AFP – Technical Status 1.Cost estimates 2.Manpower estimates 3.First Actions AFP Kick-Off 03FEB2015 1 Michael Rijssenbeek.

Slides:



Advertisements
Similar presentations
M. Gilchriese US ATLAS Pixel Meeting July 18-19, 2002 UC Santa Cruz.
Advertisements

Conference Title L. Stringhetti, IASF Milano, ASTRI Meeting #9, Bologna 24 Feb Status of the ASTRI/CTA project and organization/management issues.
L. Greiner 1HFT PXL LBNL F2F – March 14, 2012 STAR HFT The STAR-PXL sensor and electronics Progress report for F2F.
IBL interim-MoU Annexes G. Darbo – INFN / Genova PEIB, 1 March 2010 o IBL interim-MoU Annexes Pixel Extended Institution Board CERN, March 1 st, 2010 NCP.
Construction and Installation of the CLIC Experimental Area
October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab.
ATLAS POH.P, G.D12/5/2009 IBL Update H. Pernegger, G. Darbo (PO 12/5/09) Organization and WG coordinator Schedule Decision Items Organization Tools & Meetings.
AFP ATLAS Forward Proton Upgrade Project AFP physics goals AFP where and how AFP plans Work to be done:  Integration in the LHC (ECR, specifications,
March ‘08G. Ruggiero Totem Collaboration Meeting Roman Pot Detectors 1 st RP Detector Assembly RP vs DCS and DB CERN Open day.
EE and SE Installation Wolfgang Funk - CERN CMS 11/9/ ) Introduction 2.) Installation scenario 3.) SE schedule, manpower, cost estimates 4.) EE.
David M. Lee Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs.
M. Gilchriese ATLAS Upgrade Introduction January 2008.
V. Bobillier1 Long distance cable installation status Calorimeter commissioning meeting.
Pixel Upgrade Status and Plan G.M. Bilei Firenze Mar. 6 th 2013.
Slide 1 6-Nov-98PHOBOS Review: Cost & Schedule Cost & Schedule S. Steadman, MIT PHOBOS Cost & Schedule Review Technical Advisory Committee BNL November.
Silicon Inner Layer Sensor PRR, 8 August G. Ginther Update on the D0 Run IIb Silicon Upgrade for the Inner Layer Sensor PRR 8 August 03 George Ginther.
L. Greiner 1IPHC meeting – May 7, 2012 STAR HFT Plans for the next year A short report on HFT/PXL plans for post May 2012 TPC – Time Projection Chamber.
Construction and Installation Readiness of TOTEM Roman Pots Detectors Federico Ravotti (PH/TOT) Gennaro Ruggiero (PH/TOT) LHCC minireview – 06 May 2009.
Silicon Meeting July 10, 2003 Module and Stave Production Status James Fast Fermilab.
Workpackages & deliverables Funding & manpower Uncovered areas Institutions round table Institutes commitments Vit Vorobel, AFP kick-off1.
LS2 Other LHC Experiments Mike Lamont Thanks to: Michael Rijssenbeek (AFP) Joachim Baechler (TOTEM) Karl-Heinz Hiller (ALFA)
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese U.S. ATLAS Review Revised Version November 29, 2000.
Cooling Systems Adopted For the Use in the Particle Detectors 1 V. Vacek AGENDA: What we can offer for the the AFP R&D Project: Two cooling systems (Aircooler.
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
Tracker Summary Alan Bross MICE CM October 10, 2007.
Technical Support Activities in PH-ADO-PO
RP detectors CTS Sensors now in production, full delivery between February and June 07 Production GUI and DB being finalised Test Procedure being defined.
G. Carboni – Muon Meeting – April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to
U.S. Deliverables Cost and Schedule Summary M. G. D. Gilchriese Revised Version December 18, 2000.
MM detector construction One or several modules per sector considerations.
AFP: present status and next steps M. Bruschi – INFN Bologna (ITALY)
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
M. Gilchriese Items from Talks U.S. Pixel Meeting Santa Cruz July 2003.
Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs Cost Schedule.
IBL Kick-off Meeting – Summary & Issues G. Darbo – INFN / Genova UPO, 21 July 2009 o IBL kick off meeting summary and issues ATLAS Upgrade Project Office.
TC Straw man for ATLAS ID for SLHC This layout is a result of the discussions in the GENOA ID upgrade workshop. Aim is to evolve this to include list of.
TE-CRG-CE OMP Meeting 06 / 11 / 2014TE-CRG-CE OMP Meeting.
Walter Snoeys – CERN – PH – ESE – ME –TOTEM October 2009 TOTEM Electronics Status.
Dec
RRB scrutiny Report: Muons. Internal scrutiny group for RRB report Internal scrutiny group composition – J. Shank, G. Mikenberg, F. Taylor, H. Kroha,
AFP Trigger DAQ and DCS Krzysztof Korcyl Institute of Nuclear Physics - Cracow on behalf of TDAQ and DCS subsystems.
Assembly scenario of ILD Si trackers 2015/4/21 Yasuhiro 1.
David M. Lee Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs.
Upgrade PO M. Tyndel, MIWG Review plans p1 Nov 1 st, CERN Module integration Review – Decision process  Information will be gathered for each concept.
Status of Contributions, Draft Budget Request for 2005 and Outlook for the Longer Term Future Martyn Davenport 8 TH October 2004 CAST FRC-D
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
Preparations to Install the HBD for Run 6 Craig Woody BNL PHENIX Weekly Meeting January 26, 2006.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
G. Ruggiero / TOTEM 1 Si Edgeless Detectors in the RPs Edgeless detector (on the old “AP25 module”) active edges (“planar/3D”) planar tech. with CTS (Current.
IBL TDR G. Darbo / INFN Genova ATLAS CB – October 2010 o TDR of Insertable B-layer ATLAS CB, October 8 th 2010 G. Darbo / INFN - Genova Indico agenda page:
Joint LHC Machine-Experiments Workshop on Very Forward Detectors - 25 January 2007 Beniamino Di Girolamo - CERN PH ATLAS Roman Pots status, commissioning.
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
Steinar Stapnes, LHCC June The ATLAS inner detector TRT endcap A+B TRT endcap C TRT barrel SCT barrel SCT endcap Pixels uWhole ID sits inside bore.
Tracker cooling status General status Production: Manifolds, Distribution lines Work at P5 Plan Conclusions 19/05/091E. Focardi.
ATLAS Forward Project (AFP) Technical review outcome Review done on (morning) September 2013, see agenda
ATLAS Forward Proton Detectors ATLAS Forward Proton Detectors Michael Rijssenbeek for the ATLAS Collaboration Physics summary: Physics withSingle and Double.
USCMS Pixel PMG, Nov 29, Mechanics Status Disks, ½ Service Cylinders Installation USCMS FPIX FNAL PMG Joe Howell Bruno Gobbi Nov. 29, 2006.
RD42 Status Report W. Trischuk for the RD42 Collaboration LHCC Meeting – June 12, 2013 Development of CVD Diamond Tracking Detectors for Experiments at.
Preparation & Commissioning of TOTEM for the Run-II of LHC S.Giani on behalf of the TOTEM Collaboration.
Prototype Cryomodule FDR Ken Premo 21 – 22 January 2015 High Power Coupler Design.
Silicon Vertex Detector Schedule 23 July 2012 Christian Irmler (HEPHY Vienna) 12 th Open Meeting of the Belle II Collaboration.
Status of the ATLAS Forward Proton Detectors Michael Rijssenbeek for the ATLAS AFP group 25FEB2016.
TC activities.
Introduction Status before the 2009 run Results from the 2009 run
LS2 LHC forward experiments
Planning for the TDR KEK schedule: Technical Design Report (TDR)
Sub-Detector Assembly Area Summary of discussion at ALCW2015
2017 AFP Beam Tests AFP has 1 week as main user and will also measure together with ATLAS ITk Pixel in H6B -> 2 periods of ~3 weeks
Update on ATLAS insertable B-layer
SVT – SuperB Workshop – Frascati Sept. 2010
Presentation transcript:

AFP – Technical Status 1.Cost estimates 2.Manpower estimates 3.First Actions AFP Kick-Off 03FEB Michael Rijssenbeek

AFP 0+2 Single Arm, 2 Roman Pot Stations (206 m, 214 m) Earliest opportunity to install: Winter SSD (9 wks!) – AFP Beam Pipe section ~9 m – RP Stations + BPM – Cables – Vacuum, Cooling Tracking detectors (SiT) – 4 planes of 3D Silicon Pixels; edgeless (150 um) – provide L1 Trigger from FE-I4 HitOR outputs (e.g. 3 planes out of 4) – SiT can be installed during a short (6 hr) access NO Time-of-Flight for AFP0+2 (ToF) – ToF not needed/useful for 1-arm physics … only for study of time structure of backgrounds …  install only if the rest is done ! AFP Kick-Off 03FEB a VERY large job in VERY little time !

Summary TDR Draft version ready: – Some missing sections which are not too important for AFP 0+2 – Sections still needing words/ideas: L2 Trigger DCS Infrastructure Final Version in for Collaboration review (after AFP Kick-off) – Required for final version: – Clean-up – Critical read by AFP in this week ! Deadlines: Feb 2 Mo midnight: TDR vs.01, section responsibles sign-off on their sections. MR does cross-checks. TDR will be put on EDH on Feb 9. – Feb 9 Mo midnight: TDR vs.02, AFP-MB has signed off on whole TDR – ready for Collaboration review AFP Kick-Off 03FEB2015 3

Costs and Manpower and Time All WBS and Cost Books are in svn: – File: AFP_WBS.zip – To view: load AFP_WBS.xlsx, and all AFP_CostBook_*.xlsx where * stands for L2 tasks: RPS, SiT, ToF, TDAQ, Infrastructure, TestBeam, Installation, Commissioning Check costs, responsibilities, labor estimates, durations for your task! – modify yourself, or tell me what to change! Constants: Arms, Spares, valuta conversions, etc. in ‘Constants’-sheet in AFP_WBS.xlsx Final Version to be ready for Collaboration review (soon after this AFP Kick-off meeting) – Critical read by AFP Institutes ! Deadline: Feb 9 Mo midnight AFP Kick-Off 03FEB2015 4

Costs and Manpower and Time All WBS and Cost Books are in svn: – File: AFP_WBS.zip AFP Kick-Off 03FEB2015 5

Estimated Cost & Manpower: RPS AFP Kick-Off 03FEB Very Tight!

Example Scheduling (RPS) AFP Kick-Off 03FEB PRELIMINARY Stations MUST be fully ready for LHC final acceptance testing per mid Nov 2015

Roman Pot Stations Immediate order to VP for the Prototype Station (Prague CU ?) – price is good; speed is of the essence!  must ask CU to pay !! – follow by order of 1 st Station if prototype is accepted – (identify local contact engineer in Prague … Volunteers?) In parallel: Pot – Build 2 TOTEM pots at CERN – 1 Prototype AFP Pot by Alberta In parallel: RPS infrastructure – Flanges – Motor, ball screw, rails – LVDT, switches – tooling balls, … – about 50 KCHF for 3 Stations … Who Pays? 2 nd Station: – Who Pays? – and: we need 2 more for AFP2+2 … AFP Kick-Off 03FEB Note: Stations + Infrastructure are most urgent; Detectors can be installed during short access … for AFP0+2 the RPS and Pot are straight copies of TOTEM design

SiT AFP Kick-Off 03FEB2015 9

Silicon 3D Tracker – SiT Urgent: – need FE-I4 chips with metallization! seems to be solved – chips from Prague to IZM for UBM? IFAE pays for UBM – need Flex design and production! required for module (= bonded sensor + FE-I4) QA – cannot wait for layer card design and production! – therefore: special flex (cannot use the IBL flex for several reasons) – who does this ?? – need Layer Card & card Holder! Design, Production – Geneva is not available – Who then? Saclay ?? Prague CTU ?? Bologna ?? others ?? AFP Kick-Off 03FEB

TDAQ OptoBoards available and will be bought RCE on loan from SLAC ? L1 HitOR Trigger (LIP?) needs a EE designer and small production … – design trigger (majority) coincidence card (e.g. 3 out of 4 planes) – trigger driver, trigger receiver + CTP interface AFP Kick-Off 03FEB

AFP Kick-Off 03FEB Infrastructure

Actions: Infrastructure Infrastructure in the Tunnel – Prepare AFP Beam Pipe section design ASAP – BPM 1 BPM per arm (at 214 m station) define type, cables, installation location, procedure, … – Vacuum Pump – Cooling Vortex Cooling! – DCS Elzbieta has started on a detailed scheme AFP Beam/interlocks: contact with Sigi Wenig – Cables & Trays define cable types, numbers, paths from LHC-approved types patch panel layouts, locations AFP Kick-Off 03FEB

TB, Installation, Commissioning A similar WBS task exists for the ToF … Installation Tasks to be developed – Dummy beam pipe installation scenario – Cable tray installation, Cabling scenarios – RP Station installation – Detector exchange/installation AFP Kick-Off 03FEB

Actions This/Next Week Start process of Procurement & Engineering Change Requests – Tight collaboration with ATLAS TC profit from ALFA and TOTEM experience – Confer with Patrick & Sune for help – Order of business: Cable Trays: procurement, contact with LHC … Cable installation: define types, procurement, LHC certification … Station support and footing: adapt TOTEM Brackets to ALFA Table AFP Kick-Off 03FEB

AFP0+2 Cost Summary Need new Collaborators / new Responsibilities: – Not covered Detector Projects (=?): ~43 KCHF Si Tracker Card Si Tracker Holder (Reference Clock for ToF – for AFP2+2) – Not Covered Infrastructure (=??): ~193 KCHF RP Station 2 Flanges, Motors, Transducers, etc. Feedthroughs for SiT, ToF, Services RPS support tables AFP Beam Pipe BPM (1 per arm) Vacuum Pump Patch panels & Cables Institutional contributions should be confirmed at this time ! AFP Kick-Off 03FEB InstitutionCost ? 43 ?? 193 Barcelona IFAE 117 Cracow IFJ PAN 36 Milano 6 Olomouc(ToF) Oslo 8 Portugal LIP 9 Prague AS 12 Prague CTU(ToF) Prague CU 20 Stony Brook 4 SLAC (RCE Loan) 17 * Alberta 4 New Mexico(ToF) Arlington(ToF) TOTAL COST468 NOT COVERED (?, ??)236 *) under discussion

Summary Non-covered Items RPS infrastructure~73KCHF Tables, Flanges, Motor, Slide, Rails, LVDT, etc. 1 st (part) + 2 nd RP Station ~23KCHF TOTEM Pots ~13KCHF AFP Beam Pipe section, BPM, vacuum pump ~56KCHF Cables, trays, patch panels ~28KCHF DCS ~ 8KCHF SiT Flex design and production cannot wait for layer card design and production! Genoa, Oslo ?? SiT Layer card & card Holder ~36KCHF Who? Saclay ?? Prague CTU ?? Bologna ?? others ?? AFP Kick-Off 03FEB

Summary Manpower (2015) The estimate (also using ALFA experience) suggests we need: Urgent: – 1 FTE of onsite TC (+ 1 FTE PL FTE RC) – 0.5 FTE of onsite Project/Mechanical Engineer: assistance with oversight of RP Station assembly, Detector integration, LHC integration, installation. To work closely also with ATLAS TC. – 1.0 FTE of a good onsite Technician with experience in UHV work and electrical work: RP Station assembly, Detector integration, installation (~50% from FD M&O B) – 0.2 FTE of offsite Mechanical Engineer/Designer for the Silicon Tracker (sensor cards and holder in pot) Not Urgent: – 0.2 FTE for 0.3 year of Mechanical Engineer/Designer for the Time-of-Flight (detector holder) Some of the above could be split: it would be very advantageous to have a local mechanical/UHV engineer in Prague to follow the RP Station production and Vortex Cooling at Vakuum Praha and at CTU. This same person might also work on the Si Tracker holder. Similar manpower required for 2016: Installation of AFP2+2 in Winter SD 2016/17 AFP Kick-Off 03FEB ME+EE: 1.5 FTE 2.ET+MT: 1.5 FTE 3.Students: 3.0 FTE