POWER SYSTEM PLANNING CHARTER AND PROCESSES Presentation to TAC May 6, 2004 Transmission Services Ken Donohoo, Manager of System Planning Dan Woodfin,

Slides:



Advertisements
Similar presentations
NERC TPL Standard Issues TSS Meeting #146 Seattle, WA August 15-17, 2007 Chifong Thomas.
Advertisements

NERC Footnote b / 12 – Load Loss
GEORGIA POWERS SMALL POWER PRODUCERS FUNDAMENTALS.
RPG: September 24, Approach for ERCOT Independent Review of the 2013 Houston Import Project Jeff Billo, Manager, Transmission Planning September.
Regional Planning Group Charter Revisions May 2008.
2004 Congestion Costs. 2 Transmission Congestion Occurs when analysis shows a given outage of a transmission element (contingency) will result in the.
Houston Import Evaluation Cross Texas Transmission & Garland Power & Light ERCOT RPG Meeting August 27th, 2013.
Economic Criteria for Transmission Planning in the ERCOT Region Public Utility Law Seminar DeAnn Walker August 3, 2012.
KURTEN SWITCH PROJECT (BRYAN/ COLLEGE STATION AREA UPGRADES) Technical Advisory Committee December 1, 2005 Transmission Services.
MARCH 31, 2014 Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE.
1. 11/26/2012: NERC Board of Trustees adopted CIP v5 CIP thru CIP CIP and CIP Version 5 Filing FERC requested filing by 3/31/2013.
January 5, 2012 TAC Cross Valley 345 kV Project Jeff Billo Manager, Mid-Term Planning.
2001 South First Street Champaign, Illinois (217) Davis Power Consultants Strategic Location of Renewable Generation Based on Grid Reliability.
PLWG Report to ROS July 9, PGRRs needing vote PGRR043 – FIS Scoping Amendment – PGRR043 moves the Subsynchronous Resonance (SSR) Study out of the.
ERCOT Compliance Audits Robert Potts Sr. Reliability Analyst March 23, 2005.
Determine Facility Ratings, SOLs and Transfer Capabilities Paul Johnson Chair of the Determine Facility Ratings Standard Drafting Team An Overview of the.
ERCOT SOL Methodology for the Planning and Operations Horizons Stephen Solis 2014 OTS 1.
ISO Grid Planning Presentation to CREPC October 1, 2002
JACKSBORO TO WEST DENTON 345-kV PROJECT Presentation to Technical Advisory Committee April 8, 2004 Transmission Services Operations.
2006 Reliability Study Scope Name Date. DRAFT 2 Purpose of Study Assess the PEC and Duke transmission systems’ reliability Develop a single reliability.
Long Term Study Task Force Update Transmission Study Practices and Methodologies April 5th,2011 LTS.
10/03/ Report on Existing and Potential Electric System Constraints and Needs Within the ERCOT Region October 3, 2002.
Lyndonville Electric Department Feasibility Analysis Review December 2,
McCAMEY 345 kV TRANSMISSION PLAN Presentation to Technical Advisory Committee May 8, 2003 KENNETH A. DONOHOO, P.E. Manager, System Planning Transmission.
POWER SYSTEM PLANNING CHARTER AND PROCESSES Presentation to TAC 10/09/2003 KENNETH A. DONOHOO, P.E. Manager of System Planning Transmission Services
OSC Meeting April 27, Transmission Cost Allocation Overview.
Reliability Requirements Bill Blevins Manager of Operations Support ERCOT.
LAREDO PLANT RMR EXIT STRATEGY Presentation to Board of Directors March 16, 2004 Transmission Services Operations.
SPS policy – Information Presentation Presentation to ROS June 16, 2004.
© Property of ERCOT /06/20041 Overview of SPS in ERCOT February 5, 2004.
ERCOT PUBLIC 4/21/ RTP: Cascade Analysis April 21, 2015.
ISO Comparison – CAISO Alex Lee (ERCOT)
POWER SYSTEM PLANNING CHARTER AND PROCESSES UPDATES Presentation to TAC Sept 9, 2004 Transmission Services Ken Donohoo, Manager of System Planning
Jones Creek Project Submitted to RPG on July 7, 2014 July 22, 2014 Regional Planning Group Meeting.
Current Export Initiatives Jerry Mossing Exports Workshop February, 16,2006, Metropolitan Center, Calgary.
Transmission Outage Process April Purpose In compliance with the Protocols and the Electric Reliability Council of Texas (ERCOT) Operating Guides,
LAREDO RMR EXIT STRATEGY Presentation to Technical Advisory Committee March 4, 2004 Transmission Services Operations.
JACKSBORO TO WEST DENTON and WEST LEVEE TO NORWOOD 345-kV PROJECTS April 20, 2004 Transmission Services Operations.
May 11, 2012 RPG meeting YTP Scope and Process – RPG Comments.
SPP.org 1. Status Update for Reliability and Economic Assessments Stakeholder Meeting September 16, 2008 Austin, TX.
SPP.org 1. Final Report: Reliability and Economic Assessments Stakeholder Meeting December 1, 2008 Austin, TX.
Outage Planning Subcommittee Mark Wilson. Outage Planning Subcommittee Created to address Market Participant concerns with existing rules and procedures.
Operating Guide and Planning Guide Revision Requests Blake Williams, ROS Chair September 13, 2012.
ERCOT TAC11/2/ CREZ Study Update ERCOT TAC 11/2/2006.
TRANSMISSION CONSTRAINTS KENNETH A. DONOHOO, P.E. Manager of System Planning, Technical Operations
October 16, 2009 RPG Meeting ERCOT Independent Review of the Corpus Christi Improvements Project Jeff Billo.
Current Operational Challenges Computing the West – North Limits Potential IROLs Local Voltage & Thermal issue (OOME) High Voltage Outages.
LCRA TSC/ CPS Energy Transmission System Addition Regional Planning Group Project Jeff Billo Sr. Manager, Transmission Planning TAC ERCOT Public March.
ERCOT ROS Planning Working Group (PLWG) Scope Approved at ROS Meeting.
September 1, 2011 TAC Lower Rio Grande Valley Regional Planning Group Project Jeff Billo Manager, Mid-Term Planning.
Planning for Texas’ Energy Future Select Committee on Electric Generation Capacity and Environmental Effects Bob Kahn President & CEO February 6, 2008.
Role of Account Management at ERCOT 2006 TAC Subcommittee Review ERCOT Board February 21, 2006.
OPSTF – Issue 7 Long-term unavailability of autotransformers.
Oncor Transmission Service Provider Kenneth A. Donohoo Director – System Planning, Distribution and Transmission Oncor Electric Delivery Co LLC
Capacity, Demand and Reserves Report Bill Bojorquez May 4, 2007.
Capacity, Demand and Reserves Report Bill Bojorquez Board of Directors Meeting May 16, 2007.
ERCOT Transmission Planning Process Overview and Recommendations November 6, 2002.
Transmission Services Report: North and West RPG Projects Bill Bojorquez TAC July 7, 2005.
2006 Reliability Study James Manning Bryan Guy May 12, 2006.
03/06/2008 TAC CREZ Transmission Optimization (CTO) Study Update Dan Woodfin Director, System Planning.
©2003 PJM 1 Presentation to: Maryland Public Service Commission May 16, 2003.
Reliability Standards Committee 2009 Scope and Plan Judith James Manager, Reliability Standards.
1 NPCC – A-2 Dr. Mayer Sasson Transmission Planning Consolidated Edison of New York June 1, 2006 Presented to the NYSRC-RRS.
Reliability Must Run Workshop RMR Study Process May 24, 2016.
Freeport Area Master Plan Project -
Transmission Planning in ERCOT- Overview
Wind Management at MISO
ERCOT – Southern Cross Transmission ROS/WMS Working Group Assignments
Modifications to Planning Charter
Reliability and Operations Subcommittee Report
Presentation transcript:

POWER SYSTEM PLANNING CHARTER AND PROCESSES Presentation to TAC May 6, 2004 Transmission Services Ken Donohoo, Manager of System Planning Dan Woodfin, Manager of Resource Planning

© ERCOT 2004 KAD 05/06/2004 CURRENT MAJOR STUDIES UNDERWAY Central Texas (Clear Springs-Salado 345 kV Line) North and Central RPG Underway, expect completion Fall 2004 Dallas-Ft. Worth and Northeast ERCOT North RPG Scope developed, reviewed and approved Underway, expect completion Winter Rio Grande Valley Area (Laredo-McAllen-Harlingen- Brownsville) South RPG and RMRTF Bryan-College Station Area North and South RPG Just starting

© ERCOT 2004 KAD 05/06/2004 CHARTER DEVELOPMENT PROCESS DEVELOPED AND REVIEWED WITH: Regional Planning Groups (North, South & West) Transmission Owners (TDSP’s) PUCT Staff Market Participants and other Stakeholders PRESENTED AND ACCEPTED BY ROS September 10, 2003 PRESENTED AND ACCEPTED BY WMS September 17, 2003 PRESENTED AND ACCEPTED BY TAC October 9, 2003 PRESENTED AND ACCEPTED BY ERCOT BOARD October 22, 2003

© ERCOT 2004 KAD 05/06/2004 PLANNING RESPONSIBILITIES CHARTER DEFINES PLANNING RESPONSIBILITIES FOR: ERCOT STAFF TDSP’s (Transmission Owners) STAKEHOLDER/MARKET PARTICIPANTS PUBLIC UTILITY COMMISSION Substantive Rules REGIONAL PLANNING GROUPS

© ERCOT 2004 KAD 05/06/2004 PLANNING PROCESS Studies include computer modeling of the generation, transmission facilities and station loads Apply contingency conditions along with changes in load and generation that might be expected to occur Identify adverse results based upon the planning criteria Develop options and examine the effectiveness of various problem-solving alternatives Test effectiveness of each grid configuration and facility change Thermal and Voltage Limits (Steady State) Dynamic Stability Limits (Transient and Voltage) Repeated simulations under different conditions are required Options considered may affect other alternatives so that several different combinations must be evaluated Once feasible alternatives have been identified, the process is continued with a comparison of those alternatives, multiplying the number of simulations required To determine the most viable, compare the short-range and long- range benefits of each including operating flexibility, maintenance/construction coordination and compatibility with future plans

© ERCOT 2004 KAD 05/06/2004 REGIONAL PLANNING GROUPS Goal is to obtain all viewpoints and ideas and avoid problems due to lack of communication For Major Project Studies before project development stakeholder input requested at: Study scope development – start of study Preliminary status at middle of study Presentation of preliminary report at end of study Web posting and s to RPG members are “Official Notice” System Planning data area on Internet Must register for access exploder lists for each region (North, South & West) Open, anyone can be on the lists Regional Planning Group addresses North – South – West –

© ERCOT 2004 KAD 05/06/2004 PLANNING PROCESS Project Submission And Review Requirements Small Projects - “Tier 1” 138 kV to 60 kV projects not requiring PUCT certification (CCN) Regional Planning Group review (includes ERCOT & PUCT Staff) Large Projects - “Tier 2” 345 kV and higher projects along with other projects requiring PUCT certification (CCN) Includes exempt municipal & electric cooperatives projects under what-if test Regional Planning Group review (includes ERCOT & PUCT Staff) ERCOT Staff independent study Why haven’t all projects been submitted for RPG review? Open process phase-in issue Propose that we require all projects with in-service date of 2006 or greater be submitted for review 2004, 2005 and some 2006 projects are already in-progress Many 345 kV projects for 2004 through 2010 have already be submitted, reviewed and are underway

© ERCOT 2004 KAD 05/06/2004 PLANNING PROCESS Generation New Interconnection or Change ERCOT Security Screening Study Site feasibility for new interconnection or change (addition) Identify current operating limits Rough estimate of the transmission system additions needed to integrate all of the new or changed generation “ERCOT will inform the generating entity if it considers the proposed site to be inappropriate to the point that ERCOT will not support the addition of transmission needed to integrate the project into the transmission system.” Highly subjective Full Interconnection Study with transmission owners Completes interconnection or change request Complete Interconnection Agreement with transmission owner New generation project or change becomes public Impact studies (security and full interconnection) posted on internet Generation related transmission projects submitted to the full Regional Planning Group for review and approval

© ERCOT 2004 KAD 05/06/2004 PLANNING CRITERIA ERCOT Planning Criteria state the fundamental minimum requirements for planning and constructing reliable interconnected electric systems under: Normal Condition PC Category A Single Contingency Conditions PC Category B Includes the contingency loss of single faults resulting in multiple elements (SFME) out Includes the contingency loss of a double-circuit transmission line that exceeds 0.5 miles in length Double circuit = Single contingency = Category B Includes the contingency loss of any single generating unit unavailable, and with any other generation preemptively redispatched, the contingency loss of a single transmission element Generator + Single contingency = Category B Multiple contingency conditions PC Category C & D Allows generation, load and/or system adjustment

© ERCOT 2004 KAD 05/06/2004 TYPES OF PROJECTS Reliability Driven Projects are defined as system improvements primarily intended to resolve current or projected levels of reliability criteria violations that cannot be met by redispatch of existing generation Economic Projects are defined as system improvements primarily intended to resolve current or projected levels of reliability criteria violations that could instead be solved by preemptive redispatch of existing generation but have been initiated because they are projected to result in a net economic benefit to the market based on ERCOT-wide impacts.

© ERCOT 2004 KAD 05/06/2004 ReliabilityEconomic Study on-peak and off-peak load conditions Study all hours Use unconstrained economic dispatch powerflow case Solve category B criteria violations through preemptive redispatch Use security-constrained economic dispatch for each hour Identify remaining criteria violations Identify elements that result in less than economic dispatch through time Develop upgrades that minimize cost of solving remaining criteria violations through time Develop upgrades that minimize sum of construction and production cost through time May plan reliablity-driven project for criteria violation in one hour May not plan upgrade that would result in reduced congestion in peak hours if not warranted by cost reductions over time PROJECT DRIVERS

© ERCOT 2004 KAD 05/06/2004 Economic Criteria The criteria for determining whether a project is economic is the increase in economic value to the market due to the project, as measured by an expected reduction in the market production cost due to the project that exceeds the cost of the project.

© ERCOT 2004 KAD 05/06/2004 DFW/NE Study Process Overview List of Highest Congestion Cost Elements Peak Hour Contingency Analysis Develop Reliability- driven Solutions Economic Evaluation of Sets of Alternatives Recommend Upgrades Powerflow Cases with Unconstrained Economic Dispatch Violations Solved by Redispatch ? Develop Solution Alternatives to Overloads Contingency Analysis of Economic Alternatives No Yes List of Overloads with No Feasible Redispatch Solutions

© ERCOT 2004 KAD 05/06/2004 QUESTIONS/DISCUSSION

© ERCOT 2004 KAD 05/06/2004 PLANNING CRITERIA Category A & B

© ERCOT 2004 KAD 05/06/ The contingency loss of a double-circuit transmission line that exceeds 0.5 miles in length (either without a fault or subsequent to a normally-cleared non-three-phase fault) with all other facilities normal should not cause a) cascading or uncontrolled outages, b) instability of generating units at multiple plant locations, or c) interruption of service to firm demand or generation other than that isolated by the double-circuit loss, following the execution of all automatic operating actions such as relaying and special protection systems. Furthermore, the loss should result in no damage to or failure of equipment and, following the execution of specific non- automatic predefined operator-directed actions (i.e., Remedial Action Plans), such as generation schedule changes or curtailment of interruptible load, should not result in applicable voltage or thermal ratings being exceeded. 2.With any single generating unit unavailable, and with any other generation preemptively redispatched, the contingency loss of a single transmission element (either without a fault or subsequent to a normally-cleared non- three-phase fault) with all other facilities normal should not cause a) cascading or uncontrolled outages, b) instability of generating units at multiple plant locations, or c) interruption of service to firm demand or generation other than that isolated by the transmission element, following the execution of all automatic operating actions such as relaying and special protection systems. Furthermore, the loss should result in no damage to or failure of equipment and, following the execution of specific non-automatic predefined operator-directed actions (i.e., Remedial Action Plans) such as generation schedule changes or curtailment of interruptible load, should not result in applicable voltage or thermal ratings being exceeded. Generator + Single contingency = Category B Double circuit = Single contingency = Category B PLANNING CRITERIA Category B

© ERCOT 2004 KAD 05/06/2004 PLANNING CRITERIA Category C

© ERCOT 2004 KAD 05/06/2004 PLANNING CRITERIA Category D

© ERCOT 2004 KAD 05/06/2004 PLANNING CRITERIA Footnotes to Table a) Applicable rating (A/R) refers to the applicable normal and emergency facility thermal rating or system voltage limit as determined and consistently applied by the system or facility owner. b) Planned or controlled interruption of generators or electric supply to radial customers or some local network customers, connected to or supplied by the faulted component or by the affected area, may occur in certain areas without impacting the overall security of the interconnected transmission systems. To prepare for the next contingency, system adjustments are permitted, including curtailments of contracted firm (non-recallable reserved) electric power transfers. c) Cascading is the uncontrolled successive loss of system elements triggered by an incident at any location. Cascading results in widespread service interruption, which cannot be restrained, from sequentially spreading beyond an area predetermined by appropriate studies. d) Depending on system design and expected system impacts, the controlled interruption of electric supply to customers (load shedding), the planned removal from service of certain generators, or the curtailment of contracted firm (non-recallable reserved) electric power transfers may be necessary to maintain the overall security of the interconnected transmission systems. e) A number of extreme contingencies that are listed under Category D and judged to be critical by the transmission planning entity(ies) will be selected for evaluation. It is not expected that all possible facility outages under each listed contingency of Category D will be evaluated.