular Coils (WBS 14)

NCSX 21 March 2003 Reiersen - 3 Requirements for the project level DOE review We need to establish the Preliminary Design Baseline Update the design of the stellarator core to reflect configuration changes since the CDR and incorporate the new modular coil design and vacuum vessel design Update the design of ancillary systems consistent with the updated stellarator core design Update all cost and schedule estimates We need to document the Preliminary Design Baseline Write a Preliminary Design Report (similar to CDR) Provide backup documentation for cost and schedule estimates

NCSX 21 March 2003 Reiersen - 4 Requirements for an internal PDR Performance requirements have been defined A design has been developed that fully meets those requirements All feasibility issues have been resolved Interfaces with other systems have been fully defined Plans for assembly, installation, and test are established Models and drawings have been developed, reviewed, and released at the Preliminary Design level Activities needed to address PDR requirements for the VV and modular coils should be identified in the SEMLs

NCSX 21 March 2003 Reiersen - 5 Foundational milestones Define geometry of stellarator core (21 Feb) Modular coil design from Physics (16 Dec) Winding pack geometry (17 Jan) MC shell and VV geometry (14 Feb) TF/PF geometry (21 Feb) Define turns and current waveforms (14 Mar) Perform flexibility studies (11 Apr)

NCSX 21 March 2003 Reiersen - 6 Key VV PD milestones representative dates Prepare performance specification (28 Feb) Finalize port geometry consistent with diagnostic viewing requirements (14 Mar) Design closure joint (14 Mar) Establish envelopes and location for in-vessel components (4 Apr) Establish port allocations (18 Apr) Complete FMECA, structural, and thermal analyses (25 Apr) Prepare ICDs (9 May) Perform mfg development activities for PDR (9 May) Develop cost and schedule estimates (16 May) Prepare PDR documentation (30 May) and presentations (13 Jun)

NCSX 21 March 2003 Reiersen - 7 Key modular coil milestones again, representative dates Prepare performance specifications (28 Feb) Develop design features – bolted joints, VV supports, shell cutouts, clamps, cooling lines, wings, instrumentation (18 Apr) Perform winding R&D - keystoning tests (7 Feb), material properties and allowables (7 Mar), molding process and VPI in autoclave (21 Mar) Perform FMECA, structural, and thermal analyses (25 Apr) Prepare ICDs (9 May) Perform mfg development activities for PDR for MCWF (9 May) Develop cost and schedule estimates (16 May) Prepare PDR documentation (30 May) and presentations (13 Jun)

NCSX 21 March 2003 Reiersen - 8 Other key milestones again, representative dates Procure SLA model to confirm field period and final assembly (11 Apr) Document plans for field period and final assy (2 May) Complete preliminary design for all systems (2 May) Develop cost and schedule estimates (16 May) Prepare PDR documentation (30 May) and presentations (13 Jun)

NCSX 21 March 2003 Reiersen - 9 Summary We have a coil design! The PDR has slipped until the week of 23 Jun because of the delayed arrival and to put some time between the PDR and the QPS CDR (26 Apr) The PDR will serve two purposes – DOE’s requirements for establishing the performance baseline and our own requirements for proceeding with the Final Design of the VV (WBS 12)and Modular Coils (WBS 14)