ELENA: Commissioning & operation ELENA beam commissioning Operation 12/11/2015T.Eriksson CERN BE/OP/AD1
General planning 12/11/2015T.Eriksson CERN BE/OP/AD2
General installation planning 12/11/2015T.Eriksson CERN BE/OP/AD3
Commissioning key dates (baseline) So far and imminent: AD ejection line modification & validation: completed / in operation Kicker pulse generators tested Ion source installation & initial tests: completed Ion source & Ion switch commissioning: early 2016 (Feb/Mars.) 1:st part of AD to ELENA transfer line: could this be done during 2016 AD start-up ?(April.) EPC/Vacuum ? 12/11/2015T.Eriksson CERN BE/OP/AD4
Beam commissioning key dates (baseline) ELENA ring HW installation & tests completed by 5/7/2016 – All equipment tested incl. controls/SW Ring commissioning with Ions & Pbars (ppm) 5/7 – 14/ ; ~ 4 months. Pbar shift plan with AD users Ion operation could continue >14/11 if compatible with shutdown work 2016 physics run ends 14/11, by this date we will know more about: – Deceleration efficiency – Beam cooling performance – Emittances – Lifetime => decision point for new ejection line installation 12/11/2015T.Eriksson CERN BE/OP/AD5
ELENA setting-up keV 1 Hz, ring in normal polarity & reverse direction: – Finalise set up of xfer line from source: need BTV:s, BPM – First injections & circulating beam: need ring BPM:s, tune msmnt, Schottky system – Orbit/tune/coupling/chromaticity: validation of systems, corrections: need RF – Acceptance check/studies: need scraper system – Lifetime/blow-up rates – Lattice validation with orbit response msmnts – Study effects of e-cooler solenoids – Acceleration tests & ramp corrections: further RF setup needed incl. B-train – Repeat at intermediate & top plateau 12/11/2015T.Eriksson CERN BE/OP/AD6
ELENA setting-up keV 1 Hz, ring in normal polarity & normal direction: – Set-up e-cooler – If H- lifetime is too short: use protons, ring in reverse polarity & normal direction, additional corrections might be necessary later for pbar operation due to remanence effects – Recombination detection (protons), additional tool for alignment/tuning – Extensive use of scraper system for profile and emittance msmnts – Schottky analysis for long. Emittances – Cooling time studies – Lifetime/blow-up rates 12/11/2015T.Eriksson CERN BE/OP/AD7
ELENA setting-up keV protons or 1 Hz, ring in reverse or normal polarity & normal direction: – Initial setting-up of the extraction and ejection lines (only short sections installed at this stage for main and GBAR lines) – Need u-wire monitors + high sensitivity intensity msmnt pickup in lines 12/11/2015T.Eriksson CERN BE/OP/AD8
ELENA setting-up MeV Hz, ring in normal polarity & normal direction: – Set-up transfer line from AD : need BTV, GEM, TFA7049, BPM. (optics validation) – RF synchro s-u for bunch to bucket transfer – Ramp studies: orbits, tunes, slope – Further e-cooler set-up – Set-up of nominal cycle; obtain nominal emittances – Bunched beam extraction 12/11/2015T.Eriksson CERN BE/OP/AD9
ELENA setting-up 5 Further studies with pbars: Space charge studies on higher intensity bunches (extraction on lower harmonics); compatibility with ejection lines Deceleration efficiency > 60% ? Synthetic B-train, validation for use in regular operation => ELENA ring commission complete – ~4 months total time available – Overly optimistic ? 12/11/2015T.Eriksson CERN BE/OP/AD10
ELENA setting-up 6 New transfer lines: 18/8 – 10/ keV pbars or H- – Setting-up of ~ 100m electrostatic xfer lines – u-wire “semi-non-destructive” profile monitors – Set-up of deflectors used for fast switching between experiments – Set-up of beam request/distribution SW/HW 2 months available 12/11/2015T.Eriksson CERN BE/OP/AD11
Operation Sequencing 1/3 Based on ADE sequencing concepts ELENA will have a virtual super cycle ELENA cycle can be: Coupled to the Production Chain (beam from ADE) Standalone mode (beam from source) Goals Optimize the beam request in the beam production chain Maximize the beam availability for experiments Maximize the MD beams Bunches destination «On Demand» and prioritized ELENA Project Review - S.Pasinelli CERN BE/OP12/11/2015
Sequencing 2/3 12/11/2015ELENA Project Review - S.Pasinelli CERN BE/OP
Sequencing 3/3 12/11/2015ELENA Project Review - S.Pasinelli CERN BE/OP
Bunches Extraction Timings 12/11/2015ELENA Project Review - S.Pasinelli CERN BE/OP
Constrains No more action on the ADE from experiments Enable/disable extraction kicker Static settings in the Common Transfer Lines 12/11/2015ELENA Project Review - S.Pasinelli CERN BE/OP
Operation Manpower Commissioning (immediately after AD start-up): – Op-team will work from ACR – AD start-up/operation + ELENA commissioning in 2016 – 2 shifts per day can be covered, (weekends) by team of 7/8 – Eq. specialists will also participate (EN, TE, BE/ABP etc.) – External help is welcome, discussions underway. Once AD/ELENA operational stability obtained: – Machine supervisor from BE/AD/OP team will look after the machines during day-time and be on-call on weekly basis 24h/24, 7d/7 – BE/OP/PS section will do routine operation + initial troubleshooting from the ccc during nights and weekends – Equipment groups ensure “piquet” or best-effort coverage – Note: yearly AD start-ups are very time-consuming, with ELENA even more so 12/11/2015T.Eriksson CERN BE/OP/AD17