PHENIX WEEKLY PLANNING 1/24/2008 Don Lynch. 1/17/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going Switch.

Slides:



Advertisements
Similar presentations
PHENIX WEEKLY PLANNING 9/13/2007 Don Lynch. 9/13/2007 Weekly Planning Meeting 2007 PHENIX Shutdown April-June 2007: Complete run, De-mount HBD West, Begin.
Advertisements

PHENIX WEEKLY PLANNING 1/17/2008 Don Lynch. 1/17/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going1/18 Gas.
PHENIX WEEKLY PLANNING 6/7/2007 Don Lynch. 6/7/2007 Weekly Planning Meeting 2 Schedule End of Run Party 6/29/07 Next Maintenance Day No More Planned Remove.
2/2/20121 PHENIX WEEKLY PLANNING 2/2/2012 Don Lynch.
PHENIX WEEKLY PLANNING 2/15/2007 Don Lynch. 2/15/207 Weekly Planning Meeting 2 Remaining Schedule StartComplete Cosmic Ray Run (Run 6.9)In Progress All.
2/9/20121 PHENIX WEEKLY PLANNING 2/9/2012 Don Lynch.
Technical Support /5/08 PHENIX WEEKLY PLANNING 6/5/2008 Don Lynch.
PHENIX WEEKLY PLANNING 5/17/2007 Don Lynch. 5/17/2007 Weekly Planning Meeting 2.
PHENIX WEEKLY PLANNING 5/31/2007 Don Lynch. 5/31/2007 Weekly Planning Meeting 2 Schedule End of Run Party 6/29/07 Next Maintenance Day 6/6 or 6/13/07?
1 7/02/2009 PHENIX WEEKLY PLANNING 7/2/2009 Don Lynch No Meeting this week due to July 4 th holidays. Slides have been updated. Next planning meeting will.
6/6/ PHENIX WEEKLY PLANNING 6/6/2013 Don Lynch Note: No PHENIX planning meeting this week due to end of run party. Feel free to discuss safety and.
PHENIX WEEKLY PLANNING 2/21/2008 Don Lynch. 2/21/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
8/9/20121 PHENIX WEEKLY PLANNING 8/9/2012 Don Lynch.
1 3/5/2009 PHENIX WEEKLY PLANNING 3/05/2009 Don Lynch.
PHENIX WEEKLY PLANNING 4/10/2008 Don Lynch. 04/10/08 Shutdown ’08 Schedule Purge Flammable Gas, Magnet & DAQ TestsDone Remove lock-out & open shield wallDone.
PHENIX WEEKLY PLANNING 5/24/2007 Don Lynch. 5/24/2007 Weekly Planning Meeting 2 Schedule End of Run Party 6/29/07 Next Maintenance Day 6/6/07 Remove HBD.
PHENIX WEEKLY PLANNING 3/8/2007 Don Lynch. 3/8/207 Weekly Planning Meeting 2 Schedule Cosmic Ray Run (Run 6.9) Continues…. All Up Commissioning In Progress.
Progress Completed Order/Fabricate SS Piping for HBD Purge gas from all detectors DAQ tests Prep. for Shutdown work (open doors, move carriages, etc. Pave.
Technical Support /4/08 PHENIX WEEKLY PLANNING 9/4/2008 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
PHENIX WEEKLY PLANNING 10/11/2007 Don Lynch. 10/11/2007 Weekly Planning Meeting2 Run 8 Prep Schedule ItemStartFinish MPC South InstallationDoneDone Elec.
PHENIX WEEKLY PLANNING 3/6/2008 Don Lynch. 3/6/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
Technical Support /1/08 PHENIX WEEKLY PLANNING 5/1/2008 Don Lynch.
PHENIX WEEKLY PLANNING 6/29/06 Don Lynch. 6/29/2006 Weekly Planning Meeting 2 This Week TOF W tests continue, modification decisions made? New HV connector.
3/6/ PHENIX WEEKLY PLANNING March 6, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 3/27/2008 Don Lynch. 3/27/2008 Weekly Planning Meeting2 Shutdown ’08 Schedule CM Crane ReviewMar Purge Flammable Gas, Magnet.
5/1/ PHENIX WEEKLY PLANNING May 1, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 2/2/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 11/2/06 Don Lynch. 11/2/06 Weekly Planning Meeting 2 New Detectors TOF West HBD RXNP MPC North.
PHENIX WEEKLY PLANNING 3/22/2007 Don Lynch. 3/22/2007 Weekly Planning Meeting 2 Schedule Re-Start 5 man shifts 3/20/07 Beam: blue ring 3/8/07, in yellow.
PHENIX WEEKLY PLANNING 1/10/2008 Don Lynch. 1/10/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going1/18 Gas.
PHENIX WEEKLY PLANNING 2/9/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 9/14/06 Don Lynch. 9/14/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown '065/1/200612/8/2006.
Technical Support /8/08 PHENIX WEEKLY PLANNING 5/8/2008 Don Lynch.
PHENIX WEEKLY PLANNING 12/6/2007 Don Lynch. 12/6/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn GoingOn Going.
1 3/10/2011 PHENIX WEEKLY PLANNING 3/10/2011 Don Lynch.
9/27/20121 PHENIX WEEKLY PLANNING 9/27/2012 Don Lynch.
PHENIX WEEKLY PLANNING 10/4/2007 Don Lynch. 10/4/2007 Weekly Planning Meeting 2007 PHENIX Shutdown October 2007: Finish MPC South Installation, replace.
PHENIX WEEKLY PLANNING 12/7/06 Don Lynch. 12/7/06 Weekly Planning Meeting 2.
PHENIX WEEKLY PLANNING 10/18/2007 Don Lynch. 10/18/2007 Weekly Planning Meeting2 Run 8 Prep Schedule ItemStartFinish MPC South InstallationDoneDone Elec.
3/20/ PHENIX WEEKLY PLANNING March 20, 2014 Don Lynch.
12/6/20121 PHENIX WEEKLY PLANNING 12/6/12 Don Lynch.
PHENIX WEEKLY PLANNING 11/15/2007 Don Lynch. 11/8/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going11/30.
PHENIX WEEKLY PLANNING 12/27/2007 Don Lynch. 12/27/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn GoingOn Going.
PHENIX WEEKLY PLANNING 3/15/2007 Don Lynch. 3/15/2007 Weekly Planning Meeting 2 Schedule Cosmic Ray Run (Run 6.9) Done All Up Commissioning On Going Re-Start.
PHENIX WEEKLY PLANNING 3/02/06 Don Lynch. BLM Test.
Technical Support /15/08 PHENIX WEEKLY PLANNING 5/15/2008 Don Lynch.
5/24/20121 PHENIX WEEKLY PLANNING 5/24/2012 Don Lynch.
PHENIX WEEKLY PLANNING 6/28/2007 Don Lynch. 6/14/2007 Weekly Planning Meeting 2007 Summer Shutdown Schedule ItemStartComplete RPC Factory set up5/ ?
PHENIX WEEKLY PLANNING 12/20/2007 Don Lynch. 12/20/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn GoingOn Going.
PHENIX WEEKLY PLANNING 7/26/2007 Don Lynch. 7/26/2007 Weekly Planning Meeting 2007 Summer Shutdown Schedule ItemStartComplete RPC Factory set upStarted.
PHENIX WEEKLY PLANNING 5/7/2007 Don Lynch (Thursday is Monday this week)
Preparations for Run 6 Don Lynch February 13, 2006.
PHENIX WEEKLY PLANNING 1/31/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going Switch.
PHENIX WEEKLY PLANNING 5/3/2007 Don Lynch. 5/3/2007 Weekly Planning Meeting 2 Schedule HyTec CM vibration modes test5/23/07 End of Run Party 6/29/07 Next.
1 1/29/2009 PHENIX WEEKLY PLANNING 1/29/2009 Don Lynch.
1 7/16/2009 PHENIX WEEKLY PLANNING 7/16/2009 Don Lynch.
3/7/20131 PHENIX WEEKLY PLANNING 3/7/2013 Don Lynch.
Technical Support /16/08 PHENIX WEEKLY PLANNING 10/16/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/1/2007 Don Lynch March: in like a lion Out like a lamb.
2/27/ PHENIX WEEKLY PLANNING Feb. 27, 2014 Don Lynch.
Technical Support /22/08 PHENIX WEEKLY PLANNING 5/22/2008 Don Lynch.
1 7/9/2009 PHENIX WEEKLY PLANNING 7/9/2009 Don Lynch.
PHENIX WEEKLY PLANNING 11/8/2007 Don Lynch. 11/8/2007 Weekly Planning Meeting2 Run 8 Prep Schedule ItemStartFinish Elec. Cooling Water upgrade(CA) (under.
PHENIX WEEKLY PLANNING 6/8/06 Don Lynch. 6/8/2006 Weekly Planning Meeting 2 This Week Rec’d TOF West Access: move HBD to Dead Turtle Position Sec’y of.
1 11/25/2010 PHENIX WEEKLY PLANNING 11/25/2010 Don Lynch.
2/20/ PHENIX WEEKLY PLANNING Feb. 20, 2014 Don Lynch.
1 2/19/2009 PHENIX WEEKLY PLANNING 2/19/2009 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 2/14/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
PHENIX WEEKLY PLANNING 2/16/06 Don Lynch. Prep for Run 6 Completed.
Presentation transcript:

PHENIX WEEKLY PLANNING 1/24/2008 Don Lynch

1/17/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going Switch to p+p run1/281/28 Next scheduled Maint. Day?1/301/30 CM Crane design review2/12/28 Scheduled Maint. Day2/132/13 Lab Holiday (Presidents Day)2/182/18 Scheduled Maint. Day2/272/27 Mu Trigger FEE Prototype II install2/27 ?2/27 ? Complete new beampipe design2/292/29 End PP run3/123/12 Low Energy Run3/133/14 End of Run 83/155/27 Install new UPS~3/15~3/31 End of Run Party4/44/4 Install Gas house UPS’s4/156/13 Install HBD 7/159/15

1/17/2008 Weekly Planning Meeting3 Yesterday’s Maintenance: Jan. 16th Next Maintenance Access Day Scheduled for 1/28/08: Switch over to p-p run switch Pad chambers onto gas with alcohol move ZDC back into symmetric-beam positions install access step on BBC rack/CM access ladder hardware TBD subsystem maintenance Remaining Scheduled Maintenance Access Days 2/13 & 2/27 MuTrigger FEE Prototype II test on 2/27

1/17/2008 Weekly Planning Meeting4 PC gas supply modifications

1/17/2008 Weekly Planning Meeting5 PC gas supply modifications

1/17/2008 Weekly Planning Meeting6 PC gas supply modifications

1/17/2008 Weekly Planning Meeting7 CM Ladder/Stair Shutdown Access

1/17/2008 Weekly Planning Meeting PHENIX Shutdown Prep January-March 2008: Run 8 technical support RPC factory support new beam pipe design completion and review CM Crane design review and purchase placement Muon Trigger FEE prototype test II MMN station 1 & 2 scaffolding design and safety review Muon Trigger Rack platform design and review RPC3 installation review preparation (support structure, transport and installation fixture design, tunnel vapor barrier modification design, gas mixing and distribution system and piping design). VTX, FVTX & NCC technical support

1/17/2008 Weekly Planning Meeting9 Tent Preparation – Done Safety systems – Installation complete, mini-blue sheet Equipment Issues – Need specs for 3T (Tilting Transport Table) and GMHOS (gap, module and ½ octant storage) racks, then need to fabricate assemble and install. Work plan – Update for factory procedures RPC Factory Support, cont. Security –Comply with C-A policy

1/17/2008 Weekly Planning Meeting10 RPC Factory Issues, cont. Area to the west of RPC factory is now re-posted and cordoned with yellow tape as a controlled area. A corridor has been left to access the bathroom. Any activities which will need to traverse the posted area (e.g. delivery of materials, equipment etc. through the roll up doors) will require a work permit

1/17/2008 Weekly Planning Meeting11 RPC Factory Support Safety System Procedure Done!

1/17/2008 Weekly Planning Meeting12 New Beampipe Design & Review Current beampipe IR region: 3 inch (76.2 mm) OD Be section,.04” (1 mm) wall thickness 55” (1400 mm) long Proposed beampipe IR region: 1.61 inch (41.0 mm) OD Be section,.02” (0.5 mm) wall thickness 31.5” (800 mm) long Design to be ready for final review by 2/29/08

1/17/2008 Weekly Planning Meeting13 CM Crane Crane Design nearly ready for review Uses Gorbel 1-ton capacity Ceiling mounted Bridge Crane, modified to be supported by 2 Steel Channels attached to CM Bridge and hoist to be removed for running. measuring clearances for crane runways

New ADTX Board IR RIKEN/RBRC Itaru Nakagawa Scheduled Maintenance Day Feb.27

1/17/2008Weekly Planning Meeting15 MuTr North, Station-2, Octant 7(bottom) Same Setup as Summer Chamber Cover, Velcro Tape, Water Cooling Pluming, LV power

1/17/2008Weekly Planning Meeting16 Set Up backup MuTr.N StandAlone

1/17/2008Weekly Planning Meeting17 Local DAQ + +

1/17/2008Weekly Planning Meeting18 Works to Do and Time Estimation  Access Preparation to MuTr.N bottom Volume (1 hr)  Installation Local DAQ, New Boards (1.5hr)  Grounding & Noise Measurement (2hr)  Uninstallation (0.5hr)  MuTr Full Calibration (0.5hr)  IR Closing (1hr) Min. Total 6.5 hr + Unexpected Delay

1/17/ IR Counting room ADTX TX(receiver) Local DAQ Beam clock distributor Patch connection data Beam clock Possible test set up for winter test Pro No need to bring local DAQ in IR. We can save time (1hr). Con Data/BCLK has to travel long way (~100m?), attenuation? Jitter? 19

1/17/ IR Counting room ADTX TX(receiver) Local DAQ Beam clock Distributor or Function generator Patch connection data Beam clock Pretest of patch connection at

1/17/ Travel schedule 21 itaru tsutomYoshi.F Kenichi K. 2/14 2/27

1/17/2008 Weekly Planning Meeting22 MMN Scaffolding Existing MMN MuTr scaffolding is being redesigned to be assemble-able with only one lampshade removed and access to all station 2&3 FEE’s from lower hatch. Additional scaffolding to be designed to access all Station 1 North FEE’s and lampshade sites adjacent to station 1. Station 1 North scaffolding to be useable for Station 1 South with minimal modification. Station 2 & 3 South scaffolding to be addressed later

1/17/2008 Weekly Planning Meeting23 New Platform 8’ x 2.5’ Muon Trigger Rack Platforms HBD/RXNP MuTrgrFEE NMuTrgrFEE S VTX FVTX NCC N NCC S RPC1 S RPC1 N New Platform 8’ x 2.5’

1/17/2008 Weekly Planning Meeting24 Muon Trigger Rack Platforms New Idea: Put MuTrggr FEE South Rack in front of middle MuTr Rack on eyebrow. Use bridge as walkaround. (Need rolling walkway on east side like west side). Made measurements for North Rack.

1/17/2008 Weekly Planning Meeting25 RPC 3 Design Review 2008 shutdown: install one RPC 3 South and one RPC 2 South prototype half octant: requires installation fixtures, prototype gas system, modifications to tunnel vapor barriers, prototype electronics, cable routing support, and, of course, structural support design All require both functional and safety reviews (may be combined) by ~June Assume installation in Aug.-Sept Cu Absorber installation (1 octant on south) Final review for 2008 prototype installation, interim review for overall project. MuTrgr FEE electronics, installation, water & air, safety (final for North, interim for south) 4 months to prepare

1/17/2008 Weekly Planning Meeting26 Other Work VTX, FVTX and NCC prototype support Integration Physical and Rack space Infrastructure upgrades New Counting House Door

1/17/2008 Weekly Planning Meeting27 Safety, Security, Etc. : As noted at today’s PHYSICS all-hands meeting, walking and falling is the single greatest cause of injuries at the lab. Look before you walk. EMS and OSH Audits Coming in February BNL will be having the annual Environmental Management System (ISO14001) internal audit during the week of 2/11. This will be done by outside auditors. C-AD will be conducting the annual OSH (ISO18001) audit at that same time period. These audits are needed to prepare for the annual independent Registration Audit in June of this year by NSF, our registrar. New Subject Area Posted on SBMS: Walking and Working Surfaces Contains procedures for the safety of all BNL staff, contractors, visitors, and guests who walk and work on a variety of surfaces, including elevated surfaces, stairs, and ladders. This subject area does not apply to activities directly covered under the Fall Protection, Lifting Safety, Forklift Safety, Excavation Safety, and Construction Safety Subject Areas.Fall ProtectionLifting SafetyForklift SafetyExcavation SafetyConstruction Safety

1/17/2008 Weekly Planning Meeting28 March 2008: Complete Run 8, MUTrigger FEE Prototype tests, Purge flammable gas, open shield wall. RPC Factory work. RPC installation design work. April 2008: Disassemble Shield wall, remove collars, disconnect EC & move to AH, set up IR for shutdown. Test assembly of MMN scaffolding (in AH). Install Station1 South scaffolding. Install CM access stairs. Prep EC for Shutdown requirements. May 2008: Install CM Crane. MuTr decapacitations in station1 south. Prep work for MuTrgr electronics platforms north & south. Prep work for RPC prototype installation June 2008: MuTr decaps, station 1 S & N, PC1 repairs, Inst. station2/3 N scaffolding. July 2008: Re-Install HBD, RPC prototype gas system, Move shielding for RPC installation, RPC prototype cable routing and support, modify crystal palace and tunnel vapor barrier, fabricate RPC installation fixtures, install MMN Station 2 & 3 scaffolding, TBD subsystem maintenance August 2008: Install RPC prototypes, install Mu Trigger FEE’s in MMS and MMN, Install N&S rack support platforms for Mu Trigger FEE’s. Install MMN cooling water and air supply for MMN. TBD prototype tests, TBD infrastructure work September 2008: Replace tunnel shielding, connect electronics, gas, water and air as necessary for RPC and Mu Trigger FEE, October 2008: Prepare for run, EC into IR, install collars, build shield wall, etc. November 2007: blue sheets, white sheets, close wall, start shifts, flam. Gas, physics 2008 PHENIX Shutdown

1/17/2008 Weekly Planning Meeting29 5 Year Plan 2008 Install stations 1& 2 of MuTr FEE upgrades (north), 1 octant Cu absorber (S), 2 half otants RPC2/3 S, infrastructure upgrades & repairs, misc. subsystem work, MMN scaffolding, 1 octant of MuTrigger FEE upgrades (south), MuTr N stn. 1,2 & 3 repairs, MuTrigger rack platforms (N&S), CM crane 2009 Scaffolding in MMS, MuTr S stn. 1 & 2 repairs, RPC2 N, RPC3 N, north Cu absorbers, infrastructure upgrades & repairs, misc. subsystem work, remove/replace beampipe, VTX prototype, DC West upgrade/repair 2010Remove HBD & RXNP, VTX barrel, south Cu absorber completed, MuTr FEE stn. 3 S, MuTr stn. 1, 2 & 3 S repairs, infrastructure upgrades & repairs, misc. subsystem work 2011RPC1 N&S, NCC S, FVTX, infrastructure upgrades & repairs, misc. subsystem work, remove south absorber 2012NCC N, upgrades contingency & wishlist, infrastructure upgrades & repairs, misc. subsystem work, remove north absorber * Years refer to the shutdown year and follow the run with the similar number (i.e. work in 2008 is to be done in the shutdown that follows run 8, and so on)

1/17/2008 Weekly Planning Meeting30 Links for the weekly planning meeting slides, long term planning, pictures, videos and other technical info can be found on the web site: Where To Find PHENIX Technical Info