Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before.

Slides:



Advertisements
Similar presentations
LCW Upgrades - Final Booster RF Cavity LCW Isolation Valve Replacement. – 8 valves and unions previously replaced – An additional 10 valves and unions.
Advertisements

Proton Plan PMG 7/26/07 E Prebys 1 Proton Plan Status June Eric Prebys.
Chris Smith Booster RF Cavity Upgrade Contents: The Booster Existing RF Cavities Why Upgrade? New Cavities Prototype Plans University Involvement Prototype.
Proton Source Workshop Booster Downtime Wednesday, December 8, 2010 T. Sullivan.
KICKOFF AS PRESENTED 6/17/11, SEE THIS WEEKS SCHEDULE FOP THE LATEST UPDATE Shutdown Shutdown ‘11.
All Experimenters’ Meeting January 09, Accelerator Operation Summary Calendar Week # 51 NuMI Weekly Integrated Intensity 8.81E18 protons BNB Weekly.
NOvA meeting PIP Update W. Pellico. PIP Goals and Scope (Provided in 2011 – Directorate S. H. / DOE Talk ) Goals: Specific to the issues surrounding the.
08/24/07Shutdown’07 Week 3 F.G. Garcia1 MTA beam line installation Weekly Report August 24, 2007 Period covered: August 17 th to August 24 th (Week 3)
PIP Update June 25 th Agenda Summary Update – Current Activities/Updates – Ryan Crawford: Anode Supply Update – Peter Prieto: BPM Update – CY Tan:
Preparation for May-2013 Review of UCN Beamline March 27, Date: May 2-3, 2013 Review Committee finalized Scope – Overall concept, focusing on 2014.
ANU Shutdown Status AEM meeting Cons Gattuso 6/3/2012.
Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
PIP Update Aug 6 th Agenda Summary Update – Current Activities/Updates – New Tuner Test Result: Reid & Slabaugh – Anode Supplies: Crawford.
PIP Update Feb 20 th Agenda Summary Update – Current Activities/Updates – Startup Schedule Highlights – Upcoming Talks, Reports, Meetings Updates/Talks:
ANU Shutdown Status AEM meeting Cons Gattuso 7 May 2012.
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
Proton Plan Director’s Review 8/15/06 Prebys 2006 Shutdown Eric Prebys, FNAL Accelerator Division.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Proton Improvement Plan William Pellico FRA Visiting Committee Meeting March 14-15, 2011.
Ff NO A Accelerator Upgrades: Status Phil Adamson Fermilab
2015 Shutdown Joe Compton 3/11/2015. RIL PIP Work  Install operational laser notcher  5 days  Dave Johnson & Todd Johnson.
Accelerator and NuMI Upgrades Shutdown Update Cons Gattuso July 02, 2012 July 2, 2012 Cons Gattuso1.
Maintenance and Accelerator Support RHIC StartUp10.
Proton Improvement Plan Bob Zwaska January 7, 2013 All-Experimenters Meeting.
PIP Update Oct Agenda Summary Update – Current Activities Updates/Talks: Dave Johnson – Linac Notching (laser)
08/31/07Shutdown’07 Week 4 F.G. Garcia1 MTA beam line installation Weekly Report August 31, 2007 Period covered: August 24 th to August 31 st (Week 4)
Proton Improvement Plan Keith Gollwitzer January 5th, 2015 All Experimenters’ Meeting 11/5/2015Gollwitzer AEM.
MINU GPP WBS 1. Main Injector Neutrino Upgrades - Infrastructure Project Dixon Bogert APD Department Report – March 7, 2007 Russ Alber - FESS Engineering.
PIP Update July 30 th Agenda Summary Update – Current Activities/Updates – Project Controls Update: K. Domann – Linac Lattice – Valeriy Kapin.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
Matthew Gardner, 8/20/14.  Replace old water based AC system with conventional rooftop AC system. Drain and abandon old water lines.  Remove old air.
PIP Update April 8 th Agenda Summary Update – Current Activities – Updates (V. Kapin: Booster Collimator) – Additional Meetings/Notes.
Booster Bias Supply and Cavity Upgrade November 16 th, 2011.
Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status June Report Eric Prebys.
Proton Plan PMG 9/27/07 E Prebys 1 Proton Plan Status Eric Prebys.
L-band test stations in End Station B Richard Swent.
Proton Improvement Plan Bill Pellico April 19, 2013 NOvA collaboration Meeting Bill Pellico NOvA.
What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003.
Proton Plan PMG 2/23/06 E Prebys 1 Proton Plan Status January Report Eric Prebys.
PIP Update June 18 th Agenda Summary Update – Current Activities/Updates – Reid, Slabaugh.
2/17/2016 Recycler -Gattuso Recycler Shut Down Status  Flying Wire Status  Wire Vacuum Certified  Tunnel Bake Prep status Disconnection of BPM, Correctors,
09/07/07Shutdown’07 Week 5 F.G. Garcia1 MTA beam line installation Weekly Report September 07, 2007 Period covered: August 31 st to September 7 th (Week.
MTA Installation Meeting March 7, 2007 Agenda 1)Progress report (Fernanda) 2)Water skid discussion (Maurice) 3)Alignment needs (O’Sheg + all) 4)AOB Key.
Machine Status  Proton Source Commissioning and Studies 8/13-8/14: Linac & Booster Maintenance Period  Main Injector MI30 vacuum ○ Work continues to.
Proton Plan PMG 2/22/07 E Prebys 1 Proton Plan Status January Eric Prebys.
PIP Update Dec 17 th Agenda Summary Update – Current Activities – Updates – Additional Meetings/Notes.
Proton Plan Director’s Review 8/15/06 Prebys Proton Plan Summary Director’s Review August 2006 Eric Prebys.
Proton Plan PMG 10/13/05 E Prebys 1 Proton Plan Status September Report Eric Prebys.
July 15, 2013 Photo by Greg Vogel. Shutdown Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster.
PIP Update Jan. 16 th Agenda Summary Update – Current Activities/Updates – Shutdown ScheduleHighlights – Upcoming Talks, Reports, Meetings Updates/Talks:
PIP Update Oct 29 th Agenda Summary Update – Current Activities – Updates – Additional Meetings/Notes.
Proton Plan PMG 4/18/05 E Prebys/J. Sims 1 Proton Plan Status March Report Eric Prebys Jeff Sims.
August 2007 Booster RF Upgrades J.Reid Booster RF Upgrades West Gallery LCW modifications: – Headers in select locations to be upgraded by.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
Proton Source Meeting, August 8, 2003 – E. Prebys 1 Major Projects in Linac/Booster  New Linac Lambertson  (4) New EDWA magnets in MI-8 line  (3) New.
PIP Update July 29 th Agenda Summary Update – Current Activities – Updates Tom Kubicki (Station 20,21,22 – Gallery and Equipment Work) – Additional.
PAC Meeting, December 12, Prebys 1 The Problem.
PIP Update March 6 th Agenda Summary Update – Current Activities/Updates – Startup Schedule Highlights – Upcoming Talks, Reports, Meetings Updates/Talks:
July 29, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Trying to.
March 7 th Shutdown Shutdown Begins: Monday morning, March 7 th :00 Beam OFF Safety System Testing 08:00 Rack out KRSS, switch MI house power to.
09/21/07Shutdown’07 Week 7 F.G. Garcia1 MTA beam line installation Weekly Report September 21, 2007 Period covered: September 14 th September 21 th (Week.
Booster Status, September 4, 2003 – E. Prebys 1 Frantic Shutdown Preparations Continue…
PIP Shutdown Status 9/17/2014. RIL/Linac Jobs L1 Transformer ◦Rigging complete ◦Electrical work started ◦Turn on this coming weekend Laser notcher flange.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
Friday 5/1/ meeting. I wish to lock in the power outage onTuesday 5/5/09 at the end of the 0930 lab scheduling meeting speak now or :
MI/RR Shutdown 2012 Dec Gev Lines/Injection region: Staging equipment, cleaning and prepping new part to start vacuum work. Preparing to modify the.
10/3/2014 Proton Source Update. RIL Update Source B is back in place and under vacuum It will be baked over the weekend It will be started early next.
All Experimenters Meeting PIP Report Fernanda G. Garcia on behalf of PIP team 10/06/2014.
Proton PMG May 7 th 2015 Cons Gattuso AD Shutdown Manager.
Presentation transcript:

Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before Beam pipe installation Continued Kicker installation LCW pipe for corrector upgrade nearly done ORBMP magnet/Girder work delayed but progressing ORBMP Power Supply Conditioning

Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before Beam pipe installation Continued Kicker installation LCW pipe for corrector upgrade nearly done ORBMP magnet/Girder work delayed but progressing ORBMP Power Supply Conditioning

Q806 arrives

Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before Beam pipe installation Continued Kicker installation LCW pipe for corrector upgrade nearly done ORBMP magnet/Girder work delayed but progressing ORBMP Power Supply Conditioning

Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before Beam pipe installation Continued Kicker installation LCW pipe for corrector upgrade nearly done ORBMP magnet/Girder work delayed but progressing ORBMP Power Supply Conditioning

Booster Shutdown Work - Week 4 Booster West 13.8KV switch gear installed RF maintenance continues 400 MeV Gallery work progressing BWT dig progressing for conduit. Still waiting on MI-8 conduit!!!

Booster Shutdown Work - Week 4 Booster West 13.8KV switch gear installed RF maintenance continues 400 MeV Gallery work progressing BWT dig progressing for conduit. Still waiting on MI-8 conduit!!!

Bias Supplies

Booster Shutdown Work - Week 4 Booster West 13.8KV switch gear installed RF maintenance continues 400 MeV Gallery work progressing BWT dig progressing for conduit. Still waiting on MI-8 conduit!!!

MI8 Excavation

Booster Shutdown Work - Week 4 Booster West 13.8KV switch gear installed RF maintenance continues 400 MeV Gallery work progressing BWT dig progressing for conduit. Still waiting on MI-8 conduit!!!

Reminder 13.8KV Transformer/Switchgear Replacement - Prepare for next week's transformer/switchgear work - 208V work - Schedule for power outage and switch to generator to 12:00 for electrical work and switch over to generator Monday March 27 -This will effect BET, BEG and Booster Tunnel